[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Jones, R (on the application of) v The Secretary of State for Business, Energy and Industrial Strategy [2017] EWHC 1111 (Admin) (16 May 2017) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2017/1111.html Cite as: [2017] EWHC 1111 (Admin) |
[New search] [Context] [View without highlighting] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT IN WALES
Llangefni, Anglesey |
||
B e f o r e :
____________________
R on the application of JOHN MARS JONES (on his own behalf and on behalf of the PYLON THE PRESSURE GROUP |
Claimant |
|
- and - |
||
THE SECRETARY OF STATE FOR BUSINESS, ENERGY AND INDUSTRIAL STRATEGY |
Defendant |
____________________
Mr Richard Moules (instructed by Government Legal Department) for the Defendant
Mr Mark Westmorland Smith (instructed by Pinsent Masons LLP) for the First Interested Party
The second and third interested parties did not appear and were not represented
Hearing dates:10 and 11 April 2017
____________________
Crown Copyright ©
THE HONOURABLE MR JUSTICE LEWIS:
INTRODUCTION
THE LEGAL FRAMEWORK
The Legislative Framework
"1. The acquisition of land, compulsorily or by agreement.
2. The creation, suspension or extinguishment of, or interference with interests in or rights over land (including rights of navigation over water), compulsorily or by agreement.
…..
"36. The payment of compensation."
The Relevant National Policy Statements.
"3.7.10 In the light of the above, there is an urgent need for new electricity
transmission and distribution infrastructure (and in particular for new lines of
132 kV and above) to be provided. The [Secretary of State] should consider that
the need for any given proposed new connection or reinforcement has been
demonstrated if it represents an efficient and economical means of
connecting a new generating station to the transmission or distribution
network, or reinforcing the network to ensure that it is sufficiently resilient
and has sufficient capacity (in the light of any performance standards set by
Ofgem) to supply current or anticipated future levels of demand. However, in
most cases, there will be more than one technological approach by which it
is possible to make such a connection or reinforce the network (for example,
by overhead line or underground cable) and the costs and benefits of these
alternatives should be properly considered as set out in EN-5 (in particular
section 2.8) before any overhead line proposal is consented."
"Given the level and urgency of need for infrastructure of the types covered by the energy NPSs set out in Part 3 of this NPS, the [Secretary of State] should start with a presumption in favour of granting consent to applications for energy NSIPs. That presumption applies unless any more specific and relevant policies set out in the relevant NPSs clearly indicate that consent should be refused."
"5.8.12 In considering the impact of a proposed development on any heritage
assets, the [Secretary of State] should take into account the particular nature of the significance of the heritage assets and the value that they hold for this and
future generations. This understanding should be used to avoid or minimise
conflict between conservation of that significance and proposals for
development.
"5.8.13 The [Secretary of State] should take into account the desirability of sustaining and, where appropriate, enhancing the significance of heritage assets, the contribution of their settings and the positive contribution they can make to sustainable communities and economic vitality122. The [Secretary of State] should take into account the desirability of new development making a positive contribution to the character and local distinctiveness of the historic environment. The consideration of design should include scale, height, massing, alignment, materials and use. The [Secretary of State] should have regard to any relevant local authority development plans or local impact report on the proposed development in respect of the factors set out in footnote 122.
"5.8.14 There should be a presumption in favour of the conservation of designated heritage assets and the more significant the designated heritage asset, the greater the presumption in favour of its conservation should be. Once lost
heritage assets cannot be replaced and their loss has a cultural, environmental, economic and social impact. Significance can be harmed or lost through alteration or destruction of the heritage asset or development within its setting. Loss affecting any designated heritage asset should require clear and convincing justification. Substantial harm to or loss of a grade II listed building park or garden should be exceptional. Substantial harm to or loss of designated assets of the highest significance, including Scheduled Monuments; registered battlefields; grade I and II* listed buildings; grade I and II* registered parks and gardens; and World Heritage Sites, should be wholly exceptional.
