![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Balfour Beatty Regional Construction Ltd v Grove Developments Ltd [2016] EWCA Civ 990 (13 October 2016) URL: https://www.bailii.org/ew/cases/EWCA/Civ/2016/990.html Cite as: [2017] Bus LR 824, [2017] BLR 1, [2016] EWCA Civ 990, [2017] 1 All ER (Comm) 729, [2017] WLR 1893, [2017] 1 WLR 1893, 168 Con LR 1, [2016] WLR(D) 522 |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Buy ICLR report: [2017] 1 WLR 1893]
[View ICLR summary: [2016] WLR(D) 522]
[Buy ICLR report: [2017] Bus LR 824]
[Help]
ON APPEAL FROM Queen's Bench Division, Technology and Construction Court
Mr Justice Stuart-Smith
HT2015000412
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE JACKSON
and
LORD JUSTICE
VOS
____________________
Balfour Beatty Regional Construction Limited |
Defendant/ Appellant |
|
| - and - |
||
Grove Developments Limited |
Claimant/ Respondent |
____________________
Alexander Nissen QC & William Webb (instructed by Macfarlanes LLP) for the Claimant/Respondent
Hearing date : Wednesday 27th July 2016
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
Lord Justice Jackson :
| Part 1 Introduction | Paragraphs 2 - 7 |
| Part 2 The facts | Paragraphs 8 - 22 |
| Part 3 The present proceedings | Paragraphs 23 - 26 |
| Part 4 The appeal to the Court of Appeal | Paragraphs 27 - 29 |
Part 5 Did Balfour Beatty have any contractual entitlement to interim payments after valuation 23? |
Paragraphs 30 - 49 |
Part 6 Do the 1996 Act and the Scheme enable Balfour Beatty to recover interim payments after July 2015? |
Paragraphs 50 - 61 |
Part 7 Did the parties reach a separate agreement for interim payments after valuation 23? |
Paragraphs 62 - 66 |
| Part 8 Conclusion | Paragraph 67 |
Balfour
Beatty
Regional Construction Limited. I shall refer to the contractor at all stages as "BB". I shall refer to the employer,
Grove
Developments Limited, as "
Grove".
"109. Entitlement to stage payments.
(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless
(a) it is specified in the contract that the duration of the work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
(4) References in the following sections to a payment provided for by the contract include a payment byvirtue
of this section.
110.- Dates for payment.
(1) Every construction contract shall
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
(b) provide for a final date for payment in relation to any sum which becomes due.
The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
(3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) [ ], the relevant provisions of the Scheme for Construction Contracts apply."
Grove
engaged BB to design and construct a hotel and serviced apartments at Greenwich Peninsular in south east London. The contract was the JCT standard form Design and Build Contract 2011, subject to a number of bespoke amendments. It was dated 11th July 2013. The contract sum (subject to adjustment in accordance with the contract provisions) was £121,059,632.00.
"Issue and amount of Interim Payments
4.7
.1 Interim Payments shall be made by the Employer to the Contractor in accordance with section 4 and whichever of Alternative A (Stage Payments) or Alternative B (Periodic Payments) is stated in the Contract Particulars to apply.
.2 The sum due as an Interim Payment shall be an amount equal to the GrossValuation
under clause 4.13 where Alternative A applies, or clause 4.14 where Alternative B applies, in either case less the aggregate of:
.1 any amount which may be deducted and retained by the Employer as provided in clauses 4.16 and 4.18 ('the Retention')
.2 the cumulative total of the amounts of any advance payment that have then become due for reimbursement to the Employer in accordance with the terms stated in the Contract Particulars for clause 4.6; and
.3 the amounts paid in previous Interim Payments.
Contractor's Interim Applications and due dates
4.8
.1 In relation to each Interim Payment, the Contractor shall make an application to the Employer (an 'Interim Application') in accordance with the following provisions of this clause 4.8, stating the sum that the Contractor considers to be due to him and the basis on which that sum has been calculated.
.2 Where Alternative A applies, an Interim Application shall be made as at completion of each stage specified in or by the Contract Particulars for Alternative A. Following the application in respect of the last stage, such applications shall be made at intervals of 2 months (unless otherwise agreed), the last such application being made upon the expiry of the Rectification Period or, if later, the issue of the Notice of Completion of Making Good (or, where there are Sections, the last such period or notice). The due date for payment (the 'due date') in each case shall be the later of the date of completion of the stage (or, when applicable, the 2 monthly date) and the date of receipt by the Employer of the Interim Application.
