![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Drax Energy Solutions Ltd v Wipro Ltd [2023] EWHC 1342 (TCC) (09 June 2023) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2023/1342.html Cite as: [2023] EWHC 1342 (TCC), 210 Con LR 80, [2023] BLR 537 |
||
[New search]
[Context
]
[View without highlighting]
[Printable PDF version]
[Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
B e f o r e :
____________________
DRAX ENERGY SOLUTIONS LIMITED(Formerly Haven Power Limited) |
Claimant |
|
| -and- |
||
| WIPRO LIMITED |
Defendant |
____________________
(instructed by Milbank LLP, Solicitors) for the Claimant
ALEX CHARLTON KC and DANIEL GOODKIN (instructed by Clyde & Co LLP, Solicitors)
for the Defendant
Hearing date: 9 February 2023
____________________
Crown Copyright ©
Drax
Energy Solutions Ltd ("
Drax")
and the Defendant, Wipro Ltd ("Wipro") dated 20 January 2017 ("the MSA").
Drax
issued proceedings against Wipro on 2 September 2021, and the main trial is due to commence on 1 October 2024, with a time estimate of 36 days.
Drax,
an energy supplier. The new IT system to be provided, based on Oracle software, included customer relationship management, billing and smart metering facilities for
Drax's
business.
(1) SOW 1-3 would be entered into on 17 January, 10 February and 10 March 2017 and they addressed the design, build, test and implementation of the Oracle-based software modules to include software licences for 5 years;
(2) SOW 4 would be entered into on 19 April 2017 for a 4-year period in respect of Application Management Services and a further 4 years for Data Centre Costs, Meter to Cash, and Oracle Cloud Application Maintenance Costs;
(3) SOW 5 would be entered into on 24 January 2017, for 5 years, for WAN Network Services;
(4) SOW 6 would be entered into on 19 April 2017 for a design for software encryption
and all of these comprised the "Planets" suite of programs.
(1) SOW1: £4.8 million;
(2) SOW2: £2.2 million;
(3) SOW3: £250,000; and
(4) SOW4: £858,000.
(1) Year 2: £840,404;
(2) Year 3: £992,404;
(3) Year 4: £983,404, and
(4) Year 5: £608,644.
Drax
alleges that it had to spend very large sums of money to render acceptable the deliverables provided by Wipro. In the end,
Drax
terminated the MSA on 7 August 2019 for what it says were repudiatory breaches on the part of Wipro.
Introduction
Drax's
claim and, critically, the amounts claimed. I should say at the outset that
Drax's
total quantified claim is for some £31 million. There is then a counterclaim by Wipro of around £10 million. The counterclaim includes £5.5 million by way of damages for wrongful termination, £1.28 million for prolongation costs, unpaid invoices of £1.5 million and termination claims of £2.4 million.
Drax
amounted to £4.9 million.
Drax
breaks down into 4 categories:
(1) Misrepresentation Claim;
(2) Quality Claims;
(3) Delay Claims; and
(4) Termination Claims.
Misrepresentation
Drax
alleges that, but for the representations which were false, it would not have entered into the MSA and the SOWs at all. It has therefore lost its entire net expenditure on the project being £31.7 million.
Quality Claims
Drax
over and above what it would have to have incurred in any event, in relation to dealing with Wipro's work product. In other words, it spent more than it should have done to make the work product contractually acceptable and useful. Those losses come to some £9.8 million.
Delay Claims
Termination Claims
Drax
would reasonably have incurred had the MSA been properly performed. This item is included in the £31.7 million claimed in respect of the Misrepresentation Claim.
Drax,
some other costs that might be described as "reliance expenditure" and then the costs listed under the second description of Quality and Delay Claim losses in the Schedule to the POC. These were the expected costs, assuming that the MSA had run its course but were now wasted due to its wrongful termination by Wipro. These amounted to £3.7 million in respect of quality and £827,278 in respect of Delay, making a total of just over £4.5 million.
Claims Analysis
Drax's
primary case on its claims, they are as follows, using round figures:
(1) Quality: £9.8 million;
(2) Delay: £9.7 million;
(3) Termination: £12 million; and
(4) Misrepresentation: £31 million.
Drax's
maximum quantified figures and any or all of them could be less, perhaps significantly less, even if the underlying liability is established.
"33. LIABILITY
33.1 Subject to clauses 33.5 and 33.6, the Supplier's liability to the Customer, whether in contract, tort (including negligence) for breach of statutory duty or otherwise, for loss or damage to tangible property arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to £20 million per event or series of connected events.
33.2 Subject to clauses 33.1, 33.3, 33.5 and 33.6, the Supplier's total liability to the Customer, whether in contract, tort (including negligence), for breach of statutory duty or otherwise, arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to an amount equivalent to 150% of the Charges paid or payable in the preceding twelve months from the date the claim first arose. If the claim arises in the first Contract Year then the amount shall be calculated as 150% of an estimate of the Charges paid and payable for a full twelve months.
33.3 The Supplier's total aggregate liability arising out of or in relation to this Agreement for any and all claims related to breach of any provision of clause 21 whether arising in contract (including under an indemnity), tort (including negligence), breach of statutory duty, laws or otherwise, shall in no event exceed 200% of the Charges paid or payable in the preceding twelve months from the date the claim first arose or £20m (whichever is greater).
33.4 Subject to clauses 33.5 and 33.6, the Customer's total liability to the Supplier, whether in contract, tort (including negligence), for breach of statutory duty or otherwise, arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to the Charges payable under this Agreement (including all Statements of Work) in respect of Services properly performed by the Supplier at the point the claim is made.
33.5 Subject to clause 33.6, neither party will be liable to the other party for any indirect, consequential or special loss including but not limited to any loss of profits or loss of goodwill arising out of, or in connection with, this Agreement or any Statement of Work.
33.6 Nothing in this Agreement or any Statement of Work shall exclude or limit:
33.6.1 either party's liability for death or personal injury caused by its (or its agent's or sub-contractor's) negligence or for fraud or fraudulent misrepresentation;
33.6.2 the Supplier's liability, whether categorised as direct or indirect losses, to the Customer arising out of a breach of clause 4.2.4 (Compliance with Laws), clause and/or where the Supplier has indemnified the Customer in clause 19 (IPR Indemnity), and/or arising out of a breach of clause 26 (Confidentiality and Announcements) and/or clause 37 (Anti corruption);
33.6.3 the Supplier's liability for wilful misconduct or abandonment; or
33.6.4 either party's liability that cannot, as a matter of law, be limited or excluded."
(1) Issue 1: On a true construction, does clause 33.2 of the MSA provide for a single aggregate cap which applies to the Defendant's liability for the Claimant's claim; or multiple caps with a separate financial limit applying to each of the Claimant's claims?
(2) Issue 2: If there are multiple caps, what are each of the Claimant's claims to which the cap applies?
Drax
says that if these preliminary issues are determined in its favour, the effect of the cap is to reduce Wipro's maximum possible liability in these proceedings down from £31.7m (see paragraphs 13 and 17 above) to around £23m. This is because, while the claims in respect of Quality and Delay would fall below the relevant caps for each, and those claims are worth £19.5m, there would be an applicable cap of £3.78m on the Termination Claims of £12 million (see paragraph 18 above).
Drax,
in summary, as follows:
(1) The charges payable in the first 12 months were, as we have seen, £7,671,118;
(2) 150% of that figure is £11,506,677;
(3) Rounded to £11.5 million, this is the maximum amount of loss for which Wipro can be made liable, in respect of all and any of the claims made against it;
(4) It follows that ifDrax
succeeded entirely, and in principle, Wipro was liable for £31.7 million of loss,
Drax
could only recover £11.5 million;
(5) To the extent necessary, Wipro also contends that the "claim" referred to in the Clause means the total liability established; or, alternatively, for the purposes of the Clause, there is only one claim which is the totality of the claims (if defined more narrowly) which succeeded; and
(6) In this regard, Wipro accepts and contends that for present purposes, the "claim" arose in the first contract year.
Drax
contends, first, that the £11.5 million figure is a limit which applies to each and every separate claim, assuming they all arose in the first year. It is not a single maximum applied to all claims.
Drax's
primary position is that a claim means "cause of action". On that footing, a relevant claim for present purposes could be each and every item in the Schedule to the POC which has a particular loss ascribed to it. That would entail 14 claims in respect of quality, 19 claims in respect of Delay and 23 claims in respect of Termination (assuming no overlap with the Quality and Delay Claims). The Misrepresentation Claims would be more than one since, on any view, different Representations are relied upon, which are said to be false.