"5.8.15 Any harmful impact on the significance of a designated heritage asset should be weighed against the public benefit of development, recognising that the greater the harm to the significance of the heritage asset the greater the
justification will be needed for any loss. Where the application will lead to
substantial harm to or total loss of significance of a designated heritage
asset the [Secretary of State] should refuse consent unless it can be demonstrated that the substantial harm to or loss of significance is necessary in order to deliver
substantial public benefits that outweigh that loss or harm.
…..
"5.8.18. When considering applications for development affecting the setting of a designated heritage asset, the Secretary of State should treat favourably applications that preserve those elements of the setting that make a positive contribution to, or better reveal the significance of, the asset. When considering applications that do not do this, the Secretary of State should weigh any negative effects against the wider benefits of the application. The greater the negative impact on the significance of the designated heritage asset, the greater the benefits that will be needed to justify approval."
"new above ground electricity lines, whether supported by lattice steel
towers/pylons or wooden poles, can give rise to adverse landscape and visual
impacts, dependent upon their scale, siting, degree of screening and the nature of
the landscape and local environment through which they are routed. For the most
part these impacts can be mitigated, however at particularly sensitive locations
the potential adverse landscape and visual impacts of an overhead line proposal
may make it unacceptable in planning terms, taking account of the specific local
environment and context."
"Where possible, applicants should follow the principles below in designing
the route of their overhead line proposals and it will be for applicants to offer
constructive proposals for additional mitigation of the proposed overhead
line. While proposed underground lines do not require development
consent under the Planning Act 2008, wherever the nature or proposed
route of an overhead line proposal makes it likely that its visual impact
will be particularly significant, the applicant should have given appropriate
consideration to the potential costs and benefits of other feasible means
of connection or reinforcement, including underground and sub-sea cables
where appropriate. The ES should set out details of how consideration has
been given to undergrounding or sub-sea cables as a way of mitigating
such impacts, including, where these have not been adopted on grounds of
additional cost, how the costs of mitigation have been calculated."
"Undergrounding
"2.8.8 Paragraph 3.7.10 of EN-1 sets out the need for new electricity lines of
132kV and above, including overhead lines. Although Government expects
that fulfilling this need through the development of overhead lines will often
be appropriate, it recognises that there will be cases where this is not so.
Where there are serious concerns about the potential adverse landscape
and visual effects of a proposed overhead line, the [Secretary of State] will have to balance these against other relevant factors, including the need for the proposed infrastructure, the availability and cost of alternative sites and routes and methods of installation (including undergrounding).
"2.8.9 The impacts and costs of both overhead and underground options vary
considerably between individual projects (both in absolute and relative
terms). Therefore, each project should be assessed individually on the basis of
its specific circumstances and taking account of the fact that Government
has not laid down any general rule about when an overhead line should be
considered unacceptable. The Secretary of State should, however only refuse consent for overhead line proposals in favour of an underground or sub-sea line if it is satisfied that the benefits from the non-overhead line alternative will clearly outweigh any extra economic, social and environmental impacts and the
technical difficulties are surmountable….."
THE FACTS
The Application
The Examination of the Application
The Report of the Panel
"4.5.93 The Panel considers that the information provided by the Applicant in relation to comparative costs contains sufficient detail which is realistic and credible. The costs report identifies that undergrounding would be approximately double the cost of the overhead line. For a 25 year connection this would equate to approximately an additional £16.6m. The Panel also accepts the Applicant's reasoning for the choice of underground route for cables between Clocaenog Forest and St Asaph, and in doing so considers that the underground route, following roads and road verges would not have any unsurmountable environmental, archaeological or social impacts and could be completed in a year.
4.5.94 The Panel accepts that undergrounding sections of the development, for example past Berain and under the A543, would require a set of terminal poles at either end of the underground section. The ES did not consider the environmental effects in relation to the additional sets of terminal poles and so they were not part of the proposed development. Undergrounding the development past Berain, or in other locations along the route, cannot therefore be considered in relation to the proposal that is before the Examination.
