![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Drax Smart Generation Holdco Ltd v Scottish Power Retail Holdings Ltd [2024] EWCA Civ 477 (08 May 2024) URL: https://www.bailii.org/ew/cases/EWCA/Civ/2024/477.html Cite as: [2024] EWCA Civ 477 |
||
[New search]
[Context
]
[View without highlighting]
[Printable PDF version]
[Help]
ON APPEAL FROM THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
LONDON CIRCUIT COMMERCIAL COURT (KBD)
Mr Simon Birt KC (sitting as a Deputy Judge of the High Court)
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE MALES
and
LORD JUSTICE BIRSS
____________________
DRAX SMART GENERATION HOLDCO LIMITED |
CA-2023-000655 Claimant/ Appellant |
|
| - and - |
||
| SCOTTISH POWER RETAIL HOLDINGS LIMITED |
Defendant/Respondent |
|
And Between: |
||
DRAX SMART GENERATION HOLDCO LIMITED |
CA-2023- 000669 Claimant/ Respondent |
|
| -and- |
||
| SCOTTISH POWER RETAIL HOLDINGS LIMITED |
Defendant/ Appellant |
____________________
Drax
Sa'ad Hossain KC and Joyce Arnold (instructed by Womble Bond Dickinson (UK) LLP) for Scottish Power
Hearing date: 16th April 2024
____________________
Crown Copyright ©
LORD JUSTICE MALES:
Background
Generation
Limited and now renamed VPI Power Limited ('the Company') to
Drax
Smart
Generation
Holdco Ltd ('
Drax')
for a total price of £702 million. The Agreement was a long and complex document running to some 225 pages.
title
of E.ON.
Drax,
was that the rights under the Damhead Creek II Option Agreement were not transferred to the Company, with the result that the Company was not entitled to exercise those rights. Unfortunately this mistake was not recognised in time.
Drax
was concluded on 18th October 2018. It included terms by which Scottish Power warranted that the benefit of the Damhead Creek II Option Agreement would be assigned to the Company prior to Completion and agreed to indemnify
Drax
for all losses suffered as a result of (among other things) any failure to transfer the benefit of the option agreement to the Company.
Drax
gave notice to Scottish Power of 'a matter which may give rise to a claim under the [Agreement]', summarising the events set out above. There was further correspondence over the course of the next year which it is unnecessary to summarise, save to say that during 2020 the parties entered into two deeds of variation relating to the time limit for notifying claims under the Agreement. The first deed of variation, dated 30th June 2020, defined a new type of claim, a 'Damhead Creek II Option Agreement Claim', and provided that the time limit for
Drax
to give notice in respect of any such claim was 24 months from the Completion Date. The second deed of variation, dated 29th December 2020, extended this time limit until 30 months from the Completion Date (i.e. until 30th June 2021).
Drax
sold the Company to VPI
Generation
Limited ("VPI"), pursuant to a sale and purchase agreement dated 15th December 2020. So far as we have been made aware, it does not appear that the price which
Drax
was able to achieve for the sale of the Company was affected by its inability to transfer to VPI the benefit of an easement over the Kingsnorth site.
Drax
gave what it described as 'formal notice of a Damhead Creek II Option Agreement Claim', and also 'to the extent necessary … formal notice of a Reorganisation Claim' under the Agreement ('the Notice of Claim'). It is the sufficiency of this notice which is in issue on these appeals. Before examining the terms of the notice, however, it is necessary to set out some of the terms of the Agreement.
Relevant terms of the Agreement
'The Seller warrants to the Buyer that the Warranties are true and accurate at the date of this Agreement. …'
'9.1. The Reorganisation has been carried out in accordance with the Reorganisation Agreements and, except as Disclosed, all transfers and other actions envisaged by the Reorganisation Documents have occurred.
…
9.3. All material licences, registrations, consents, permits, concessions, certifications, approvals and other authorisations (public and private) that are necessary for the completion of the Reorganisation have been obtained.'