.3 Where Alternative B applies, for the period up to practical completion of the Works, Interim Applications shall be made as at the monthly dates specified in the Contract Particulars for Alternative B up to the date of practical completion or the specified date within one month thereafter. Subsequent Interim Applications shall be made at intervals of 2 months (unless otherwise agreed), the last such application being made upon the expiry of the Rectification Period or, if later, the issue of the Notice of Completion of Making Good (or, where there are Sections, the last such period or notice). The due date in each case shall be the later of the specified date and the date of receipt by the Employer of the Interim Application.
.4 Interim Applications may be madebefore, on or after completion of the relevant stage or the monthly date and shall be accompanied by such further information as may be specified in the Employer's Requirements and Contractor's Proposals.
Interim Payments final date and amount
4.9
.1 The final date for payment of an Interim Payment shall be 28 days14 daysfrom its due date.
.2 Not later than 5 days after the due date the Employer shall give a notice (a 'Payment Notice') to the Contractor in accordance with clause 4.10.1 and, subject to any Pay Less Notice given by the Employer under clause 4.9.4, the amount of the Interim Payment to be made by the Employer on or before the final date for payment shall be the sum stated as due in the Payment Notice.
.3 If the Payment Notice is not given in accordance with clause 4.9.2, the amount of the Interim Payment to be made by the Employer shall, subject to any Pay Less Notice under clause 4.9.4, be the sum stated as due in the Interim Application.
.4 If the Employer intends to pay less than the sum stated as due from him in the Payment Notice or Interim Application, as the case may be, he shall not later than 35days before the final date for payment give the Contractor notice of that intention in accordance with clause 4.10.2 (a 'Pay Less Notice'). Where a Pay Less Notice is given, the payment to be made on or before the final date for payment shall not be less than the amount stated as due in thenoticePay Less Notice.
.5 If the Employer fails to pay a sum, or any part of it, due to the Contractor under these Conditions by the final date for its payment, the Employer shall, in addition to any unpaid amount that should properly have been paid, pay the Contractor simple interest on that amount at the Interest Rate for the period from the final date for payment until payment is made. Interest under this clause 4.9.5 shall be a debt due to the Contractor from the Employer.
.6 Acceptance of a payment of interest under clause 4.9.5 shall not in any circumstances be construed as a waiver of the Contractor's right to proper payment of the principal amount due, to suspend performance under clause 4.11 or to terminate his employment under section 8.
Payment Notices, Pay Less Notice and general provisions
4.10
.1 Each Payment Notice under this Contract shall specify the sum that the Party giving the notice considers to be or have been due at the due date in respect of the relevant payment and the basis on which that sum has been calculated.
.2 A Pay Less Notice:
.1 (where it is to be given by the Employer) shall specify both the sum that he considers to be due to the Contractor at the date the notice is given and the basis on which that sum has been calculated;
.2 (where it is to be given by the Contractor) shall specify both the sum that he considers to be due to the Employer at the date the notice is given and the basis on which that sum has been calculated.
.3 A Payment Notice or a Pay Less Notice to be given by the Employer may be given on his behalf by the Employer's Agent or by any other person who the Employer notifies the Contractor as being authorised to do so.
.4 In relation to the requirements for the giving of notices under section 4 and the submission of a Final Statement, it is immaterial that the amount then considered to be due may be zero.
.5 Any right of the Employer to deduct or set off any amount (whether arising under any provision of this Contract or under any rule of law or equity) shall be exercisable against any monies due or to become due to the Contractor, whether or not such monies include or consist of any Retention.
.5 Notwithstanding his fiduciary interest in the Retention as stated in clause 4.16, the Employer is entitled to exercise any rights under this Contract of withholding or deduction from sums due or to become due to the Contractor, whether or not any Retention is included in any such sum under clause 4.18."
Final Statement and final payment
4.12.
.1 Following practical completion of the Works the Contractor shall submit the Final Statement to the Employer and supply him with such supporting documents as he may reasonably require.
.2 The Final Statement shall set out the adjustments to the Contract Sum to be made in accordance with clause 4.2 and shall state:
.1 the Contract Sum, as so adjusted; and
.2 the sum of amounts already paid by the Employer to the Contractor,
and the final payment shall be the difference (if any) between the two sums, which shall be shown as a balance due to the Contractor from the Employer or to the Employer from the Contractor, as the case may be. The Final Statement shall state the basis on which that amount has been calculated, including details of all such adjustments.