"4.5.95 In section 5.2 of this report, concerning landscape and visual impact matters, the Panel concludes that the Applicant's approach to the Holford Rules and consideration of alternatives is proportionate. The Panel has given consideration to the EN-5 requirement in relation to whether serious concerns had been raised regarding landscape and visual impact. It concludes that serious concerns had been raised by IPs and then went on to consider the need for the development and the effects it would have on the landscape and visual receptors against the tests of EN-5. It concludes that the balance of benefits of the underground alternative would not clearly outweigh the extra economic costs. Report Section 5.1 concludes that there are no reasons relating to biodiversity effects from the proposed development that would prevent the DCO from being made, provided the proposed environmental surveys and mitigation are delivered. In relation to historic environment, the Panel has given specific consideration to the prospect of undergrounding sections of the route in the vicinity of Berain, as well as through the un-designated historic parkland of Eriviat Hall, but reached the conclusion, having regard to various factors, including costs associated with the alternative, that undergrounding would not be justified at these locations.
"4.5.96 The Panel has borne in mind that from a policy perspective, EN1 does not consider any general requirement to consider alternatives or to establish whether the proposed development is the best option. The Panel has no doubt that the proposed development represents an efficient and economical means of connecting the remaining wind farms to the electricity transmission and distribution network to assist in supplying current and future levels of demand."
"5.2.100. The additional costs of undergrounding are considered and concluded upon in report Section 4.5 above. The Panel accepts that an underground cable route would be technically feasible and deliverable, but it is not satisfied that the benefits of such an option would clearly outweigh the additional costs burden.
5.2.101 Report Section 4.5 also provides details in relation to the environmental and archaeological consequences of undergrounding the development and concludes that the underground option would be technically feasible as it would be installed in road margins and verges. The Panel considers therefore, that it would be unlikely to experience any significant unknown archaeological interests and would be unlikely to have significant environmental impacts.
5.2.102 The Panel concludes that moderate (and therefore significant) adverse effects would arise in relation to landscape and visual impact, from the proposed development. However, the Panel finds that the adverse landscape and visual impact effects would not lead to a level of harm which sufficient to outweigh the urgent and national need for the development. The Panel also concludes that the balance of benefits from undergrounding the development would not clearly outweigh the extra economic impacts that would be incurred."
"5.4.125 The Panel has taken into consideration all of the documents and other representations from the Applicant and the IPs that commented on the impact that the development would have on the setting of Berain. In addition, the Panel viewed the location and setting on various site inspections.
"5.4.126 The Panel has considered the impacts of the proposed development on the setting of Berain listed buildings. In so doing, it has taken into account national policy in EN-1, section 5.8 and considers that the setting of Berain has a heritage significance that merits consideration. It considers that, in relation to paragraph 5.8.13 of EN-1, the proposed development would not enhance the significance of the of the heritage asset, the contribution of the setting or assist in making a positive contribution to sustainable communities and economic viability.
"5.4.127 The two tests in EN-1, section 5.8, in relation to the impact upon the listed buildings at Berain and their settings are whether the proposed development would lead to substantial harm, and if so, whether the proposed development is wholly exceptional development.
"5.4.128 The Panel considers that, in view of its proposed location, height, scale and materials that would be used, and distance away from the listed buildings at Berain, the double wood pole line would not cause substantial harm or loss to the buildings themselves or their setting. The fact that the wood pole line would be decommissioned after 30 years assists the Panel in coming to the conclusion that whilst the impact of the development on the setting of Berain would be moderate and therefore significant for its life, 30 years in the life of the listed buildings would not be a substantial proportion of their life. The Panel also concludes that a moderate or significant impact on the setting of Berain for the duration of the development is not substantial harm.
"5.4.129 If the Panel had concluded that the harm to the setting of the listed buildings at Berain would give rise to substantial harm or loss, then the second test in EN-1, paragraph 5.8.14, that the development should be wholly exceptional, would also fail. Had this situation occurred the Panel would have concluded that the development should be undergrounded. For this development however, as the first part of the EN-1 test in relation to the setting of the listed buildings at Berain, the Panel concludes that the development would not cause substantial harm or loss to the listed buildings or their setting. Therefore, the Panel concludes that there is no justification, in relation to the listed buildings at Berain and their setting, for it to recommend that Secretary of State should refuse the development in favour of an underground alternative.