Drax's
claims is brought:
'Subject to Completion taking place and subject to Clauses 11.2 and 11.3, the Seller covenants to pay to the Buyer, each Group Company and each other Buyer's Group Undertaking within five (5) Business Days of a demand by written notice from the Buyer to the Seller an amount which is equal, on an after-Tax basis, to any and all Losses suffered by any Group Company or any member of the Buyer's Group, whether arising before, on or after Completion:
…
11.1.3 in relation to, or arising out of, any steps or actions taken to implement the Reorganisation (or any part thereof) (including, for the avoidance of doubt, any steps or actions comprised in the Reorganisation which occur after Completion) and including Losses arising as a result of a Group Company ceasing to be a member of a group or consortium or other association for Tax purposes with any member of the Seller's Group which would not have arisen but for any transfer or transfers undertaken pursuant to the Reorganisation;
11.1.4 that would not have been suffered but for (i) the fact that the Reorganisation (or any part thereof) … was not implemented and completed in full prior to the date of this Agreement; or (ii) the fact that the Reorganisation (or any part thereof) was not implemented and completed correctly in accordance with the Reorganisation Documents and Applicable Law; …'
'The Seller shall procure that the benefit of the Damhead Creek II Option Agreement shall be assigned to the Company on or prior to Completion on terms approved by the Buyer (such approval not to be unreasonably withheld or delayed).'
Drax
seeks to bring arises out of a single factual complaint, namely that the Company did not have the benefit of the Damhead Creek II Option Agreement, as it ought to have done. The claim is put in three ways. First, it is said that Scottish Power was thereby in breach of clause 14.51.3 of the Agreement. Second, it is said that Scottish Power was in breach of clause 8.1 of the Agreement because the Warranties in paragraphs 9.1 and 9.3 of Schedule 3 were not true and accurate. Third, it is said that Scottish Power is obliged pursuant to clauses 11.1.3 and 11.1.4 of the Agreement to pay
Drax
an amount which is equal to its losses suffered as a result of the Company not having the benefit of the Damhead Creek II Option Agreement.
Drax's
letter dated 30th June 2021 was insufficient to satisfy the requirements of paragraph 2.1 of Schedule 4 of the Agreement (which I shall call the 'Notice of Claim clause'). As originally agreed, this provided:
'In the case of the types of claim detailed below, the Seller shall not be liable for a claim unless the Buyer has notified the Seller of the claim, stating in reasonable detail the nature of the claim and the amount claimed (detailing the Buyer's calculation of the Loss thereby alleged to have been suffered):
2.1.1 in respect of any Relevant Claim … on or before the date which is 18 months from the Completion Date;
2.1.2 in respect of any Fundamental Warranty Claim, on or before the date which is seven (7) years from the Completion Date;
2.1.3 in respect of any Fundamental Property Warranty Claim, on or before the date which is seven (7) years from the Completion Date;
2.1.4 in respect of any Tax Warranty Claim or any claim under Schedule 9 (Tax Covenant), on or before the date which is seven (7) years from the Completion Date;
2.1.5 in respect of any claim under or pursuant to Clause 14.43, on or before the date which is seven (7) years from the Completion Date;
2.1.6 in respect of any Daldowie Indemnity Claim, on or before the date which is two (2) years from the Completion Date;
2.1.7 in respect of any Reorganisation Indemnity Claim: (a) which relates to EHS Matters (including, without limitation, decommissioning), on or before the date which is ten (10) years from the Completion Date; (b) which relates to any other matter, event or circumstances, on or before the date which is seven (7) years from the Completion Date;
2.1.8 in respect of any Pensions Indemnity Claim, on or before the date which is eight (8) years from the Completion Date; or
2.1.9 in respect of any claim under or pursuant to Clause 14.8 or Clause 14.11 of this Agreement, on or before the date which is six (6) months from the date on which the Group Companies are released and discharged from the SPUK PLC Support Commitments.'
Drax's
claims for breaches of clauses 14.51.3 and 8.1 of the Agreement fell within the definition of 'Relevant Claim', so that the applicable time limit for those ways of putting its case was 18 months from the Completion Date (i.e. 30th June 2020) and that its claim pursuant to clauses 11.1.3 and 11.1.4 of the Agreement fell within the definition of 'Reorganisation Indemnity Claim', so that
Drax
had seven years from the Completion Date (i.e. until 31st December 2025) to give notice of this claim. In this connection it should be noted that the definition of 'Relevant Claim' expressly excluded a 'Reorganisation Indemnity Claim', so that the time limits in paragraphs 2.1.1 and 2.1.7 were mutually exclusive even though a single factual complaint could give rise to a claim under each of these paragraphs.