.5 The due date for the final payment shall be the date one month after whichever of the following occurs last:
.1 the end of the Rectification Period in respect of the Works or (where there are Sections) the last such period to expire;
.2 the date stated in the Notice of Completion of Making Good under clause 2.36 or (where there are Sections) in the last such notice to be issued; or
.3 the date of submission to the other Party of the Final Statement or, if issued first, the Employer's Final Statement ("the relevant statement").
Ascertainment Alternative A
4.13 The GrossValuation
shall be the total of the amounts referred to in clauses 4.13.1 and 4.13.2 less the total of the amounts referred to in clause 4.13.3, calculated as at completion of the relevant stage.
.1 The following which are subject to Retention shall be included:
.1 the cumulativevalue
at the relevant stage;
.2 thevalue
of any Changes or other work referred to in clause 5.2 that are relevant to the Interim Payment (whether agreed pursuant to clause 5.2 or
valued
under the
Valuation
Rules) but excluding any amounts referred to in clause 4.13.2-4;
3. thevalue
of any Listed Items, when their
value
is to be included under clause 4.15;
.4 the amount of any adjustment under Fluctuations Option C (if applicable);
.5 where Fluctuations Option C is applicable and where in accordance with the Formula Rules amounts in theValue
of Work are to be allocated to lift installations, structural steelwork installations or catering equipment installations, the total
value
of Site Materials of those descriptions, provided that their
value
shall only be included if they are adequately protected against weather and other casualties and they are not on the Works prematurely; and
.6 the amount of any adjustment by Confirmed Acceptance of an Acceleration Quotation.
.2 The following which are not subject to Retention shall be included:
.1 any amounts to be included in Interim Payments in accordance with clause 4.3 by the Employer as a result of payments made or costs incurred by the Contractor under clause 2.5.2, 2.20, 3.12, 6.10.2 or 6.10.3 or paragraph B2.1.2 or C3.1 of Schedule 3;
.2 any amounts payable under clause 4.11.2;
.3 any amounts ascertained under clause 4.20;
.4 any amounts in respect of any restoration, replacement or repair of loss or damage and removal and disposal of debris under paragraph B3.5 and C4.5.2 of Schedule 3 or clause 6.11.5.2; and
.5 any amount payable to the Contractor under Fluctuations Option A or B, if applicable.
.3 The following shall be deducted:
.1 any amounts deductible under clause 2.35 or 3.6; and
.2 any amount allowable by the Contractor to the Employer under clause 6.10.2 or under Fluctuations Option A or B, if applicable.
Ascertainment Alternative B
4.14 The GrossValuation
shall be the total of the amounts referred to in clauses 4.14.1 and 4.14.2 less the total of the amounts referred to in clause 4.14.3, calculated as at the date for making an Interim Application under clause 4.8.3.
.1 The totalvalues
of the following which are subject to Retention shall be included:
.1 work properly executed including any design work carried out by the Contractor and work so executed for which avalue
has been agreed pursuant to clause 5.2 or which has been
valued
under the
Valuation
Rules, together, where applicable, with any adjustment of that
value
under the Fluctuations Option C or by Confirmed Acceptance of an Acceleration Quotation, but excluding any amounts referred to in clause 4.14.2-4;
. 2 Site Materials provided that theirvalue
shall only be included if they are adequately protected against weather and other casualties and they are not on the Works prematurely; and
.3 Listed Items (if any), when theirvalue
is to be included under clause 4.15.
.2 The following which are not subject to Retention shall be included:
.1 any amounts to be included in Interim Payments in accordance with clause 4.3 by the Employer as a result of payments made or costs incurred by the Contractor under clause 2.5.2, 2.20, 3.12, 6.10.2 or 6.10.3 or paragraph B2.1.2 or C3.1 of Schedule 3;
.2 any amounts payable under clause 4.11.2;
.3 any amounts ascertained under clause 4.20;
.4 any amounts in respect of any restoration, replacement or repair of loss or damage and removal and disposal of debris under paragraph B3.5 or C4.5.2 of Schedule 3 or clause 6.11.5.2; and
.5 any amount payable to the Contractor under Fluctuations Option A or B, if applicable.
