[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Vrinera Marine Company Ltd. v Eastern Rich Operations Inc [2004] EWHC 1752 (Comm) (21 July 2004) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2004/1752.html Cite as: [2004] 2 Lloyd's Rep 465, [2004] EWHC 1752 (Comm), [2004] 2 CLC 1148 |
[New search] [Context] [View without highlighting] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
COMMERCIAL COURT
IN THE MATTER OF THE ARBITRATION ACT 1996
AND
IN THE MATTER OF AN ARBITRATION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
IN THE MATTER OF THE ARBITRATION ACT 1996 AND IN THE MATTER OF AN ARBITRATION VRINERA MARINE COMPANY LIMITED |
Claimant/Owners |
|
- and - |
||
EASTERN RICH OPERATIONS INCORPORATED |
Defendant/Charterers |
____________________
Mr J. Turner (instructed by DLA LLP) for the Defendant/Charterers
Hearing date: 16 July 2004
____________________
Crown Copyright ©
The Hon. Mr Justice Langley:
The Appeal
The Claim in the Arbitration.
The Award.
"The dispute in this case has always been whether, as the Owners contended, the pattern of bottom set-up and the structural collapse seen in dry dock in Nantong in late 1999 was brought about with an appreciable external force being applied to the hull (i.e. a grounding ….) or, as the Charterers said, because of a catastrophic failure of the under frame rings in the lower part of the side ballast tanks …due to unchecked corrosion."
In the following paragraph the Tribunal described the matters raised by ERO as "the obverse of the Owners' claim for a breach of the warranty of safety".
"39. The Owners are quite right that claims to recover costs as damages in chain arbitrations usually fail, coming to grief on the rocks of causation and remoteness. However, here we agreed with the Charterers that, whilst in most cases it will be appropriate simply to protect time by commencing arbitration proceedings and then awaiting the outcome of those arbitration proceedings before deciding whether to pursue an indemnity claim down the line, here that was not (in practice) an option open to them. They plainly took the view earlier this year that it would be necessary to bring Bao Steel into the case in order to obtain (and deploy in this arbitration) evidence that would enable them to defend the Owners' claim, a claim that they always maintained was spurious and as to which they were proved right. Accordingly, it seemed to us that their conduct in actively pursuing the arbitration against Bao Steel and applying for the sub-arbitration to be heard concurrently with this arbitration so that the evidence obtained in the former could be deployed in the latter was a reasonable course of action to adopt and did not (contrary to some cases involving chain arbitrations) break the chain of causation between the breach and the damage claimed.
40. Important (indeed crucial) evidence was obtained from Bao Steel which assisted the Charterers case and which would not, but for the active prosecution of the sub-arbitration, have been available to them. The hazards for an intermediate charterer of fighting safe port/berth claims up and down the line in separate, non-concurrent arbitrations are well known. Had the Owners succeeded and the Charterers then sought to pass on that liability in a sub-arbitration, they might well have been met with new (and for them fatal) evidence which, had it been available earlier, would have enabled them to defeat the original claim.
41. We also agreed with the Charterers that what happened was a foreseeable result of the Owners' breach and the damage to the vessel consequent thereon."
The Issue.
"Liability in costs on the part of [ERO] to a sub-charterer would have been within the reasonable contemplation of the parties at the time of concluding the charterparty as a not unlikely result of the owners breaching the charter by delivering the vessel in an unseaworthy state."
The Principles to be Applied.
"On an appeal under this section the court may by order-
(a) confirm the award,
(b) vary the award,
(c) remit the award to the tribunal, in whole or in part, for reconsideration in the light of the court's determination, or
(d) set aside the award in whole or in part.
The court shall not exercise its power to set aside an award, in whole or in part, unless it is satisfied that it would be inappropriate to remit the matters in question to the tribunal for reconsideration."
Application of the Principles.