'"Damhead Creek II Option Agreement Claim" means any claim under or pursuant to this Agreement arising out of or in connection with or in respect of any failure to validly assign the benefit of the Damhead Creek II Option Agreement from [SPDCL] to the Company, including without limitation any claim under or pursuant to the Agreement arising out of or in connection with or in respect of any failings or deficiencies in the Damhead Creek II Option Covenant and/or the Damhead Creek II Option Assignment.'
'2.1.10 in respect of any Damhead Creek II Option Agreement Claim, on or before the date which is 30 months from the Completion Date.'
Drax's
claim for breach of clause 8.1 of the Agreement, the definition of 'Warranty Claim' is such that it would not affect
Drax's
claims for breach of clause 14.51.3 or for an indemnity pursuant to clauses 11.1.3 or 11.1.4.
The Notice of Claim
'In particular, this letter sets out (in reasonable detail) the nature of the claims and an estimate of the losses alleged to have been suffered.'
Drax
had entered into discussions with Uniper, which had indicated that Uniper was potentially willing to grant an easement over the Kingsnorth land to
Drax
at an open market rate, but over a different route which would lead to increased costs. It added that if
Drax
was unable to agree suitable terms with Uniper, it might need to consider applying for a compulsory purchase order.
Drax
contended that it had a claim against Scottish Power, as I have summarised them. It explained that the Company had been sold to VPI, but added that:
'37.Drax
remains liable for any and all losses suffered by [the Company] in relation to the Reorganisation, and the fact that the Reorganisation (or any part thereof) was not implemented and completed in full prior to the date of the [Agreement], or the fact that the Reorganisation (or any part thereof) was not implemented and completed correctly in accordance with the Reorganisation Documents.'
'40. In the circumstances, the loss suffered is yet to crystallise. As such, we set out below the details of the likely heads of loss (in relation to both the potential terms that may be agreed with Uniper and in the event that such agreement is not reached and a compulsory acquisition is required) and where possible an estimate of the potential loss that is likely to be suffered. Given the unique circumstances of this matter, this is of course an estimate andDrax
reserves the right to update the loss suffered as matters develop and the loss is crystallised.'
The proceedings
Drax
issued its claim form on 22nd December 2021, within the six-month period referred to in paragraph 3 of Schedule 4. The Particulars of Claim set out the various ways in which
Drax
puts its claim and pleads its losses in accordance with the way in which the loss was identified in the Notice of Claim. The pleading makes clear that the alleged losses to be incurred in obtaining the easement (whether by negotiation or by compulsory acquisition) and the increased cost of laying cables over the Kingsnorth land were losses which would be suffered by the Company rather than by
Drax
itself.
Drax
had made no demand pursuant to those clauses, that being an essential element of the claim, and it was now too late to do so.
Drax
did not attempt to defend the Particulars of Claim as originally pleaded. Instead it sought permission to amend. The draft amendment deleted references to the Company suffering the loss and pleaded a case that the loss was suffered by
Drax
alone; that loss was suffered at the Completion Date and consisted of the difference between (a) the warranted value of the Company (i.e. its value with the benefit of the Damhead Creek II Option Agreement) and (b) its true value (i.e. without the benefit of those rights); the cost of obtaining an easement by negotiation with Uniper, together with the increased cost of laying cables over a longer route, was evidence of this difference in value; and a case based on compulsory acquisition was no longer advanced.
Drax
for permission to amend the Particulars of Claim. Both applications turned on the same point, whether the reformulated claims in the draft Amended Particulars had a real prospect of success.
The judgment
Drax
was liable; that the Notice of Claim therefore did not reflect the claim for
Drax's
own loss based on a difference in value which
Drax
now sought to bring in the draft Amended Particulars of Claim; and that (if that was the claim which
Drax
now sought to bring), the fact that the claim was one based on the difference in value of the shares had to be notified in the Notice of Claim:
'86. I have already set out the text of paragraph 2 of Schedule 4 of the [Agreement]. Pursuant to its terms, in order for Scottish Power to be liable for a claim,Drax
had to, in its notification of that claim: (i) state in reasonable detail the nature of the claim; and (ii) state in reasonable detail the amount claimed (detailing
Drax's
calculation of the loss thereby suffered).
87. In my view, each of those requirements meant that, ifDrax's
claim was one based on the diminution in value of the shares in the Company at the point of
Drax's
discovery of Scottish Power's breaches, as is now the claim sought to be brought in the Amended Particulars of Claim, that had to be identified in the Notice of Claim.'
