[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |||||||||
England and Wales High Court (Technology and Construction Court) Decisions |
||||||||||
PLEASE SUPPORT BAILII & FREE ACCESS TO LAW
To maintain its current level of service, BAILII urgently needs the support of its users.
Since you use the site, please consider making a donation to celebrate BAILII's 25 years of providing free access to law. No contribution is too small. If every visitor this month gives just £5, it will have a significant impact on BAILII's ability to continue providing this vital service.
Thank you for your support! | ||||||||||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Community Gateway Association Ltd v Beha Williams Norman Ltd [2011] EWHC 2994 (TCC) (21 November 2011) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2011/2994.html Cite as: [2011] EWHC 2994 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
COMMUNITY GATEWAY ASSOCIATION LIMITED |
Claimant |
|
- and - |
||
BEHA WILLIAMS NORMAN LIMITED |
Defendant |
____________________
Andrew Onslow QC, Neil Hext and David Thomas (instructed by Kennedys) for the Defendant
Hearing date: 11 November 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
Costs
"(a) conduct before, as well as during, the proceedings…
(b) whether it was reasonable for a party to raise, pursue or contest a particular allegation or issue;
(c) the manner in which the party has pursued or defended his case or particular allegation or issue…"
CPR Part 44.3 (6) gives to the Court a discretion to make a very wide range of costs orders including allowing only a proportion of costs, costs incurred from or until a certain date, costs relating only to a distinct part of the proceedings and interest on costs.
Permission to Appeal