[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Azimut-Benetti Spa (Benetti Division) v Healey [2010] EWHC 2234 (Comm) (03 September 2010) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2010/2234.html Cite as: 132 Con LR 113, [2010] CILL 2921, [2010] TCLR 7, [2010] EWHC 2234 (Comm) |
[New search] [Context] [View without highlighting] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AZIMUT-BENETTI SpA (Benetti Division) |
Claimant |
|
- and - |
||
DARRELL MARCUS HEALEY |
Defendant |
____________________
Mr N.G. Casey (instructed by Clyde & Co LLP) for the Defendant
Hearing date: 9th August 2010
____________________
Crown Copyright ©
MR JUSTICE BLAIR:
"16. Termination by Builder
16.1 In addition to such rights as it may have at general law the Builder may suspend construction of the Yacht and/or terminate this Contract at any time by written notice to the Buyer:
(a) if the Buyer fails to pay any sum due and owing under this Contract within forty-five days after the due date;
...
16.3 Upon lawful termination of this Contract by the Builder it will be entitled to retain out of the payments made by the Buyer and/or recover from the Buyer an amount equal to 20% of the Contract Price by way of liquidated damages as compensation for its estimated losses (including agreed loss of profit) and subject to that retention the Builder will promptly return the balance of sums received from the Buyer together with the Buyer's Supplies if not yet installed in the Yacht."
"Lord Dunedin in the Dunlop case makes the point that, although the issue is one of construction, the court is not confined to the terms of the agreement and may look at the "inherent circumstances of each particular contract, judged of as at the time of the making of the contract, not at the time of the breach …" (at page 87). In my judgment, the inherent circumstances to which the court may have regard extend beyond those which may be adduced in evidence for the purposes of determining the true interpretation of the agreement under the well known test in the Investors' Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896. But the purpose of adducing that evidence is not so that the parties can demonstrate that they agreed to opt out of the remedies regime provided by the common law but rather that the reasons that they had for doing so constitute adequate justification for the discrepancy between the contractual measure of damages and that provided by the common law."
This passage was applied in General Trading Company (Holdings) Ltd v Richmond Corporation Ltd [2008] 2 Lloyd's Rep 475 at [124] (Beatson J), and the defendant accepts this approach for the purpose of this hearing. The argument between the parties has been what, if anything, the negotiations demonstrate as regards the parties' reasons for agreeing clause 16.3 as contemplated in this passage. I should say that I accept the defendant's submission that the mere assertion by or on behalf of the builder that the clause was a genuine pre-estimate of damage does not in itself advance matters.
"20% is a genuine pre-estimate of the Builder's loss and the Buyer needs to understand that this clause provides, not just compensation for the Builder, but also an immediate refund of the rest of the Buyer's money.
The alternative, should the current clause be unacceptable, is to revert to the more conventional model whereby the Builder completes and sells Yacht to someone else; realises its actual loss; and then accounts back to the Buyer for any excess remaining. In this scenario the Builder will retain the Buyer's instalments for a very long time, particularly if there has to be an arbitration."
"As already discussed with Sergei in the past we once again stand by our figure of 20% as this is the minimum it would cost Benetti to resell the ship in case of the client terminating the contract. On top of the cost of resale we would have all of the costs due to borrowing the money from the bank, depreciation of the yacht and depreciation of the yacht due to the fact that it is tailored on [a]n other client i.e. modifications to apply to the boat to be resold. This … is a very firm point in our contracts."
"Not agreed. If preferred we can revert to a more traditional clause whereby, on termination of the Contract, the Builder completes the yacht, sells to someone else to realise its actual loss, and then accounts to the Buyer for any surplus remaining. You need to recognise, however, that in this scenario there will be no accounting to the Buyer until after the yacht has been sold, or in a disputed case, until after an arbitration award has been published. The clause as it stands allows the Buyer to recover his instalments immediately, even in a disputed case, and subject only to the agreed liquidated damages, but Benetti are not willing to take any greater risk of loss and if the Buyer is unwilling to agree the clause as it is then we may have to revert to the more traditional solution. I should add that we have had this discussion on several occasions with buyers – after consideration they invariably prefer the clause as it is."
The parties' contentions on the penalty point
The law on penalties
"The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the essence of liquidated damages is a genuine covenanted pre-estimate of damage ... The question whether a sum stipulated is penalty or liquidated damages is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged of as at the time of the making of the contract, not as at the time of the breach... It will be held to be penalty if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach."
"... whether a provision is to be treated as a penalty is a matter of construction to be resolved by asking whether at the time the contract was entered into the predominant contractual function of the provision was to deter a party from breaking the contract or to compensate the innocent party for breach. That the contractual function is deterrent rather than compensatory can be deduced by comparing the amount that would be payable on breach with the loss that might be sustained if breach occurred."
Discussion and conclusion on penalty point
The claimant's alternative case for payment of the first instalment
"When a party to a simple contract, upon a breach by the other contracting party of a condition of the contract, elects to treat the contract as no longer binding upon him, the contract is not rescinded as from the beginning. Both parties are discharged from further performance of the contract, but rights are not divested or discharged which have already been unconditionally acquired. Rights and obligations which arise from the partial execution of the contract and causes of action which have accrued from its breach alike continue unaffected."
This statement of principle was approved in Johnson v. Agnew [1980] A.C. 367, HL, at p.396, and referred to with approval in Hyundai itself by Lord Edmund Davies at p.1141F-H. Had I been in the defendant's favour on the penalty point therefore, I would nevertheless have held that there was no defence to the claim for the first instalment which had accrued prior to termination.
Conclusion