"5.4.130 In coming to these conclusions, the Panel has had regard to the desirability of preserving the listed buildings and their setting and the features of special architectural and historic interest which they possess in accordance with Welsh policy as contained in paragraph 6.1.1 of PPW 8."
"5.4.135 The harm identified by the IPs and the Panel in relation to heritage assets and historic environment has been considered against EN-1 policy. The Panel concludes that there are no historic environment reasons (including the setting of listed buildings), which would lead the Panel to conclude that the proposed development should be refused in favour of an underground alternative. In coming to this conclusion the Panel has had regard to the enjoyment of the heritage assets and their settings by owners, their guests and visitors to the locality and Regulation 3 of the Infrastructure Planning (Decisions) Regulations 2010."
"7.6.1 The legal and policy context for the Examination of the application has already been set out in Chapters 3 and 4 of this report. This has provided a framework for the Panel's subsequent findings and conclusions.
"7.6.2 These conclusions apply equally to both option A and option B, unless otherwise stated. However, the Panel has considered and concluded upon option A and option B in report Section 5.15 where it concludes that, for various reasons, option B is preferred over option A.
"7.6.3 Having regard to the overarching national policy statement for energy (EN-1), paragraph 4.1.2, and the Panel's findings in relation to need and alternatives, it starts with a presumption in favour of granting consent for the Application. The Panel has considered and applied, the more specific and relevant policies set out in EN-1 and National Policy Statement for Electricity Networks Infrastructure (EN-5) in report Chapters 4 and 5. There are no other national policy statement policies that clearly indicate, that in the case of the proposed development, the DCO should not be made in favour of an alternative (underground or single wood pole) proposal.
"7.6.4 The Panel has taken into consideration the potential benefits of the proposed development, primarily its contribution to meeting the needs for energy infrastructure to connect wind farms in north Wales to the electricity network.
"7.6.5 The Panel has concluded upon the various potential adverse effects of the proposed development during construction, operation and decommissioning. It has given careful consideration to the impacts on residential properties, listed buildings, farming interests and other commercial interests along the proposed route. The Panel has weighed the potential adverse impacts that would arise from the proposed development against the benefits of the scheme.
7.6.6 The Panel has weighed in the balance, the potential harm to the setting of the listed buildings at Berain and the historic parkland at Eriviat Hall, the latter could be considered by Cadw for inclusion in the Welsh register of historic parks and gardens.
"7.6.7 The Panel has also taken into account PPW 8 which has a policy presumption against the loss of any BMV land. The Panel accepts that the loss of 2.5ha of BMV land would be contrary to Welsh policy in PPW 8, but concludes that as the route of the development would be restored when the development would be decommissioned, it would not therefore be a permanent loss.
"7.6.8 The Panel has considered alternative routes and alternative solutions (i.e. undergrounding and single poles) in report Section 4.5. Whilst other overground routes would have been technically possible, many crossed land with nationally important environmental designations. All other overhead line routes would have been significantly longer than the proposed development. The Panel concludes that the need for the development is sufficient to outweigh the PPW 8 policy constraint in relation to BMV land and considers that agricultural land classification has been given due weight within the Examination.
"7.6.9 During the course of the Examination it was evident to the Panel that there were no issues raised in relation to persons who share a relevant protected characteristic and persons who do not.
"7.6.10 Having regard to EN-1, paragraph 4.1.3, the Panel finds it necessary to weigh in the overall balance the adverse impacts of the development against its benefits. The Panel has assessed the potential adverse impacts, including any long term and cumulative impacts. It has taken into account the mitigation proposed, and in some instances, has proposed additional measures within the Panel's recommended draft DCO (Appendix E) to assist in minimising identified adverse impacts that would arise from the development
"7.6.11 These are the conclusions that the Panel has reached for option B. It has identified in report Section 5.15 that on many issues there is no difference in impacts on nearby receptors between option A and option B. However, having regard to the effect of option A on the farming community and a residential receptor, the Panel concludes that there are strong reasons for concluding that option B is preferred over option A. In the even that the Secretary of State disagrees with this view, and concludes that option A should be preferred, then the additional impacts of the proposed development upon the farming community and residential receptors would need to be weighed in for overall balance. Although the Panel has expressed its preference for option B, it does not consider that additional impacts associated with option A would be sufficient to alter the overall balance of the case.