Drax's
calculation of the claim. This fact had not been stated in the Notice of Claim. As a result the claim pleaded in the draft Amended Particulars had no real prospect of success:
'101. Accordingly, the Notice of Claim did not state in reasonable detail the nature of the claim or the amount claimed (detailingDrax's
calculation of the loss thereby alleged to have been suffered). If
Drax's
claim was one based on the diminution in value of the shares in the Company at the point of
Drax's
discovery of Scottish Power's breaches, as is now the claim sought to be brought in the Amended Particulars of Claim (or indeed at any earlier date such as the date the shares were transferred), that ought to have been identified in the Notice of Claim. In fact, a different basis for
Drax
having suffered loss was identified, namely that
Drax
bore a liability for losses suffered by the Company.
102. The result is that the Notice of Claim did not comply with paragraph 2 of Schedule 4 to the [Agreement] in relation to the warranty claim and the other breach of contract claim. There is therefore no real prospect of Scottish Power being liable for those claims, and summary judgment on those claims ought to be granted to it.'
Drax's
claim, based as it was on the failure to provide the Company with the benefit of the Damhead Creek II Option Agreement, fell within the definition of a Damhead Creek II Option Agreement Claim so that the applicable deadline for a notice of claim was 30th June 2021; that because the obligation under clause 11.1 was to pay within five business days of a demand, no liability could arise under clauses 11.1.3 and 11.1.4 until a written demand for payment of an ascertained sum had been sent; that there had been no such demand in the Notice of Claim (or for that matter in the original Particulars of Claim); and that although there had been a demand in the draft Amended Particulars, that came too late because it was after the deadline for a Damhead Creek II Option Agreement Claim.
'113. First, … Scottish Power contends that it was not open toDrax
to make a demand under clause 11.1 in its draft amendments because, by that date, the relevant time limit in paragraph 2 of Schedule 4 had expired. That presupposes that the time limits in paragraph 2 of Schedule 4 apply to the making of a demand under clause 11.1.
114. However, in my judgment, the time limits under para 2 Schedule 4 do not so apply. As Mr Quest, forDrax,
contended, there are two requirements and they are independent. The first (in clause 11.1) requires the demanding of an ascertained sum by written notice, the second (in paragraph 2 of Schedule 4) requires a notice of the claim, stating in reasonable detail the nature of the claim and the amount claimed, etc. They are two separate requirements. There are specific time limits in respect of the second of those, as set out in paragraph 2 of Schedule 4, and a notice needs to be sent before the relevant time period expires. There is no such time limit in relation to the demand required by clause 11.1.
115. There is nothing in the wording of the SPA, or in any material context that was drawn to my attention, that suggests that the demand under clause 11.1 had to meet the requirements not only of clause 11.1 but also of paragraph 2 of Schedule 4.'
'125. …
(1) Before the amendments that led to the introduction of the defined term "Damhead Creek II Agreement Claim", there would have been no argument about which time period applied to a Reorganisation Indemnity Claim. Such a claim was not within paragraph 2.1.1 because the definition of Relevant Claim excluded a Reorganisation Indemnity Claim, and such a claim was covered separately at paragraph 2.1.7. The amendments made were to carve out from paragraph 2.1.1 any Damhead Creek II Option Agreement Claim that fell within the definition of "Relevant Claim", such that any such claims were no longer subject to the 18 month period under that paragraph, and to give them a longer time period. Those claims that were removed from paragraph 2.1.1 were given their own time period in paragraph 2.1.10. In other words, the parties were introducing a new paragraph 2.1.10 to apply only to Damhead Creek II Option Agreement Claims which were Relevant Claims (and thus not a Reorganisation Indemnity Claim). There were no words added expressly removing any Reorganisation Indemnity Claim from paragraph 2.1.7 nor any other indication that the parties intended to remove any Reorganisation Indemnity Claim from paragraph 2.1.7 such as also to place such a claim within paragraph 2.1.10. (2) During 2021, there was good reason to extend the notification period for claims, given this allowedDrax
further time to explore how much Uniper might charge for a new easement of the Kingsnorth land. However, there is no obvious reason why the parties would have intended to shorten (considerably) the period for bringing a Reorganisation Indemnity Claim just because it was also a Damhead Creek II Option Agreement Claim. …'
Drax's
appeal – the submissions in outline
Drax,
Mr David Quest KC submitted that the Notice of Claim gave sufficient detail of the 'nature of the claim' and stated in reasonable detail the amount claimed and
Drax's
calculation of the loss suffered. In particular, it was unnecessary to state that the claim was based upon a difference in value of the shares in the Company. This was not part of the 'nature of the claim' and did not have to be identified in order to give reasonable details of the amount claimed. All that
Drax
was required to say was that it was a claim in contract for damages for breaches of specific provisions and for an indemnity, and that it related to the failure of Scottish Power to transfer the benefit of the option to the Company. He submitted further that, because difference in value is the conventional measure of damages in such a case (Lion Nathan Ltd v C-C Bottlers Ltd [1996] UKPC 9 at [9], [1996] 1 WLR 1438, 1441; MDW Holdings Ltd v Norvill [2022] EWCA Civ 883 at [24]), a reasonable recipient would have understood that damages for the breaches alleged would be assessed on that basis, and the Notice of Claim should have been understood accordingly.