Drax
did not go quite that far. In paragraph 5 (a) to (p) of its Further Information, dated 8 July 2022, it itemised:
(1) one claim for Misrepresentation;
(2) 9 claims in respect of Quality;
(3) 4 claims in respect of Delay;
(4) one claim for repudiatory breach, and
(5) one claim in respect of the Exit Plan.
Drax
has an alternative position on the meaning of "claim" which was the real focus of oral argument. As set out in paragraph 5 (q) – (t) of the Further Information, this is on the basis that the relevant claims were 4 in number, being the Misrepresentation Claim, the Quality Claims, the Delay Claims and the Termination Claims.
Drax
could only recover £11.5 million out of a maximum sum claimed here of £31 million. And as for the Termination Claims, these would also be affected by the Clause with an applicable cap of £3.78 million, as against a claim of around £12 million.
Contractual Interpretation Generally.
"i) The court construes the relevant words of a contract in their documentary, factual and commercial context, assessed in the light of (i) the natural and ordinary meaning of the provision being construed, (ii) any other relevant provisions of the contract being construed, (iii) the overall purpose of the provision being construed and the contract or order in which it is contained, (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party's intentions – see Arnold v. Britton [2015] UKSC 36 [2015] AC 1619 per Lord Neuberger PSC at paragraph 15 and the earlier cases he refers to in that paragraph;
ii) A court can only consider facts or circumstances known or reasonably available to both parties that existed at the time that the contract or order was made - see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 20;
iii) In arriving at the true meaning and effect of a contract or order, the departure point in most cases will be the language used by the parties because (a) the parties have control over the language they use in a contract or consent order and (b) the parties must have been specifically focussing on the issue covered by the disputed clause or clauses when agreeing the wording of that provision – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 17;
iv) Where the parties have used unambiguous language, the court must apply it – see Rainy Sky SA v. Kookmin Bank [2011] UKSC 50 [2011] 1 WLR 2900 per Lord Clarke JSC at paragraph 23;
v) Where the language used by the parties is unclear the court can properly depart from its natural meaning where the context suggests that an alternative meaning more accurately reflects what a reasonable person with the parties' actual and presumed knowledge would conclude the parties had meant by the language they used but that does not justify the court searching for drafting infelicities in order to facilitate a departure from the natural meaning of the language used – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 18;
vi) If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other – see Rainy Sky SA v. Kookmin Bank (ibid.) per Lord Clarke JSC at paragraph 2 - but commercial common sense is relevant only to the extent of how matters would have been perceived by reasonable people in the position of the parties, as at the date that the contract was made – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 19;
vii) In striking a balance between the indications given by the language and those arising contextually, the court must consider the quality of drafting of the clause and the agreement in which it appears – see Wood v. Capita Insurance Services Limited [2017] UKSC 24 per Lord Hodge JSC at paragraph 11. Sophisticated, complex agreements drafted by skilled professionals are likely to be interpreted principally by textual analysis unless a provision lacks clarity or is apparently illogical or incoherent– see Wood v. Capita Insurance Services Limited (ibid.) per Lord Hodge JSC at paragraph 13; and
viii) A court should not reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight, because it is not the function of a court when interpreting an agreement to relieve a party from a bad bargain - see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 20 and Wood v. Capita Insurance Services Limited (ibid.) per Lord Hodge JSC at paragraph 11."
Interpretation of clauses which exclude or limit liability
"106…a further reason for giving the word "negligence" its straightforward and ordinary legal meaning is that clear words are necessary before the court will hold that a contract has taken away valuable rights or remedies which one of the parties to it would have had at common law (or pursuant to statute).
107 The approach of the courts to the interpretation of exclusion clauses (including clauses limiting liability) in commercial contracts has changed markedly in the last 50 years. Two forces have been at work. One has been the impact of the Unfair Contract Terms Act 1977, which provided a direct means of controlling unreasonable exclusion clauses and removed the need for courts to resort to artificial rules of interpretation to get around them:… The second force has been the development of the modern approach in English law to contractual interpretation, with its emphasis on context and objective meaning and deprecation of special rules of interpretation encapsulated by Lord Hofmann's announcement in Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, 912 that "almost all the old intellectual baggage of legal interpretation has been discarded".
108. The modern view is accordingly to recognise that commercial parties are free to make their own bargains and allocate risks as they think fit, and that the task of the court is to interpret the words used fairly applying the ordinary methods of contractual interpretation. It also remains necessary, however, to recognise that a vital part of the setting in which parties contract is a framework of rights and obligations established by the common law (and often now codified in statute). These comprise duties imposed by the law of tort and also norms of commerce which have come to be recognised as ordinary incidents of particular types of contract or relationship and which often take the form of terms implied in the contract by law. Although its strength will vary according to the circumstances of the case, the court in construing the contract starts from the assumption that in the absence of clear words the parties did not intend the contract to derogate from these normal rights and obligations."
"18. In my judgment the underlying rationale for the principle that, if necessary to resolve ambiguity, exclusion clauses should be narrowly construed has nothing to do with the identification of the proferens, either of the document as a whole or of the clause in question. Nor is it a principle derived from an identification of the person seeking to rely upon it. Ambiguity in an exclusion clause may have to be resolved by a narrow construction because an exclusion clause cuts down or detracts from the ambit of some important obligation in a contract, or a remedy conferred by the general law such as (in the present case) an obligation to give effect to a contractual warranty by paying compensation for breach of it. The parties are not lightly to be taken to have intended to cut down the remedies which the law provides for breach of important contractual obligations without using clear words having that effect:…
19. This approach to exclusion clauses is not now regarded as a presumption, still less as a special rule justifying the giving of a strained meaning to a provision merely because it is an exclusion clause. Commercial parties are entitled to allocate between them the risks of something going wrong in their contractual relationship in any way they choose. Nor is it simply to be mechanistically applied wherever an ambiguity is identified in an exclusion clause. The court must still use all its tools of linguistic, contextual, purposive and common-sense analysis to discern what the clause really means. In the Seadrill Management case Moore-Bick [LJ] described the principle as, 'essentially one of common sense; parties do not normally give up valuable rights without making it clear that they intend to do so…
21. For those legal reasons I approach the issue as to the construction of clause 5.1 upon the basis that there remains a principle that an ambiguity in its meaning may have to be resolved by a preference for the narrower construction, if linguistic, contextual and purposive analysis do not disclose an answer to the question with sufficient clarity."
"The natural meaning of the language is by no means so clear as to preclude serious consideration of the commerciality or otherwise of rival interpretations or, for that matter, to preclude recourse to the principle that ambiguous exclusion clauses should be construed narrowly."
"(b) the aggregate liability of either party under the Contract for all Defaults, other than those
governed by sub-clause 8.1.2 (a) above, shall not exceed the amount stated in schedule G to be the
limit of such liability."
"…The aggregate liability of the Contractor in accordance with sub-clause 8.1.2 paragraph (b) shall not exceed:
9.2.1 for any claim arising in the first 12 months of the term of the Contract, the Total Contract Price as set out in section 1.1; or
9.2.2 for claims arising after the first 12 months of the Contract, the total Contract Charges paid in the 12 months prior to the date of that claim."
Introduction
Drax
was correct that a "claim" meant any cause of action (or at least those 16 enumerated in its primary case as set out in the Further Information) that would potentially allow for a larger amount to be claimed, taking the cap into account, as opposed to the position if the narrower and alternative definition of "claim" was correct.
Drax
treats the entire Misrepresentation and Termination Claims as each constituting only one claim (excluding the Exit Plan Claim for the moment) there is in practice not much difference between the effect of the two formulations on the facts of the case here. But since
Drax
has not abandoned its primary case on "claim" I will need to deal with it below.
Drax's
wider interpretation of "claim" is that it is not correct. In particular, the expression "claim" cannot here be simply equated with "cause of action". See paragraphs 98 to 107 below.
Drax
is the narrower one whereby there are 4 relevant claims only. Although, in its written submissions,
Drax
invited me to consider some other interpretation of "claim" which could operate if I was against
Drax
on the narrow interpretation too, I decline to do so. It seems to me that I should proceed on the basis of the actual position of the parties. Wipro's position, of course, is that (a) there is only one claim anyway but (b) even if not, the Clause imposes one single cap in relation to all claims, however described and however numerous - unless, of course, any of them fall within 33.1 or 33.3.
The Language of the Clause
Drax's
position on the meaning of the Clause (along with other matters). There is clearly force in that point.
Drax
then makes the point that those actual words were not used and they could have been. There is some force in this point, too.
Drax's.
Language of the other provisions
Drax
says that the above features of clause 33.2 and 33.3 support its position that the Clause does indeed provide for separate caps. It adds that clause 33.3 itself does not explicitly state that it is subject to, for example, clauses 33.5 and 33.6. I have little doubt that in fact it is, and the terms of those clauses are quite explicit. But
Drax's
point is that there would be no need to make an express reference in clause 33.3 to it being subject to the other clauses if, in effect, it should be looked at as a proviso to or, in effect, a sub-clause of, the Clause even if not expressed as such. All of that would then support the notion that Clause 33.3 does indeed operate as a limiting factor to what might otherwise be recoverable under the Clause, with its separate caps.
Drax's
interpretation, that expression would have to be construed differently in each provision. The linguistic tension resulting from that is heightened if Clause 33.3 is itself to be construed simply as a proviso to the Clause.
Drax
accepted that clause 33.1 can be seen as freestanding and not as some other proviso to the Clause. On that basis, although the words "shall be limited to" are used, in substance, the meaning here is that the relevant liability is "up to" £20 million per event. But if so, there is no reason not to view clause 33.3 in the same light. In other words, its wording does not necessarily imply that it is simply a proviso to the Clause on the footing that the clause 21 liabilities would be theoretically higher under the latter.
Drax's
interpretation of the Clause, especially where there is no explicit "per claim" form of words used therein.
Drax
has suggested.
"35.1.1 employers liability insurance for a maximum amount of cover of £10 million on a per occurrence and an annual aggregate basis;
35.1.2 professional indemnity insurance for a minimum amount of cover of £20 million on a per occurrence and an annual aggregate basis;
35.1.3 public liability insurance for a minimum amount of cover of £30 million on a per occurrence and an annual aggregate basis; and
35.1.4 product liability insurance for a minimum amount of cover of £30 million on a per occurrence and an annual aggregate basis."
Conclusions on the language used
Drax's
claimed interpretation is at least possible, though in my view wrong. I do not consider that the language is, ultimately, ambiguous, however. Compare the position in Nobahar where the issue turns on the meaning to be ascribed to the single word "becoming aware of the matter". That seems to me to be a different sort of interpretive problem than that arising here.
Commercial Considerations
Drax
submits that Wipro's interpretation would lead to some surprising results. In particular,
Drax
points out that the MSA contemplated not just the provision of the initial "Planets" suite of software over 5 years by Wipro under SOWs 1-5, but also potential further works which could give rise to further claims. That is, in theory, true because, as Schedule 10 made clear, while SOWs 1-5 fall under the Planets Programme, the parties also intended that the MSA could be used to order further SOWs not related to that programme. Indeed, one such SOW was the separate Insights SOW agreed on 18 September 2017, referred to above, and which was concerned with cyber-security and the dark web. All of this is reflected in the fact that under clause 2, there is in theory no limit to the length of the MSA, albeit that the Planets Programme itself was to be delivered and maintained over a 5 year period.
Drax
could themselves execute SOWs and benefit from the services provided by Wipro under that SOW. See, for example, the reference to
Drax
Retail in connection with SOW4 .1.
Drax
also says that, given the possibility of many claims going into the future if other projects are agreed, a gradually reducing single cap would not reflect the fact that later SOWs may be for much greater value, yet they could be "stuck with" a cap based on charges made in earlier years, if the first claim arose then. The maximum that could be claimed would be the £11.5 million but less if the claim arose later.
Drax
contends that there is really no business sense to Wipro's interpretation because a single cap would be inapposite where there could be (looking at the date when the MSA was made) so many potential claims over an indefinite period of time by more than one
Drax
entity.
Drax
alleges here, the project was proving or threatening to be a disaster within the first year, it was hardly likely to commission yet further work and indeed at some point, it would surely terminate. That, of course, is exactly what
Drax
did in 2019. It should also be pointed out that clause 29.3 provides a right of partial termination and clause 31 provides for step-in rights. So I do not think that these arguments raised by
Drax
show that Wipro's interpretation makes no business sense, or was commercially absurd or anything like that.
Drax
then points out that even on the basis that there are only 4 relevant claims, this means that on Wipro's interpretation they are still capped at one third of their potential value i.e. £11.5 million as opposed to £31 million. As a matter of arithmetic that is obviously true but it can hardly be said that £11.5 million is insignificant.
Drax
did not, in the end, protect itself in terms of claims to be made as much as it could or should have done. But that is not a reason for preferring its interpretation. And it is quite different from saying that the Clause makes no commercial sense.
Drax's
interpretation, and on the basis of the claims actually made, there could in theory be an overall cap of £132 million. This is based on the application of an £11.5 million limit for each of the claims set out in paragraph 5 (a)-(l) of the Further Information. And that would be absurdly high given the actual charges payable. I see that, but of course, I have rejected
Drax's
primary case on the meaning of "claim".
Drax's
secondary case, the overall cap for the claims other than termination would be £34.5 million being £11.5 million x 3. I am not persuaded that this would fall into the category of being absurd or making no business sense. Nor do I think that it can be said that this interpretation would mean that the cap would be so high as to be devoid of any real purpose (pace the judgment of O'Farrell J in Royal Devon at paragraph 86). But it does not matter. That is because there is no "business common-sense" point which can assist
Drax.
Triple Point Considerations
Conclusion on Preliminary Issue 1
Drax's
primary position is that "claim" here means "cause of action". I quite accept that a claim must certainly include at least one cause of action. But that does not answer the question here which is whether it is precisely coterminous with "cause of action".
"It is important to note that what makes a "a new claim" as defined in Section 35(2) is not the newness of the claim according to the type or quantum of remedy sought, but the newness of the cause of action which it involves. The formula employed in Section 35(2)(a) and (5) is "a claim involving … the addition or substitution of a new cause of action". And Order 20, Rule 5(5) refers not to a claim but to"[a]n amendment the effect of which is to add or substitute "a new cause of action". Diplock LJ's widely accepted definition of a cause of action in Letang v. Cooper [1965] 1 QB 232 , CA, at 242–3, as "simply a factual situation the existence of which entitles one party to obtain from the court a remedy against another person", as distinct from "a form of action … used as a convenient and succinct description of a particular category of factual situation", is of importance. It makes plain that a claim and a cause of action are not the same thing. It follows, as Mr Croally argued, that an originally pleaded "factual situation" may disclose more than one cause of action, although one of them may not be individually categorized as such or the subject of a claim for a separate remedy. However, as Mr Browne-Wilkinson submitted, it does not follow that a claim so categorizing it and/or seeking a remedy for it made for the first time by amendment is the addition of a new cause of action so as to render it a new claim."
Drax's
primary case, and as already noted, there would be a total cap of £132 million for the first 12 claims and then a further cap for the remainder. In fact, and on a strict application of the notion that "claim" means "cause of action" that is probably an understatement. For example, on the Misrepresentation Claim, there are 13 separate statements relied upon and they are said to give rise to 3 separate representations, with 6 different pleaded falsities. I have little doubt that, certainly for the purposes of amendment and section 35, a court would be likely to hold that there was clearly more than one cause of action involved and in my view, at least 3. That would give rise to a cap for the Misrepresentation Claims alone of £34.5 million.
Drax.
Drax
was correct on its interpretation of the Clause, this really would be a consequence which would make the Clause, if not devoid of all utility, then devoid of much of it.
Drax's
primary contention on the meaning of "claim".
Drax's
alternative description of the claims as being the 4 addressed above and indeed this description appears appropriate to me. The 4 claims do not (save in the case of the Misrepresentation Claim) overlap in terms of loss and they represent how
Drax
has pleaded out its claim. Further, and in a broad (not section 35) sense, they correspond to different causes of action or groups thereof, because they are plainly different, and rely on different sets of facts, and they correspond to a common-sense view of what claims are being made in this case.
Drax was correct and there was a separate cap for each claim. This exercise of identification cannot simply be avoided.
(1) The Misrepresentation Claim;
(2) The Quality Claim;
(3) The Delay Claim, and
(4) The Termination Claims
as set out in paragraph 5 (q)-(t) of the Further Information.