"7.6.12 The Panel concludes, that for the reasons set out, and incorporating the changes proposed, that development consent should be granted, as set out in the Panel's recommended draft DCO in Appendix E.".
The Decision of the Defendant
"30. The Secretary of State notes that CCBC had made representations to the ExA requesting the two parts of the Development are undergrounded., namely at the crossing under the A543 due to views towards Elwy and Aled Valleys Special Landscape Areas and at the area around Berain (a cluster of two Grade II* and two Grade II listed buildings in a farmstead) [ER 4.5.47 and 4.5.55]. In response, the Applicant had stated the view that the impacts of the Development at two locations identified by CCBC would not trigger the need for undergrounding of the electric line, as the landscape and visual impact tests in EN-5 of serious concern, and the historic environment tests of EN-1 of substantial harm had not been met [ER 4.5.57]. The Secretary of State's consideration of the landscape and visual impacts tests in EN-5 of serious concern and the historic environment tests in EN-1 of substantial harm, are set out below.
"31. The Secretary of State has had regard to the comments of ExA set out in Chapter 4.5 and Chapter 10 of the Report, and in particular the conclusions set out regarding the consideration of alternative route options and undergrounding. The Secretary of State notes the ExA's conclusions and reasons for recommending that there are no policy or legal requirements that consent be refused for the Development (Option A or Option B) in favour of another alternative (partial or full undergrounding) and agrees with the ExA that the Development, including the overhead line, should therefore be granted consent."
"48. The Secretary of State has had regard to the comments of the ExA set out in Chapter 5.2 and Chapter 10 of the Report, and in particular the conclusions set out regarding the consideration of "serious concerns" in relation to landscape and visual impact and the test of EN-5. The Secretary of State notes the ExA's conclusion that moderate (and therefore significant) adverse effects would arise in relation to landscape and visual impact from the Development [ER 5.2.102], and agrees with this conclusion. However, the Secretary of State agrees with ExA's conclusion that the adverse and visual impact effects would not lead to a level of harm which is sufficient to outweigh the need for the Development [ER 5.2.102] and is not satisfied that the benefits of undergrounding the connection would clearly outweigh the extra economic impacts. The Secretary of State agrees with the ExA's conclusion that the requirements of EN-1 and EN-5 have been met and agrees with the ExA's recommendation that there are no reasons on landscape and visual impact grounds not to make the Order."
"52. The Secretary of State notes that Berain is a cluster of Grade II* and two Grade II listed buildings in a farmstead and that CCBC expressed concern throughout the Examination that the Development would have significant major impact on the setting of Berain [ER 5.4.54 and 5.4.72] and contended that there was an overriding case for undergrounding [ER 5.4.54 and 5.4.63]. The Secretary of State notes that whilst Cadw had advised ExA that it was likely that the Development would have a harmful visual impact on the setting of the listed buildings at Berain [ER 5.2.60 and 5.4.67], this view had been informed based on limited photographic and written evidence, rather than a site visit [ER 5.4.68]. The Secretary of State notes that the ExA agreed with the Applicant that the impact of the Development on the setting of Berain would be moderate and therefore significant, but notes that changes and the presence of man-made features are considerably greater within the vicinity of Berain compared to its wider setting [ER 5.4.118]. On this basis, the ExA concluded that when applying the tests in EN-1, in relation to balancing the need for development with harm to heritage assets, the double wood pole line would not cause substantial harm or loss to the listed buildings at Berain [ER 5.4.128]. The Secretary of State has considered ExA's reasons and recommendation and agrees that the Development would not lead to substantial harm.