Drax
not only to identify the loss claimed, but also the basis on which it was claimed, including the nature of its case on causation. In the case of a difference in value claim, it was necessary to identify the value of the shares as they ought to have been with the benefit of the option and as they in fact were. That information would be needed in order for Scottish Power to obtain valuation evidence.
Notice of Claim clauses
'46. … The purpose of a notice clause such as that in schedule 4 para 2(b) of the SPA is to enable the recipient to make such inquiries as it is able, and would wish, to make into the factual circumstances giving rise to the claim, with a view to gathering or preserving evidence; to assess so far as possible the merits of the claim; to participate in the tax investigation to the extent desirable or possible with a view to influencing the outcome; and to take into account the nature and scope of the claim in its future business dealings, whether by way of formal reserving or a more general assessment of the potential liability. As Mr Choo-Choy accepted, the additional detail available, if included in the 24 June letter, would not have advanced any of these purposes. I balk at a conclusion that the level of detail provided in a notice of this sort fell short of what was required as reasonable, that is to say was unreasonably deficient, when the additional level of detail said to have been required would not have furthered any of the commercial purposes for giving such a notice. What is reasonable takes its colour from the commercial purpose of the clause, and what businessmen in the position of the parties would treat as reasonable. Businessmen would not expect or require further detail which served no commercial purpose. That would be the antithesis of what was reasonable.'
'18. In my judgment the underlying rationale for the principle that, if necessary to resolve ambiguity, exclusion clauses should be narrowly construed has nothing to do with the identification of the proferens, either of the document as a whole or of the clause in question. Nor is it a principle derived from an identification of the person seeking to rely upon it. Ambiguity in an exclusion clause may have to be resolved by a narrow construction because an exclusion clause cuts down or detracts from the ambit of some important obligation in a contract, or a remedy conferred by the general law such as (in the present case) an obligation to give effect to a contractual warranty by paying compensation for breach of it. The parties are not lightly to be taken to have intended to cut down the remedies which the law provides for breach of important contractual obligations without using clear words having that effect: see Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 per Lord Diplock at 717H, applied in Seadrill Management Services Ltd v OAO Gazprom [2010] EWCA Civ 691, by Moore-Bick LJ at para 29.
19. This approach to exclusion clauses is not now regarded as a presumption, still less as a special rule justifying the giving of a strained meaning to a provision merely because it is an exclusion clause. Commercial parties are entitled to allocate between them the risks of something going wrong in their contractual relationship in any way they choose. Nor is it simply to be mechanistically applied wherever an ambiguity is identified in an exclusion clause. The court must still use all its tools of linguistic, contextual, purposive and common-sense analysis to discern what the clause really means. In the Seadrill Management case Moore-Bick LJ described the principle as:
"essentially one of common sense; parties do not normally give up valuable rights without making it clear that they intend to do so".'
Drax's
appeal – Discussion
Drax's
Notice of Claim as advancing a claim based on the difference in value of the shares. Mr Quest relied on the reference to 'the losses alleged to have been suffered' in the opening paragraphs of the notice (see para 30 above), submitting that this referred to past losses already suffered by
Drax.
A fair reading of the notice as a whole, however, makes clear that the loss claimed consists of a future liability to VPI, to whom the Company had been sold. Thus paragraph 37 explained that
Drax
remained liable for any and all losses suffered by the Company; and paragraph 40 explained that 'the loss suffered is yet to crystallise' and referred to 'details of the likely heads of loss' and 'the potential loss that is likely to be suffered', while reserving the right to 'update the loss suffered as matters develop and the loss is crystallised'.