.3 The following shall be deducted:
.1 any amounts deductible under clause 2.35 or 3.6; and
.2 any amount allowable by the Contractor to the Employer under clause 6.10.2 or under Fluctuations Option A or B, if applicable."
The crossings out and underlinings in the above clauses indicate the amendments which the parties had made to the standard conditions.
"TO BE AGREED WITHIN 2 WEEKS FROM DATE OF CONTRACT."
Grove
should make interim payments to BB in accordance with a schedule headed
"Greenwich Hotels and Apartments
InterimValuation/Payment
Dates 2013 2015
Valuation
Application on Third Thursday of the month"
"
Valuation no. |
Val month |
Mansell Application Submission Date to Grove | Valuation Date |
Grove Certificate Issued(3 working days) |
Payment made by Grove by (30 days from Val date) |
| JUL | |||||
| AUG | |||||
| 1 | SEPT | 19/09/2013 | 20/09/2013 | 25/09/2013 | 20/10/2013 |
| 2 | OCT | 17/10/2013 | 18/10/2013 | 23/10/2013 | 22/11/2013 |
| 3 | NOV | 14/11/2013 | 15/11/2013 | 20/11/2013 | 20/12/2013 |
| 4 | DEC | 19/12/2013 | 19/12/2013 | 24/12/2013 | 23/01/2014 |
| 5 | JAN | 23/01/2014 | 24/01/2014 | 29/01/2014 | 25/02/2014 |
| 6 | FEB | 20/02/2014 | 21/02/2014 | 26/02/2014 | 28/03/2014 |
| 7 | MAR | 20/03/2014 | 21/03/2014 | 26/03/2014 | 25/04/2014 |
| 8 | APR | 17/04/2014 | 18/04/2014 | 23/04/2014 | 23/05/2014 |
| 9 | MAY | 22/05/2014 | 23/05/2014 | 28/05/2014 | 27/06/2014 |
| 10 | JUN | 19/06/2014 | 20/06/2014 | 25/06/2014 | 25/07/2014 |
| 11 | JUL | 17/07/2014 | 18/07/2014 | 23/07/2014 | 22/08/2014 |
| 12 | AUG | 21/08/2014 | 22/08/2014 | 27/08/2014 | 28/09/2014 |
| 13 | SEPT | 18/09/2014 | 19/09/2014 | 24/09/2014 | 24/10/2014 |
| 14 | OCT | 16/10/2014 | 17/10/2014 | 22/10/2014 | 21/11/2014 |
| 15 | NOV | 20/11/2014 | 21/11/2014 | 26/11/2014 | 26/12/2014 |
| 16 | DEC | 18/12/2014 | 19/12/2014 | 24/12/2014 | 23/01/2015 |
| 17 | JAN | 22/01/2015 | 23/01/2015 | 28/01/2015 | 27/02/2015 |
| 18 | FEB | 19/02/2015 | 20/02/2015 | 25/02/2015 | 27/03/2015 |
| 19 | MAR | 19/03/2015 | 20/03/2015 | 25/03/2015 | 24/04/2015 |
| 20 | APR | 16/04/2015 | 17/04/2015 | 22/04/2015 | 22/05/2015 |
| 21 | MAY | 21/05/2015 | 22/05/2015 | 27/05/2015 | 26/06/2015 |
| 22 | JUN | 18/06/2015 | 19/06/2015 | 24/06/2015 | 24/07/2015 |
| 23 | JUL | 16/07/2015 | 17/07/2015 | 22/07/2015 | 21/08/2015 |
"
Grove
by email on 30th September 2013. He wrote in the covering email:
"Michael
Please find attached agreed schedule ofvaluation
/ payment dates for this project."
Grove
and BB faithfully adhered to the timetable set out in the Tumber schedule. They carried out the
valuation
exercise each month in accordance with the provisions of clause 4.14.
valuations
and payments.
Grove's
agent issued a payment notice in respect of that application. On 15th September
Grove
issued a Pay Less notice in respect of application 24. This showed that
Grove
would deduct £2 million, because there was a dispute about whether BB should give credit for an extra-contractual payment of £2 million previously made by
Grove.
The Pay Less notice showed the payment date as 25th September. On 18th September
Grove
paid £439,503, which was the sum shown as due on the Pay Less notice after deducting the £2 million.
Grove's
calculation of dates. They also took the
view
that by reason of
Grove's
miscalculations the Pay Less notice was ineffective. Accordingly on 30th September 2015 BB sent a formal letter to
Grove
demanding payment of the £2 million, which
Grove
had withheld in reliance on the Pay Less notice. On page 2 of that letter BB wrote:
"Despite efforts on both sides, no agreement has been reached in relation to the Interim payment process beyond July 2015. For the avoidance of any doubt, our previous offers to agree the Interim payment process beyond July 2015 are now withdrawn and are no longer capable of acceptance."
Grove
made no further payments to BB during that period. This was for two reasons. First,
Grove
maintained that their Pay Less notice of 15th September was
valid
and entitled them to withhold the disputed £2 million. Secondly, they maintained that liquidated and ascertained damages for delay exceeded and extinguished any payments due to BB in respect of work done.
Grove
asserted that BB had no continuing entitlement to receive payments.
Grove
commenced the present proceedings.
Grove
claimed a declaration to the effect that BB had no entitlement to interim payments in respect of work done after July 2015.
Grove
also sought other relief which is no longer relevant.
Grove
and issued the following declaration:
"The Defendant has no contractual right to make Interim Application no.24 (or any subsequent application) and has no right to be paid in respect thereof."
The judge also granted a second declaration concerning the
validity
of
Grove's
Pay Less notice, but that is not relevant for present purposes.
i) The Tumber schedule acted as a specific amendment to the contract. It meant that the parties abandoned Alternative A and agreed instead that there would be 23 interim payments in accordance with the dates set out in the schedule.
ii) The contract as amended by the Tumber schedule did not make any express provision for further interim payments after
valuation
23.
iii) There was no implied term providing for interim payments after
valuation
23.
iv) The contract as amended by the Tumber schedule satisfied the requirements of sections 109 and 110 of the 1996 Act. Therefore the Scheme did not apply.
v)
The parties' correspondence and conduct during the summer and autumn of 2015 was not such as to give rise to a fresh agreement for interim payments. This was because the parties never reached agreement on the essential terms for such interim payments.
vi)
Grove
were not estopped from contending that BB had no continuing entitlement to interim payments after
valuation
23.
i) The contract as amended by the Tumber schedule expressly or impliedly provided for continuing interim payments to be made between August 2015 and the date of practical completion.
ii) Alternatively, if there was no express or implied entitlement to continuing interim payments, the contract as amended by the Tumber schedule, did not comply with the requirements of section 109 of the 1996 Act. Therefore the Scheme applied and conferred a statutory right to monthly interim payments between August 2015 and practical completion.
iii) If Grounds (i) and (ii) fail, then the parties' correspondence and conduct in the summer and autumn of 2015 gave rise to a fresh contract for monthly interim payments.
Grove.
Mr Nissen argued the respondent's case on all three grounds.
valuation
23.
valuation
23?
Grove
should make stage payments to BB under Alternative A, as defined in clause 4.7 of the conditions. In other words a list of milestones in the progress of the works would be drawn up; as and when BB reached one of the milestones,
Grove
would make a stage payment. The quantity surveyors would calculate the amount of the stage payment by applying the rules set out in clause 4.13.
Grove
would make interim payments in accordance with Alternative B (as defined in clause 4.7) or some
variant
of Alternative B. Mr Nissen resists that contention, pointing out that the dates in the Tumber schedule are inconsistent with clauses 4.8 to 4.9.
valuations
and payments up to the anticipated date of practical completion.
Grove
issued payment notices on the dates shown in column 5 and made payments on the dates shown in column 6. The respective quantity surveyors quantified the payments due in accordance with clause 4.14, not clause 4.13 (as envisaged originally).
valuation
23 there was no document to tell the parties when
valuations
should be made, when payment notices and Pay Less notices should be served or when payments should be made. Extrapolation from the Tumber schedule suggested one possible timetable. Application of clauses 4.8 to 4.9 suggested an alternative possible timetable. It is hardly surprising that this situation led to confusion and disagreement about who should do what and when.
view,
it is not possible to say that in September 2013 the parties simply agreed to adopt Alternative B. What they agreed was a hybrid arrangement which had elements of Alternative B (in particular
valuation
under clause 4.14) and a timetable of their own invention. That timetable ended on 22nd July 2015, the contractual date for practical completion.
valiantly
argued that clearly the parties intended monthly interim payments to continue. The dates of
valuations,
payment notices and payments were a matter of detail which could if necessary be resolved by adjudication or some similar mechanism. I cannot accept that. Identification of the dates for
valuation,
payment notices, Pay Less notices and payments were an essential feature. If
Grove
served notices out of time, the consequences would be Draconian (as BB asserted in their letter dated 30th September 2015). Both parties needed to know with certainty what were the applicable dates.
valuation
/ payment dates for this project". Neither the email nor the schedule made any provision for interim payments after July 2015. Secondly, it is impossible to deduce from the hybrid arrangement what would be the dates for
valuations,
payment notices, Pay Less notices and payments after July 2015. These were essential matters for the reasons previously stated. Thirdly, this is a classic case of one party making a bad bargain. The court will not, indeed cannot, use the canons of construction to rescue one party from the consequences of what that party has clearly agreed. There is no ambiguity in the present case which enables the court to reinterpret the parties' contract in accordance with "commercial common sense", which Mr Walker seeks to invoke.
v
Britton [2015] UKSC 36; [2015] AC 1619 at [15] to [23]. I do not think that those principles assist BB. The language of the contract as amended by the Tumber schedule is clear. It provides only for interim payments up to
valuation
23. As Lord Neuberger said at [19]:
"The mere fact that a contractual arrangement, if interpreted according to its natural language, has worked out badly, or even disastrously, for one of the parties is not a reason for departing from the natural language."
"Fourthly, while commercial common sense is avery
important factor to take into account when interpreting a contract, a court should be
very
slow to reject the natural meaning of a provision as correct simply because it appears to be a
very
imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight. The purpose of interpretation is to identify what the parties have agreed, not what the court thinks that they should have agreed. Experience shows that it is by no means unknown for people to enter into arrangements which are ill-advised, even ignoring the benefit of wisdom of hindsight, and it is not the function of a court when interpreting an agreement to relieve a party from the consequences of his imprudence or poor advice. Accordingly, when interpreting a contract a judge should avoid re-writing it in an attempt to assist an unwise party or to penalise an astute party."
valuation
and payment dates post-July 2015 from the Tumber schedule or from clauses 4.8 to 4.9. Indeed Mr Walker has not put forward either in his skeleton argument or in his oral submissions what the sequence of dates would be if the contract is construed as he says it should be construed.
v
Shire of Hastings (1977) 180 CLR 266 at 282-3 Lord Simon stated the general principles as follows:
"for a term to be implied, the following conditions (which may overlap) must be satisfied: (1) it must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract, so that no term will be implied if the contract is effective without it; (3) it must be so obvious that 'it goes without saying'; (4) it must be capable of clear expression; (5) it must not contradict any express term of the contract."
v
BNP Parabis Securities Services Trust [2015] UKSC 72; [2016] AC 742. Lord Neuberger (with whom Lord Sumption and Lord Hodge agreed) accepted Lord Simon's statement of principle, but at [21] added the following six comments:
"First, in Equitable Life Assurance Societyv
Hyman [2002] 1 AC 408, 459, Lord Steyn rightly observed that the implication of a term was "not critically dependent on proof of an actual intention of the parties" when negotiating the contract. If one approaches the question by reference to what the parties would have agreed, one is not strictly concerned with the hypothetical answer of the actual parties, but with that of notional reasonable people in the position of the parties at the time at which they were contracting. Secondly, a term should not be implied into a detailed commercial contract merely because it appears fair or merely because one considers that the parties would have agreed it if it had been suggested to them. Those are necessary but not sufficient grounds for including a term. However, and thirdly, it is questionable whether Lord Simon's first requirement, reasonableness and equitableness, will usually, if ever, add anything: if a term satisfies the other requirements, it is hard to think that it would not be reasonable and equitable. Fourthly, as Lord Hoffmann I think suggested in Attorney General of Belize
v
Belize Telecom Ltd [2009] 1 WLR 1988, para 27, although Lord Simon's requirements are otherwise cumulative, I would accept that business necessity and obviousness, his second and third requirements, can be alternatives in the sense that only one of them needs to be satisfied, although I suspect that in practice it would be a rare case where only one of those two requirements would be satisfied. Fifthly, if one approaches the issue by reference to the officious bystander, it is "
vital
to formulate the question to be posed by [him] with the utmost care" to quote from Lewison, The Interpretation of Contracts 5th ed (2011), p 300, para 6.09. Sixthly, necessity for business efficacy involves a
value
judgment. It is rightly common ground on this appeal that the test is not one of "absolute necessity", not least because the necessity is judged by reference to business efficacy. It may well be that a more helpful way of putting Lord Simon's second requirement is, as suggested by Lord Sumption JSC in argument, that a term can only be implied if, without the term, the contract would lack commercial or practical coherence."
view
the present case falls far short of satisfying the requirements for implication of the proposed term. In particular, it is not obvious what the proposed term would say or what would be the critical dates for serving notices. Furthermore, the proposed term is not necessary to secure business efficacy. Nor can it be said that the contract would lack commercial or practical coherence without such a term.
valuation
23. BB will receive full payment for their work in due course, but they will have to wait until the final payment date as defined in clause 4.12 of the contract conditions.
v
Scutt [1920] 1 Ch 382. That case concerned a tenancy agreement in which the tenant agreed not to plough "any grass land". Eve J construed that phrase broadly as meaning all land covered in grass either at the date of the demise or subsequently. He therefore treated the word "any" as meaning "all".
view
the subsection is a more general one saying that work done under construction contracts shall (except in
very
short projects) be subject to a regime of interim payments.
value
of work done. Indeed parties normally do agree that, so that the Employer holds retention monies, usually releasing half at practical completion and the other half when all defects have been made good.
"18-106 Stage Payments. Section 109 of the Act states that a party to a construction contract is generally entitled to payment by instalments, stage payments or other periodic payments for any work under the contract. The reference to "stage payments" would seem to permit payment by reference to the achievement of particular elements of the work. Further, there is no requirement as to when such payments are to be made; any arrangement which satisfies the definition will be sufficient. Thus a contract prescribing one periodic payment, even of an insignificant amount, would, it would seem, meet the requirements."
valuation
23.
valuation
23?
very
fully the correspondence passing between the parties in the period May to December 2015. See paragraphs 16 to 21 and 39 of his judgment. I will not repeat that recitation.
valuations,
notices and payments. Both parties treated those matters as essential elements of any contract. BB themselves put this point forcefully in their letter to
Grove
dated 30th September 2015, from which I have quoted in Part 2 above.
Grove
waived the need to agree on dates by issuing payment notice 24. I do not agree.
Grove
maintained their position in relation to dates and contractual terms.
Grove
issued the payment notice and made a payment to protect themselves against the risk of losing their right to withhold £2 million, if it turned out that their interpretation of the contract was wrong. In the event, BB still maintained that
Grove
had forfeited the right to withhold £2 million.
Lord Justice
Vos:
Was the Contract ambiguous?
valuation
dates as being the "specified date" which is the same as the date of the interim application (clause 4.8.3 and 4.14), whilst the Tumber Schedule provides for
valuation
dates that were in all but one case the day following the date for the interim application. The JCT form provides for the issue by the employer of a "Payment Notice" not later than 5 days after the "due date" (the later of the specified date and date the employer receives the interim application) (clauses 4.8.3 and 4.9.2), whilst the Tumber Schedule provides for
Grove
to provide an employer's certificate 3 working days after the
valuation
date (which comes to the same thing because of the intervention of a week-end in every case). Finally, the JCT form (as originally
varied
by the parties) provided for payment of the interim payment 28 days from its due date (clause 4.9.1), whilst the Tumber Schedule provided for a payment date 30 days from the specified
valuation
date. The Tumber Schedule does not specify or contemplate "stages" as envisaged by Alternative A and clauses 4.8.2 and 4.13.
valuation
of each periodic payment envisaged by the Tumber Schedule had to be undertaken according to some known process. Neither party has suggested that any such process was available to the parties, save that contained in clause 4.14. There was no evidence that any of the 3 adjudications invoked clause 4.14, but it seems
very
likely that, had they involved an argument about the basis of the
valuation,
they would have done so. Certainly, the process envisaged by the Tumber Schedule cannot fit within the provisions of clause 4.13.
Grove
submits that it is a free standing complete document that provides for each and every interim payment that is to be made under the Contract. BB submits that it cannot be so construed, partly because of the reintroduction of clauses 4.8.3 and 4.14, but also because that is not what it says on its face. I take the
view
that BB's submissions are to be preferred, for the following reasons.
Valuation/Payment
Dates 2013-2015", which does not indicate whether or not there might be further interim payments due or to be agreed after 2015. I accept that the completion date was 22nd July 2015, but parties to any construction contract must be taken to know that the contract period may well be exceeded. Thirdly, the Tumber Schedule is headed "
Valuation
Application on Third Thursday of the month", as is reflected in the dates in the 3rd column headed "
Application Submission Date to
Grove".
The last date is understandably immediately before the agreed date for completion, but the rubric about the third Thursday of the month would be quite unnecessary if the listed interim payment application dates were intended to be exhaustive. Moreover, there is no reason to suppose that interim payments were not envisaged after practical completion as would be normal and as was provided for by clause 4.8.3. Finally, on this point, I would mention, but not take into account since it is not strictly admissible, that it was clear from their conduct after the event that the parties both thought that interim payments remained due after those listed in the Tumber Schedule until
Grove
obtained legal advice to contrary effect.
varied
the precise dates included in the JCT form for all interim payments listed in the Tumber Schedule. The Tumber Schedule is silent as to any future interim payments if practical completion were not reached on 22nd July 2015 (as in fact occurred). It could be that the Contract meant that the parties should revert to the strict wording of Alternative B and the JCT Form for interim payments after 22nd July 2015, and it could be that it meant that interim payments should continue after interim payment 23 on equivalent dates thereafter triggered on the third Thursday of every month by BB's application submission to
Grove.
It could be that the parties are to be taken as having agreed nothing after interim payment 23, save that they would later agree what process and what dates would apply to subsequent interim payments. But in my judgment, the Tumber Schedule is not clear enough to be construed as meaning, when taken together with the JCT form, that the parties must have intended that there would be no interim payments after interim payment 23.
view
that clear words would be required for such a construction of the Tumber Schedule. In reality, such a construction would mean that BB would not be paid large sums for 2 or 3 years after the last interim payment. That is an uncommercial construction. There is no suggestion from the admissible factual matrix that the financing and security risks had been intended to pass in that way to BB after the expected completion date.
Grove's
submissions on incentives to complete on time are all pure speculation when the JCT form has detailed provisions that have that effect.
Grove's
representative by BB under cover of an email that recited "[p]lease find attached agreed schedule of
valuation/payment
dates for this project". But I do not think too much weight can be placed on this document that was apparently sent after the Tumber Schedule had been agreed. Moreover, the dates in the Tumber Schedule were the only ones actually specified "for the project", so those words cannot outweigh the proper meaning of the Tumber Schedule read together with the JCT form in the way I have suggested and taken against the background of the appropriate factual matrix.
view
that the Contract is ambiguous.
If the Contract is ambiguous, what is its proper construction?
Grove,
or there being a lacuna in the Contract as properly construed.
view,
that the Tumber Schedule must be taken to have
varied
the JCT form including clauses 4.8.3 and 4.14 so as to substitute the specified dates for the specified date, the
valuation
date, the due date and the final payment date envisaged by the JCT form. In my judgment, the only sensible construction of what the parties agreed is to construe the Contract as if the Word "etcetera" were included at the end of the Tumber Schedule.
v.
Britton [2015] AC 1619. But I should say, perhaps, that I have had regard to these principles and do not think they are contravened by my construction. This is a case somewhat akin to Aberdeen City Council
v.
Stewart Milne Group Limited [2012] SC (UKSC) 240 referred to by Lord Neuberger at paragraph 22 in Arnold, where Lord Hope said (also at paragraph 22) that the context showed that the intention of the parties was as he found it to be, and that it could be assumed that that was what the parties would have said if they had been asked about it at the time. The fact that it made good commercial sense was simply a makeweight. In that case, as in this, the words of the contract itself told the reader what must have been intended. Here the parties must have intended interim payments to continue on the same basis up to practical completion. No undue
violence
is required to the words the parties actually used to reach that construction.
Lord Justice Longmore:
Vos
LJ makes a
valiant
attempt to fill in the imponderables by deciding that the parties "opted to revert" to the applicability of Alternative B. I cannot, with respect, agree; the parties had expressly agreed that Alternative B was not to be adopted. It is true that they found they could not reach agreement on Alternative A but that does not mean that they "opted to revert" to Alternative B which they had expressly agreed not to adopt in the first place. In my judgment, they made a new agreement and that new agreement covered the matters set out in the Tumber schedule and no more.
Vos LJ is (as he is happy to acknowledge) to treat the schedule as if at the end it had added the rubric "etcetera". That effectively adds an important word which is additional to the agreement made by the parties and is, to my mind, an impermissible construction.