"53. The Secretary of State notes that the ExA concluded that the concerns about longevity of the Development and the long term impacts upon heritage assets were addressed by the Applicant providing a requirement for the expiry of the development consent (Requirement 19 in the Order), so that the consent expires 30 years after the date that the Order is made [ER 5.4.103]."
"For the reasons set out in this letter, the Secretary of State considers that there is a compelling case for granting development consent. Given the policy as set out in the relevant National Policy Statements referred to above, the Secretary of State considers that the case is not outweighed by potential adverse local impacts of the Development, as mitigated by the proposed terms of the Order, and that granting consent would be consistent with EN-1 and EN-5".
The Order
"3.— Development consent etc. granted by the Order
(1) The undertaker is granted development consent for the authorised development, as set out in Schedule 1 (authorised development), subject to the provisions of this Order including the Requirements set out in Schedule 2 (Requirements)."
"18.— Compulsory acquisition of rights
(1) Subject to article 19, the undertaker may create and acquire compulsorily the rights over the Order land and impose the restrictions affecting the Order land described in the book of reference and shown on the land plans."
"23. Private rights
"(1) Subject to the provisions of this article, all private rights and restrictive covenants over land subject to the compulsory creation and acquisition of rights or the imposition of restrictions under this Order are suspended and unenforceable or, where so notified by the undertaker to the person with the benefit of such private rights or restrictive covenant, extinguished in so far as in either case their continuance would be inconsistent with the exercise of the right created and acquired or the burden of the restriction imposed—
(a) as from the date of creation and acquisition of the right or the benefit of the restriction by the undertaker, whether compulsorily or by agreement, or
(b) on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act (power of entry) in pursuance of the right,
whichever is the earliest.
"(2) Subject to the provisions of this article, all private rights and restrictive covenants over Order land owned by the undertaker or in which the undertaker has the benefit of an easement are extinguished on commencement of any activity authorised by this Order which would otherwise interfere with or breach such rights or restrictive covenants.
"(3) Subject to the provisions of this article, all private rights and restrictive covenants over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land and so far as their continuance would be inconsistent with the exercise of the temporary possession of that land.
"(4) Any person who suffers loss by the extinguishment or suspension of any private right or restrictive covenant under this Order is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
…..
"(8) Reference in this article to private rights and restrictive covenants over land includes any trust, incident, easement, wayleave, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including natural right to support and personal covenants."
THE ISSUES AND GENERAL APPROACH
(1) Did the Defendant misinterpret policy EN-1 in that he considered that it was only necessary to consider if the proposed development would cause substantial harm to the setting of Berain and failed to consider the presumption in favour of the conservation of designated heritage assets and failed to weigh the harmful impact on the significant heritage assets at Berain against the public benefit of the development as required in particular by paragraph 5.8.15 of EN-1?
(2) Given that the Defendant accepted that there were serious concerns over the landscape and visual impacts of the development, did the Defendant consider, and have available to him the necessary information to assess the alternative of partial undergrounding, that is placing the electricity line underground in the vicinity of Berain, having regard in particular to paragraph 2.8.4 of EN-5 and, in addition, did he have regard to that matter when considering the impact of the proposal on the setting of the listed buildings at Berain?
(3) Did the Defendant give adequate and intelligible reasons for his conclusions on the application of the relevant policies in EN-1 and EN-5?
(4) Did the Defendant give adequate reasons for providing a power in Article 23 of the Order to extinguish private rights permanently when consent for the development itself would expire after 30 years?
"36 The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the "principal important controversial issues", disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision-maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision."
THE FIRST ISSUE – THE PROPER INTERPRETATION OF THE RELEVANT POLICY
THE SECOND ISSUE – PLACING THE LINE PARTIALLY UNDERGROUND
THE THIRD ISSUE – THE ADEQUACY OF THE REASONS IN RELATION TO
THE NATIONAL POLICY STATEMENTS
THE FOURTH ISSUE – REASONS FOR ARTICLE 23 OF THE ORDER
CONCLUSION