Drax's
claim, as it does not appear that the price obtained for the Company from VPI was affected by the Company's inability to obtain an easement over the Kingsnorth land. Nor has it been suggested that
Drax
has in fact any legal liability to VPI as a result of the Company not having the benefit of such an easement. However, a reasonable recipient would not be aware of this and would be entitled to take at face value what was said in the Notice of Claim. Importantly, there has been no challenge to
Drax's
good faith in formulating its claim in the way set out in the Notice of Claim.
Drax
sought to advance was straightforward. It was simply a claim that under the terms of the Agreement, the Company ought to have had the benefit of the Damhead Creek II Option Agreement, but did not. Mr Quest was prepared to accept that
Drax
was required to identify the terms of the Agreement of which Scottish Power was in breach, but I am not sure that even this was necessary. A simple statement that Scottish Power had failed in its obligation to ensure that the Company had the benefit of the Damhead Creek II Option Agreement would have told Scottish Power all that it needed to know, not least as the parties had been in correspondence about this very issue for over a year. If Scottish Power was in any doubt about its contractual obligations, including which terms required it to provide the Company with the benefit of the Damhead Creek II Option Agreement, it had only to read the Agreement or to ask a lawyer for advice. If it wished to investigate whether it had a defence to the claim, perhaps on the ground that the problem with the option agreement had been disclosed to and accepted by
Drax,
it would know in which files to look or which individuals to ask. If it wished to assess its potential liability, including the likely basis on which damages would be assessed, it would be able to obtain legal advice. In practice, of course, it is likely that Scottish Power had already done all these things as a result of the parties' previous correspondence.
Drax
to spell out, as part of a statement as to the nature of the claim, that the damages claimed would be based on the difference in value of the shares in the Company as a result of not having the benefit of the Damhead Creek II Option Agreement. To impose such a requirement serves no commercial purpose and merely introduces a trap to defeat what may be a valid claim.
Drax's
actual calculation of the loss which it was claiming. As
Drax's
good faith in formulating the claim in this way has not been challenged, what was put forward was 'the Buyer's calculation of the Loss thereby alleged to have been suffered'.
Drax
retained a liability to VPI. It could have taken legal advice. If that advice had been that the basis of calculation was legally unsound, because it ought to have been based on a difference in value as at the Completion Date, it could have obtained whatever expert valuation evidence it might need in order to refute the way in which the claim was put. If it thought that the sums claimed by
Drax
were excessive, it could have offered to take over the negotiations with Uniper in order to obtain a better deal. If it thought it necessary to make a reservation in its accounts, it could have done so.
Drax's
appeal should be allowed.
Further Information
Drax,
he would have ordered
Drax
to provide further particulars of the damages claim pleaded in the draft Amended Particulars of Claim. We heard little or no submissions about this and were not provided with any Request for Further Information. I would leave the Circuit Commercial Court to decide whether further particularisation is needed.
Scottish Power's appeal – the submissions in outline
Drax's
appeal succeeds, as I have held that it should, it is not clear to me whether the alternative claim for an indemnity adds anything of substance. The pleaded calculation of the amount claimed is the same for both ways of putting the case, damages and an indemnity. Nevertheless I will consider briefly Scottish Power's appeal against the judge's decision that
Drax's
claim for an indemnity pursuant to clauses 11.1.3 and 11.1.4 of the Agreement is not barred.
Scottish Power's appeal – Discussion
Drax's
indemnity claim was seven years from the Completion Date.
Declaration
Drax
has pleaded a claim for a declaration of Scottish Power's liability to indemnify it in terms which appear to do no more than track the language of clauses 11.1.13 and 11.1.4 of the Agreement. Scottish Power contends that such a declaration would serve no useful purpose as there is no dispute about the terms of these clauses. The judge said that he could see the force of that point, but that the granting of declaratory relief was discretionary and the extent to which any particular declaration might serve a useful purpose was a matter for the trial. I would not disturb that case management decision.
Disposal
Drax.
Drax's
claims for damages are not barred by the Notice of Claim clause. I would therefore dismiss Scottish Power's application for summary judgment and would grant permission to
Drax
to amend its Particulars of Claim.
Drax's claim for an indemnity under clause 11.1 is not barred either.
LORD JUSTICE BIRSS:
SIR GEOFFREY VOS, MR: