You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> CIB Properties Ltd. v Birse Construction [2004] EWHC 2365 (TCC) (19 October 2004) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2004/2365.html Cite as: [2005] 1 WLR 2252, [2005] WLR 2252, [2005] BLR 173, [2004] EWHC 2365 (TCC) |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Buy ICLR report: [2005] 1 WLR 2252]
[Help]
QUEEN'S BENCH DIVISION
TECHNICAL &
CONSTRUCTION
COURT
B e f o r e :
____________________
CIB PROPERTIES LIMITED |
Claimant |
|
| - and - |
||
BIRSE CONSTRUCTION | Defendant |
____________________
VIVIAN
RAMSAY QC & MR LEE (instructed by Messrs Shadbolt & Co)
Counsel for the Defendant: MR PAUL DARLING QC & MISS SARAH HANNAFORD instructed by Messrs Hammonds)
Hearing date : 19 October 2004
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
CIB
Properties
Limited (
CIB)
to enforce the decision of the Adjudicator, John Uff CBE QC, made on 24th February 2004 that
Birse
Construction
Limited (
Birse)
should pay
CIB
£2,164,892.
Birse
seeks to prevent the enforcement of the Adjudicator's award by raising a number of defences including the plea that adjudication is inappropriate in a dispute of this complexity. This is a defence which goes to the root of the adjudication process. The point has not previously been decided.
CIB's
application is contested are set out in paragraph 18 of the defence and have been amplified in detailed and most helpful submissions. They are:
A. There was no dispute in being at the date of the notice of adjudication so that the Adjudicator had no jurisdiction to hear and determine the matters before him.Birse
says that any possible dispute had not crystallised because there were ongoing discussions to resolve
CIB's
claim and
CIB
had agreed to a further meeting due to take place after
CIB
served the notice of adjudication.
B.Birse
claims that the adjudication could not be and was not conducted fairly and impartially because
(a) it was irredeemably prejudiced byCIB's
tactics and conduct before the notice of adjudication was served which meant that
Birse
was put at a disadvantage before the adjudication started which could not be cured. The limited and piecemeal extensions of time given to
Birse
in the course of the adjudication could not eliminate the prejudice which had already taken place.
(b) The pressure, which not onlyBirse
but also the Adjudicator was under, led the Adjudicator to act unfairly and to the prejudice of
Birse
in relation to (i) the time for
Birse's
response; (ii) the timetable and timescales generally; (iii) the expert evidence and; (iv) the documentation generally.
(c) It led the Adjudicator, because of pressure, into making a slip in his award which transformed what should have been an award inBirse's
favour into the present award in favour of
CIB.
![]()
C. The size and complexity of the dispute meant that it could not be resolved fairly by adjudication.
Birse
cites in support comments made by Judges in other adjudication cases.
D. The Adjudicator made a slip which the court has power either to correct itself or, in the circumstances of this case, the court has power to invite the Adjudicator to correct.Birse
contends that the Adjudicator decided in section 9 of his decision that
Birse
had no liability for defects in the cladding but in section 14 of his decision he awarded
CIB
the costs of remedial works in relation to defects in the cladding for which, in section 9, he had said that
Birse
was not liable.
Birse
contends that the Adjudicator's letter in response to their own constituted exceptionally an invitation to the court to make a finding on this issue which the court should accept.
Birse
relied on two other defences which are no longer being pursued: (a) that the allegation that the service of new documents with the referral notice created a new dispute and; (b) that
Birse
was entitled to set off its own claim against
CIB's
enforcement claim.
The Law
Construction
and Regeneration Act 1996 (the Act). Section 108 of the Act provides as follows:
"108(1) A party to aconstruction
contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose 'dispute' includes any difference.
(2) The contract shall
(a) enable a party to give notice at any time of his intention to refer a dispute to adjudication;
(b) provide a timetable with the object of securing the appointment of the Adjudicator and referral of the dispute to him within 7 days of such notice;
(c) require the Adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
(d) allow the Adjudicator to extend the period of 28 days by up to 14 days with the consent of the party by whom the dispute was referred;
(e) impose a duty on the Adjudicator to act impartially and;
(f) enable the Adjudicator to take the initiative in ascertaining the facts and the law."
Construction
Contracts (the Scheme) provides that:
"the Adjudicator shall act impartially in carrying out his duties and shall do so in accordance with any relevant terms of the contract and shall reach his decision in accordance with the applicable law in relation to the contract."
v
Weijl (UK)
Ltd
[2003] 91 CLR 173. It is clear that Parliament has introduced an intervening stage in
construction
disputes which enables the parties to achieve a temporary solution in advance of the full process of litigation or arbitration.
Vol
571 cols 989-990):
"Adjudication is a highly satisfactory process. It comes under the rubric of 'pay now argue later' which is a sensible way of dealing expeditiously and relatively inexpensively with disputes which might hold up completion of important contracts."
very
costly. I was told that
CIB's
costs of the two adjudications amounted to £973,732.41 and
Birse's
costs to £1,161,341.70, in each case excluding
VAT.
To this must be added the Adjudicator's costs in the two adjudications. The Adjudicator's costs in the second adjudication amounted to over £150,000. This could not be described as inexpensive.
very
many cases where adjudication (or the threat of adjudication) leads to the early resolution of the dispute. They also perceive it to be an advantage that, unlike ordinary litigation, each party bears its own costs in any event and it is only the cost of the Adjudicator that can be the subject of a conventional order.
v
Morrison
Construction
Limited [1999] CLR 1 6:
"The timetable for adjudication isvery
tight (see section 108 of the Act). Many would say unreasonably tight and likely to result in injustice. Parliament must be taken to be aware of this."
"Parliament has not abolished arbitration and litigation ofconstruction
disputes. It has merely introduced an intervening stage in the dispute resolution process."
(a) There must be a dispute arising under aconstruction
contract which is capable of being referred to adjudication.
(b) Notice must be given to the other party to refer that dispute to adjudication.
(c) A timetable must be provided under which, if there is no designated Adjudicator, the Adjudicator must be appointed within 7 days.
(d) The Adjudicator must reach a decision on the dispute which has been referred to him.
(e) The Adjudicator must (subject to (f) below) reach his decision within 28 days of the referral or such longer period as is agreed by the parties after the dispute has been referred.
(f) The Adjudicator is permitted to extend the 28 day time limit to up to 42 days with the agreement only of the referring party.
(g) The Adjudicator has an overriding duty to act fairly and impartially. This requires the Adjudicator to direct the procedure so that each party has a proper and equal opportunity to present its case.
v
Sopex Oils [1998] 1 WLR 726 at 761. Whether there is a dispute depends on the ordinary meaning of the word and the facts of the case. In Halki, Swinton Thomas LJ citing a passage of Templeman LJ in Ellerine Brothers
v
Klinger [1982] 1 WLR 1375 held that in appropriate cases, where there had been a demand, a dispute could be inferred to exist where a party had failed to respond to the demand.
v
Solland [unreported June 2001] a decision approved by Forbes J in Beck Peppiatt
v
Norwest Holst [2003] EWHC 822 (TCC) His Honour Judge Lloyd QC carried the analysis of what is a dispute a stage further. He said:
"For there to be a dispute for the purpose of exercising the statutory right of adjudication it must be clear that a point has emerged, given the process of discussion or negotiation has ended and there is something that needs to be decided."
CIB
starting an adjudication
Birse
was anxious to keep discussions going so that it could say that the process of negotiation had not ended.
view
the test is whether, taking a common sense approach, the dispute has crystallised. Even after it has crystallised, parties may wish to have further discussions in order to resolve it. Whether or not it has, in fact, crystallised will depend on the facts in each case including whether or not the parties are in continuing and genuine discussions in order to try to resolve the dispute.
v
Barrett [2001] BLR 207, Discain Project Services
v
Opecprime Development
Ltd
[2000] BLR 402 and McAlpine PPS Pipeline Systems Joint
Venture
v
Transco TCC No HT-04-66 judgment 12 May 2004). There are a number of decisions where the court has refused to enforce a decision where the Adjudicator has conducted the procedure in a manner which is unjust or to the unfair disadvantage of a party.
Birse
challenges the Adjudicator's decision not only on specific grounds but also on the general ground that the dispute was too complex to be decided by means of adjudication.
Birse
cites in support comments of Judges in previous cases. In particular in London and Amsterdam
Properties
v
Waterman Partnership [2004] 1 BLR 179 196 His Honour Judge Wilcox said at paragraph 146:
"It must also be recognised that there may be some disputes, particularly arising at the end of a project, which are too complex to permit a fair adjudication process within the time limits of the scheme."
v
Rockingham Motorway Speedway Limited [2004] EWHC 888 (TCC) at paragraph 123 I raised the possibility that there may be disputes which are so complex and the advantages of the procedure are weighted to such an extent against the defendant that there is a conflict between the right to refer to adjudication and obtain a decision within the time limits laid down in section 108(2)(c) and (d) and the Adjudicator's duty to act impartially under section 108(f) of the Act. I went on to suggest (erroneously as I now think) that this was a conflict which it might be impossible to resolve.
CIB
that if a defendant agrees to one extension of time, it must be taken to have agreed to further necessary extensions of time. I do not agree that this is necessarily the case. It will depend in each case on the circumstances in which the initial extension of time is agreed. There will be cases where this is a proper inference. There will be other cases where no such inference can be drawn, for example, where a defendant has made it clear that the initial extension of time is agreed without prejudice to any further extensions. The test is not, therefore, whether the dispute is too complicated to refer to adjudication but whether the Adjudicator was able to reach a fair decision within the time limits allowed by the parties.
v
Dahl-Jensen [2000] 1 WLR 525 (paragraph 12), "Did he answer the right question or questions?"
Birse
has an additional argument that there was a slip which the Adjudicator should be ordered, or at least encouraged, to correct.
Birse
cites in support my decision in Bloor
v
Bowmer and Kirkland [2001] BLR 314.
CIB
argues that this decision was wrong but says that in any event it does not go far enough to assist
Birse
in the present circumstances.
v
Bowmer and Kirkland I said at page 319:
"In the absence of any specific agreement to the contrary, a term can and should be implied into the contract referring the dispute to adjudication that the Adjudicator may, on his own initiative, or on the application of a party correct an error arising from an accidental error or omission. The purpose of the adjudication is to enable broad justice to be done between the parties. Parties acting in good faith would be bound to agree at the start of the adjudication that the Adjudicator could correct an obvious mistake of the sort which he made in this case."
v
Cripps and Muldoon [1984] QB 686:
"It is a distinction between having second thoughts and intentions and correcting an award to give effect to first thoughts or intentions which creates the problem. Neither an arbitrator or a judge can make any claim to infallibility. If he assesses the evidence wrongly or misappreciates the law the resulting award or judgment will be erroneous but it cannot be corrected under section 17 (of the Arbitration Act 1950) or under the old Order 20 Rule 11. It cannot normally be corrected under section 22 (where the arbitrator has made a mistake). The remedy is to appeal if the right of appeal exists. The skilled arbitrator or judge may be tempted to describe this as an accidental slip but this is a natural form of self-exculpation."
"This enables the arbitrator to make an award on a claim which he has inadvertently overlooked such as an award of interest or to correct errors of accounting or arithmetic such as attributing a credit item to the wrong party but the section does not give the arbitrator licence to give effect to second thoughts on a matter on which he has made a conscious judgment."
Birse
must overcome in relation its claim that the adjudicator made a slip which should be corrected. The threshold question is whether the Adjudicator is prepared to admit or correct the slip at a time when it does not prejudice the other party. If the Adjudicator is not prepared to make a correction promptly that is an end of the matter. In Bouygues
v
Dahl-Jensen there was an error by an adjudicator which at page 55 Dyson J concluded was a mistake which fell into the category of a slip. The Adjudicator refused to admit or correct the mistake. Dyson J held that the Adjudicator's decision had to stand because the Adjudicator was not exceeding his terms of reference:
"He was doing precisely what he was asked to do and was answering the right question albeit in the wrong way."
The appeal was dismissed (see [2001] BLR 522) The Court of Appeal held that (subject to a separate point relating to bankruptcy law) Dyson J had stated correctly the relevant law and its application to that case.
v
Sevenoaks District Council [decided 14th April 2000] a few days after Bloor when he concluded in relation to the decision in Bloor:
"In myview,
putting the matter at its lowest, it is at least arguable that it is right."
very
limited and narrow application. In this case I am being asked by
Birse
to say that the court should review the Adjudicator's decision, conclude that he has made a slip, and either invite or order him to amend his decision. This is a
very
difficult argument on which to succeed in the light of the existing law.
Birse
contends that while under existing law this may normally be the case, the position is different where the Adjudicator has invited the court to rule on the matter. I shall consider this argument after I have considered the Adjudicator's letter dated 19th March 2004 in response to
Birse's
request that he reconsider his decision.
The facts
CIB
and
Birse
entered into a contract dated 8th August 2000 for the
construction
of a new building which was to be called the Riverdale Data Centre, Molesworth Street, London E13.
CIB
was to be the owner of the
property
and
Birse
was the main contractor. Clause 16.14.3 of the contract provided:
"Owner or contractor may at any time give written notice of its intention to refer any dispute arising under the contract forconstruction
to adjudication. The adjudication provisions of the Scheme for
Construction
Contracts shall apply."
"19(i)(c) such period exceeding 28 days after the referral notice as the parties to the dispute may, after the giving of that notice, agree."
In other words, the contract was in conformity with the Act that any extension of time beyond the 28 days required the agreement of both parties (subject to the exception of up to 42 days at the request of the Adjudicator).
CIB
terminated the contract. As a result of the termination three categories of claim were made which were later categorised as E1, E2 and E3. E1 was
Birse's
claim based on its final account up to termination of the contract. E2 was
Birse's
claim for the cost of completing the works on the basis that
CIB
had terminated the contract wrongfully. E3 was
CIB's
claim for the additional cost of completing the works after
Birse
had left the site over what
CIB
would have had to pay under the contract with
Birse.
This claim only arose if
CIB
was entitled to terminate the contract see article 14.2.4 of the contract. Since
CIB's
claim related to the time after
Birse
left site,
Birse
was largely reliant on
CIB's
documents to enable it to evaluate
CIB's
claim.
CIB
wrote to
Birse
claiming that
CIB
had a number of specific claims under the contract which amounted in total to a sum in the region of £7,500,000 and that
CIB's
total claim amounted in total to £9,000,000 excluding
VAT
and finance charges.
CIB
gave notice that it proposed to proceed to arbitration.
Birse
gave notice that it was referring to adjudication the issue of whether or not
CIB
was entitled to terminate the contract. It gave
CIB
no advance warning and it is clear that this step took
CIB
by surprise and annoyed it. From June 2002
Birse,
unknown to
CIB,
had prepared witness statements and a "
Birse
case matrix" in preparation for the adjudication.
Birse
was strictly entitled to refer the matter to adjudication,
CIB
felt that it was a less than open way of dealing with the dispute that had arisen. I have little doubt that this referral to adjudication soured the relationship between the parties and was at least partly responsible for the subsequent secretive conduct of
CIB.
Birse's
contentions,
CIB
was entitled to terminate the contract and that the termination was not wrongful.
Birse,
wrote to Mr Dupont, regional head of Corporate Realty Services of
CIB,
giving notice that
Birse
would not accept Mr Bowdery's decision as final.
Birse
on 27th September 2002 in which
CIB
claimed sums in the region of £11 million and said that when the final determination was completed
CIB
would make a demand for payment. On 17th September 2002, Mr Hart had already been engaged with five assistants to work on
CIB's
detailed claim.
"We note your statement that final costs are likely to exceed £11 million. No doubt we will be given the opportunity to comment on your arguments andvaluation
in due course. Notwithstanding the issue of termination, our own final account which is in preparation for the works will be in the region of £11.25 million including
VAT
but excluding legal costs and finance charges. We will, however, forward to you our
version
of the final account upon its completion so as to facilitate dialogue on the amounts payable either way. It is regrettable, and notwithstanding arguments as to fault, that the project came to an unseemly end. However, we in return give notice that we will continue to pursue our own entitlements under the contract."
"He has full authority to deal with this matter and it is his remit to bring it to resolution. Therefore, please address all future correspondence and communication to him at our Northampton office. This will ensure prompt attention is given to any matters raised."
construction
and engineering disputes. He said that
CIB
would issue its demand once the final costs had been determined.
Birse's
earlier referral to adjudication.
Birse
on 14th November 2002, he set out his understanding in relation to
Birse's
claim for payment and
CIB's
claim for the cost of completion of the works. Mr Atkinson said that
Birse
told him that the full claim would be submitted towards the end of January 2003. He said that
CIB
anticipated that particulars of the major part of its costs would be available in the near future and that
CIB
would confirm the precise date by the end of the following week.
CIB
was not yet in a position to give a definitive time scale for its demand for payment. In fact, the demand for payment was served on 28th July 2003.
Birse,
wrote to Mr Atkinson saying:
"We believe it would be sensible to proceed to the provisional appointment of a mediator for a mediation to take place during March next year."
Birse
instructed Dr Wolmuth as their cladding expert in relation to the proposed mediation. The proposed mediation did not, in fact, take place. On 19th February 2003 Mr Atkinson wrote to Mr Hilton at Hammonds in relation to their discussion on the postponement of the mediation from 3rd March 2003 to July 2003:
"As previously advised, our client has not and does not irrevocably agree to mediation."
"For the avoidance of doubt, the above is without prejudice to our client's right to issue any demand for payment pursuant to the terms of the contract forconstruction
dated 8th August 2000 and to pursue any remedies contractual or otherwise."
CIB
to be reserving its rights in open correspondence.
CIB
could not finalise what was later known as the E3 claim, namely costs of completing the work after
Birse
had left the site.
CIB
sent a letter signed by Mr Dupont to
Birse
addressed to Mr Budden at the Barton-on-Humber office demanding payment within 30 days of sums totalling £16,609,154.98.
CIB
reserved the right to claim further sums in respect of existing and further breaches of the contract. The letter was accompanied by Mr Hart's expert report. Both the demand letter and Mr Hart's expert report made reference to what has been referred to as the 52 files of supporting documents which became the subject of a wrangle over photocopying. These were declared to be available for inspection.
"Should contractor not respond to these demands for payment within the time limits indicated, owners will conclude that its entitlement of payment is disputed. In that case, owner reserves the right to take all available steps to enforce its legal rights as set out in this letter without further notice to contractor."
Birse
rightly treats this as part of the history. Having read the documents and heard from Mr Atkinson, I have no doubt that
CIB
was prepared to conduct matters in as hardnosed a way as it felt it was able to, subject only to acting in a way which it regarded as correct.
Birse
claimed it was seriously prejudiced, I am not persuaded that in sending the demand to Mr Budden at Head Office rather than to Mr Heath at Northampton,
CIB
was being deliberately obstructive.
Birse
on 6th August 2003.
Birse
was able to discuss it with its solicitors on 19th August 2003. It was holiday time and had the 30 day deadline been strictly adhered to, and at the end of it there had been a referral to adjudication, a court might well have concluded that
Birse
had not been given a sufficient opportunity to consider the claim and make its response and that, therefore, a dispute or difference had not yet arisen.
CIB
did not take this course.
Birse,
called "a
very
meaty document" or that it had taken a
very
substantial amount of time to prepare. Gardner and Theobald were engaged in January 2002 to produce lengthy and detailed reports on
valuations
1 and 2. They produced reports in August 2002 and a further
valuation
report in June 2003. Mr Hart was instructed by
CIB
in June 2002 to work on quantum. He was assisted from 17th September 2002 by a team of five primary assistants and some eight others. By the date of the demand, Mr Hart's team had spent 2,500 hours working on the quantum claim. It is also clear that
CIB
had been working on the documents since October/November 2002.
CIB's
experience in relation to the first adjudication it had in mind from the end of 2002 that it would be likely to proceed to adjudication and that its preparation of the documents and exhibits was undertaken with this in mind. This preparation continued up to the time when the notice of referral was served.
CIB
memorandum of 30th July 2003 says:
"The demand states that unless payment is received within 30 days we will deem it to be disputed and hence adjudication will then follow."
"We are gearing up for a second adjudication."
CIB's
claim, E3, but also with
Birse's
claims, E1 and E2. E1,
Birse's
claim on the final account, was the subject of Mr Hart's report served with the letter of claim of 28th July 2003. Mr Hart assessed the claim at £26,509,533.95. When
Birse
served its draft final account on 25th September 2003 it
valued
the costs of the works to termination at £34,335,483.31. E2,
Birse's
claim for the costs of completing the works under the contract, was assessed by Mr Hart in his report at £21,769,940.60. E3, the additional cost to
CIB
of completing the works, was assessed by Mr Hart in his report at £14,646,798.94. In his later report of 3rd November 2003, the sum claim was increased to £14,687,205.63. In the event, the Adjudicator awarded the sum of £2,164,892.
Birse's
response to the letter of demand was dated 27th August 2003. It asked for some general initial questions and suggested a meeting.
CIB's
response dated 28th August 2003 was rather uncompromising in tone. It noted that
Birse
had not inspected the 52 files. It said that the answers to
Birse's
questions were in the documents provided in the first adjudication and in the quantum reports of Gardner and Theobald and Mr Hart. It requested details of
Birse's
disagreement with
CIB's
determination. It repeated the demand for payment and stated baldly:
"In the absence of the aforesaid payment,CIB
reserves the right to take all available steps to enforce its legal right as set out in the demand without further notice."
73.CIB's
letter does indicate agreement, without prejudice, to a meeting. It ends by looking forward to
Birse's
early payment on the demand.
74. There follows considerable correspondence between the parties.CIB's
letters, including those ostensibly from Mr Dupont, read like solicitors' letters attempting to put
CIB
in a good light. The
various
references to
CIB
adopting an open and candid approach (see eg the letter of 10th September 2003) sound hollow in the context of the existing plan without any direct warning to proceed to adjudication, as was clear from the internal correspondence.
CIB
had a referral to adjudication already prepared in draft and that they expected to serve it in the week of 6th October 2003.
Birse
served its final draft account to
CIB.
It ran to 14
volumes.
Birse
also gave a
very
limited response to
CIB's
demand which consisted of a list of 126 detailed questions. It was put together by
Birse
staff in preparation for the meeting due on 2nd October 2003. Mr Hilton of Hammonds said in evidence that he was not involved in this exercise.
Birse
was not deceived by
CIB's
tactics. They were aware that
CIB
might at any stage refer the dispute to adjudication. Their own tactics were to try to avoid this by trying to avoid the dispute being regarded as crystallised. On 30th September 2003 Hammonds wrote to Mr Ashworth of Davies Langton and Everest instructing him as an expert. The third short paragraph states: "Please note these instructions are urgent there is a strong risk that
CIB
will shortly commence an adjudication."
"There is a real risk that Citibank may refer the entirety of the claim or discrete parts of it to adjudication in the immediate future."
"At the time of receiving the demandBirse's
greatest concern was that Citibank would refer the demand to adjudication.
Birse
adopted a tactic of questioning the claimant to clarify issues while avoiding crystallising the dispute."
view
both sides were jockeying for tactical advantage in a way which is apparently permitted in adjudication but is not permitted in current litigation practice.
CIB
was concerned, a week or two weeks away from completion. Mr Dupont agreed that this fact was not mentioned to
Birse
at the meeting later in the day. It was this type of conduct which I referred to earlier as secretive although it did not, in fact, mislead
Birse.
CIB's
internally agreed tactics for the meeting were to arrange a mediation within the following two weeks with authority to settle. This would fit into the timetable of the referral to adjudication which would not yet be complete. I am satisfied that
CIB
was prepared to enter into a genuine mediation but only on the basis that if it failed it would not deflect
CIB
from its timetable for referral to adjudication.
Birse
claims that the referral to mediation was merely a tactic to deflect
Birse
from preparing for a possible adjudication. I do not think this is correct or that the offer of mediation was a sham.
Birse
approved a quotation for copying costs on 27th October 2003. Copying was completed on 6th November 2003 apart from two files and
videos.
The responsibility for copying rested with
Birse
and Hammonds. If they had proceeded with the matter with expedition the files would have been copied as early as the end of August 2003.
Birse
is optimistic that Citibank will not commence an adjudication at least until after the meeting that is scheduled for 5th November 2003."
Birse
was aware before the meeting of 5th November 2003 that the discussions which were taking place were without prejudice to the possibility that
CIB
might start an adjudication at any time and certainly after 5th November 2003.
CIB
answered both the seven original questions and the 126 subsequent questions posed by
Birse.
Birse
claims that it was inconclusive and that the parties agreed to a further meeting in order to try to resolve the dispute. It claims that this meant that the dispute had not crystallised and that
CIB's
referral to adjudication was premature.
Birse's
claim was, therefore, that there was no dispute within the meaning of section 108 of the Act and that the Adjudicator had no jurisdiction to hear the dispute.
CIB
claims that the dispute had already crystallised and that there was no agreement to a further meeting or that it would defer any further action until such a meeting had been held.
Birse
narrative programme.
CIB's
three central questions were answered briefly by Mr Heath immediately before lunch.
CIB
was not satisfied either with the answers or that the answers were a serious attempt to deal with the questions which
CIB
had raised.
CIB
agreed to examine the information, take the temperature and get back to
Birse.
CIB,
under the direction of Mr Atkinson, had been pursuing a policy of continuous preparation for an adjudication. It is unlikely that at a meeting at which he was present Mr Atkinson would have allowed
CIB
to enter into any agreement with
Birse
which would deflect it from the strategy which had been pursued for months.
Birse,
on the other hand, was aware of
CIB's
general strategy and were themselves anxious to keep dialogue going for as long as possible in order that they could argue that the dispute had not crystallised and thus a referral to an adjudication was premature.
CIB
expressed themselves as being prepared to attend such a meeting in the first week in December. I am also satisfied that in saying this
CIB
was not, and was not understood by
Birse,
to be agreeing to foreclose any other option, including adjudication, until after such a meeting had taken place. I accept Mr Atkinson's evidence that something was said about "taking the temperature" or "testing the temperature." In the context of
CIB's
preparations for an imminent adjudication. This would reflect
CIB's
tentative attitude to a further meeting.
"Given the ongoing meetings between our clients in relation to this matter we are surprised at the course of action that you have adopted. You will recall that at the conclusion of the meeting on 5th November 2003 your client specifically agreed to reconvene a further meeting for the first week of December, a date to be agreed."
CIB
was not entitled to refer the matter to adjudication because the dispute had not crystallised or because there was an undertaking amounting to an agreement to continue discussions before starting an adjudication. I find that neither
Birse
nor Hammonds was surprised at this step which
CIB
took. I also find that
CIB
was not debarred from making the reference to an adjudication by reason of any agreement that there would be further discussions in December 2003. In my
view,
it was
very
clear that there was a dispute and that it had crystallised even if at a future time there might be discussions as to how the dispute might be resolved.
CIB
from starting an adjudication.
Birse
relies in support of its case that there was a dispute of such complexity that it was not susceptible to adjudication, and it is also part of the background of the claim for unfairness against which the adjudication must be considered.
Conduct of the Adjudication
"DespiteCIB
having provided
Birse
with further information and further evidence to support its demand and despite
CIB
having provided
Birse
with time to consider supporting information,
Birse
has failed to accept that it is liable to
CIB
for the demanded sums (or indeed any sums) and
Birse
has failed to make any payment in respect of
CIB's
demand. In the circumstances a dispute has now arisen which may be characterised as a dispute over the entitlement of
CIB
in respect of the heads of claim set out in
CIB's
letter dated 28th July 2003."
CIB's
claim in paragraph 9. Paragraph 10 sets out the relief sought in four claims which follow the claims A to D in the summary at the end of the demand of 28th July 2003.
CIB
to Mr Heath and Mr Budden also dated 14th November 2003. The letter referred to
various
documents, including the demand for payment dated 28th July 2003, the documents which accompanied it, and the further documents which had since been disclosed and made available for inspection. These further documents were, in fact, served on 22nd November 2003.
Birse
had had sufficient opportunity to decide whether to accept or reject the demand for payment but had adopted an approach which was clearly intended to delay payment on the demand. Accordingly,
CIB
considered that a dispute had arisen between the parties which it was entitled to refer to adjudication in accordance with article GC 16.4.3 of the contract.
CIB
saying that there had been no agreement to a further meeting.
view
of the
volume
of material so far provided by the referring party, and he asked whether the parties had agreed any proposals for the provision of further statements of case and further evidence and documentation.
view
of the case put forward by
Birse
it is necessary to consider in detail the history of the adjudication procedure and the conduct of the Adjudicator.
Birse,
wrote in response on 26th November 2003.
Birse
contended:
(1) no dispute had arisen;
(2)Birse
had been blatantly ambushed by Citibank with the referral;
(3) the matter was extremely complex;
(4) as a result of points (1) to (3) the process was inherently unfair:
"The sums of money involved, together with the amounts of documentation, render this matter inappropriate for resolution by way of adjudication. It is not possible to deal with this matter in the time that is available."
"We also stress that the last three points cannot be cured simply providing an extra two weeks (or any further period) in the event that Knowles agree to such an extension."
CIB
to his having the additional 14 days to reach his decision. The letter acknowledged that any further extension would require the agreement of both parties. This had not yet been the subject of any discussion between the parties.
Birse
made written submissions on 29th November 2003 and further submissions on 2nd December 2003.
Birse,
that there should be an oral hearing. He said he could be available on 22nd or 23rd December 2003 but invited the parties to agree a modest extension in order that the hearing could take place in early January 2004.
CIB
would consider requests for further extensions of time and invited
Birse
to say whether it agreed an extension of time to the 9th January 2004 and whether
Birse
had proposals for further extensions. There were discussions between the parties as to the future timetable, as a result of which the parties agreed on the 1st/2nd December 2003 that the written procedure would be extended to 16th December 2003 and that the time for the Adjudicator to reach his decision would be extended to 9th January 2004.
Birse
continued to consider the adjudication process to be inappropriate in the current circumstances and that no extension of time, whether in days or weeks, would materially alter the position.
Birse's
response document together with nine boxes of documents as they had agreed with
CIB
on 2nd December 2003. On receipt of this, the Adjudicator raised two further issues: (a) whether the final account may be relied on by
Birse
and; (b) whether the assessment of the
CIB
claim by
CIB
was binding on
Birse.
He enquired whether these two issues should be considered on 22nd December 2003 in advance of a detailed evaluation of the claim with the remaining parts of the adjudication deemed dealt with at a later date.
Birse
responded to the Adjudicator on 11th December 2003 asking for a hearing on both 22nd and 23rd December 2003 dealing with all matters.
CIB
also responded on 11th December 2003 but suggested that a decision on further preliminary issues should be given by 31st December 2003 and on the remaining matters by 19th January 2004.
various
discussions between the parties. On 12th December 2003
Birse
proposed that the adjudication should be turned into an arbitration.
CIB
indicated that it would consider a detailed proposal.
Birse
made a detailed proposal. The Adjudicator gave general encouragement to
constructive
proposals that would assist in the resolution of all disputes between the parties. Unfortunately the discussions did not reach a conclusion satisfactory to the parties.
CIB
served its reply to
Birse's
response to the referral notice. The reply included Mr Hart's further report on the extent of the changes between his initial report and his later explanatory report.
Birse
proposed that the adjudication should deal with the issues of natural justice, jurisdiction and no loss on 22nd December 2003. On 19th December 2003,
CIB
proposed that the adjudication should continue but that it should be followed by a dispute resolution procedure which would be completed by 1st December 2004.
Birse
proposed at the hearing that the adjudication should take place over a period of twelve months. This was not accepted.
Various
preliminary issues were considered by the Adjudicator. He gave his decision on 23rd December 2003, rejecting
Birse's
contention that the adjudication was inherently unfair or that there had been a breach of natural justice.
Birse
applied to the Adjudicator for an order that
CIB
disclose documents, the scope of which the letter acknowledged was "enormous". This request was opposed by
CIB
in a long reasoned letter. Mr Hilton of Hammonds admitted in evidence that
Birse's
request amounted to an old-fashioned discovery application. I comment that it would not have been appropriate in modern litigation, let alone in an adjudication.
Birse
were too broad and not consistent with the time scale of the adjudication. He accepted that both parties were entitled to request disclosure of key documents and invited the parties to submit reformulated requests for disclosure by 4 pm, 6th January 2004. This was an entirely reasonable way for the Adjudicator to proceed.
CIB,
objected to
Birse's
request.
Birse
agreed to disclose all the documents requested by
CIB.
Hammonds noted (email of 7th January 2004) that the documents could well amount to 50 to 100 files of documents which would have to be distilled from a thousand files.
Birse's
own request for disclosure was again
very
extensive.
Birse
to disclose the documents that it had agreed to disclose and laid down a procedure for disclosure. He rejected most of Hammonds' requests for
CIB
to disclose further documents but ordered some
very
limited further disclosure. The procedure which he adopted was in accordance with paragraph 13(a) of the Scheme, which provides that the Adjudicator:
"may request any party to the contract to supply him with such documents as he may reasonably require."
"whose principal task will be [to] assist me in handling and collating the manyvaluations
and accounts that need to be considered."
At one stageBirse
made a complaint of procedural unfairness in relation to a hearing with the Assessor where each party put forward an audit trail to prove certain documents. In cross-examination
Birse's
expert, Mr Crowter, accepted that the matter had been dealt with properly.
Birse
considered it essential for there to be a further oral hearing. He asked whether there was agreement to this course for action and noted that if it was to take place there would be a further delay in his decision. He wondered whether the parties would agree to a further extension until 6th February 2004.
Birse
that:
"As a consequence of your decisions regarding discovery, no doubt due to the inherent nature of the process in which the parties are engaged, it has been denied the opportunity to properly investigate and/or assess the claims made against it to significantly test the assertions made and be in a position properly to defend that case."
CIB's
claim was inadequately particularised and that by being denied disclosure of the documents on which
CIB
replied to substantiate its case the Adjudicator was acting contrary to natural justice.
1) A quantum experts' meeting on 30th January 2004;
2) Hearings on 2nd and 4th February 2004 for witnesses of fact;
3) A 'sweep up' hearing for legal submissions on 16th February 2004;
4) The decision be delivered on 23rd February 2004.
CIB
(Knowles) responded to Hammonds' email of 20th January 2004 by noting that with extensions the proceedings will have taken some three months. In an addendum dealing with the letter of 21st January 2004 it formally agreed to the extension to 16th February 2004 but did not agree to the extension to the 23rd February 2004 since there did not seem to
CIB
to be a need for additional oral submissions.
Birse
in relation to questioning on subcontractor procurement and delay issues post-determination (email 23rd January 2004).
CIB
sought to exclude Mr Crowter's expert submissions on behalf of
Birse
which were due on 27th January 2004 on the grounds that they were served a day late on 28th January 2004. The Adjudicator refused to exclude them.
Birse
makes a separate allegation that the adjudication was unfair because their expert, Mr Crowter, was prejudiced by the procedure ordered by the Adjudicator.
various
schedules should be prepared.
very
useful in identifying the real issues.
Birse's
submission included supplementary experts' reports and one from Mr Crowter dated 19th December 2003.
Very
properly the Adjudicator accepted the answers although they were provided a day later than ordered. On 20th January 2004 the third experts' meeting took place with the Adjudicator.
version
of his E3 analysis with explanations. The email confirmed that his analysis was directly comparable to that of Mr Hart and that Mr Crowter had examined critically each of the 1900 items in Mr Hart's E3 spreadsheet.
very
tight, I am unable to conclude that Mr Crowter was not given a proper opportunity to put forward
Birse's
case. He was and he did so.
Birse's
application for the disclosure of documents made on 30th December 2003 and on 6th January 2004. The letter said: "The recent expert and witness hearings have, in our
view,
completely undermined the position taken by Knowles. We consider that the documents disclosed in this referral failed to: 1) Tell us how
CIB's
global claims are broken down; 2) Tell you or us whether costs are costs to complete or costs to rectify defects and/or
valuations
3) Tell you or us which items within the claim should be the responsibility of
CIB.
It is clear from the witness hearings that there were matters which were the responsibility of
CIB
which would have caused delay and additional cost of the works and for which
Birse
should not be responsible.
CIB
would have it, however, that
Birse
is responsible for all costs. 4) Tell us why the works took so long to complete."
The letter concluded by inviting the Adjudicator to draw the conclusion thatCIB
had failed to prove its case.
Birse
did not have liability for patent or latent defects in the work of faēade and that these costs should be excluded from the claims against
Birse."
"We are concerned that, when you later considered the amounts which should be deducted from the cladding claims at paragraphs 14.20 and 14.21 of your decision you have made an accidental slip by not fully taking into account this finding when undertaking yourvaluation."
Birse
was requesting the correction of an accidental slip or omission: "In fact,
Birse's
complaint is that you have misapplied the law to the facts of the case. This cannot be an accidental slip or omission."
"The matter which has been raised by Hammonds, namely the way in which the decision at paragraphs 9.609.15 of the decision have been applied in section 14, is an issue with which I am familiar. I am aware that it could have been argued on both sides that the figure to be deducted from the E3 account by reason of the decision at paragraph 9.15 could have been materially different from those which I, in fact, accepted. In the circumstances of the adjudication, particularly the pressure of time, I consider the appropriate decision was to accept Mr Crowter's figure for categories Z2, Z3 and Z4 in full. I fully accept that had time been availableBirse
would have contended for much greater deductions and
CIB
for lesser deductions. Given the exchange between the parties I do not consider that it would be useful for me to express any
view
on whether my approach contains any error. If the parties or the court decide that there is any error I should be happy to review the decision and to receive further submissions from the parties "
The Decision
CIB's
claims,
Birse's
response,
CIB's
reply,
CIB
and
Birse's
evidence, final submissions, a discussion of the evidence, a discussion of whether
Birse
was entitled to an indemnity from
CIB
as claimed and the decision with reasons on each of the claims. It is clearly a conscientious and careful piece of work from an
very
experienced Adjudicator.
v
Waterman's Partnership (judgment 18th December 2003 now reported in BLR) where the learned Judge noted that:
"The scheme does not envisage that there should be a provisional resolution of a dispute by an Adjudicator at all costs. That would be far greater an injustice than that which the HGCR Act was enacted to remedy."
"I consider that I have been able to do substantial justice between the parties and to arrive at an overall figure which reflects the merits of the case as I find them."
Birse
who say that in the decision the Adjudicator concedes: "I fully accept had time been available
Birse
would have contended for greater deductions and
CIB
for lesser deductions in relation to allocated costs within the E3 account."
view,
the tests which the Adjudicator set himself, namely that he could only reach a decision if (a) he had sufficiently appreciated the nature of any issue referred to him before giving a decision on that issue, including the submissions of each party; and (b) if he was satisfied that he could do broad justice between the parties was impeccable.
Birse's
Contentions
Birse's
criticisms in more detail.
Birse
contends first that no dispute had crystallised in relation to the demand. The stage had not been reached when
CIB
gave notice of adjudication where a point needed to be decided by an adjudicator.
Birse
makes this point both as a general submission and specifically on the basis of the contention that on 5th November 2003 the parties agreed to have further discussions to settle the dispute, which rendered premature the referral on 14th November 2000.
Birse
was irredeemably prejudiced by
CIB's
conduct before the notice of adjudication, it relies on;
1) The alleged secret preparation for adjudication.
2) The alleged failure to refer to the possibility of an adjudication in correspondence withBirse.
3) After they decided to go to adjudicationCIB
allegedly gave the false impression that they were prepared to enter into meaningful discussions.
4) Refusal to answer and/or dilatory conduct in answeringBirse's
questions.
5) The dilatory conduct in copying the 52 files.
6) The statement that they would consider furtherBirse's
points made at the meeting on 5th November 2003.
7) The statement on 5th November 2003 thatCIB
would be providing further information in relation to its corporate structure.
Birse
contends that the adjudication did not cure the overwhelming disadvantage arising from
CIB's
conduct. He granted piecemeal extensions of time which did not cure the mischief.
Birse
suggests that if the adjudication had been timetabled to last 100 days at the outset it might have cured the problem.
Birse
makes complaint of the amount of time the Adjudicator allowed for submissions on jurisdiction; the preparation of the response which was not as good a document as
Birse
would have wished to put forward; the tight timetable for expert evidence which was, as they put it, shoe-horned into January 2004. This, it is alleged, was particularly the case with E3 which involved consideration of how
CIB
managed to spend such considerable sums over such a short period.
"I was able merely to make inferences as to the magnitude of the cost relative to the work that was left and draw inferences about the time it took but I was not able to quantify or understand why these things happened or understand the processes that had gone on afterBirse
left the site.
Birse
did not have that information other than the 52 files which were merely an audit trail to the money. There was no explanation as to how the money had been spent."
Birse
relied on:
1) The fact that over £12 million plusVAT
and interest was claimed.
2) Forty-nine files were filed with the referral notice containing 24 experts' reports on defects, 18 lever arch files of reports on quantum, and 16 witness statements.
3) A further 52 files relating toCIB's
E3 claim.
4) A further 55 files served by the parties in the course of the adjudication.
5) There werevery
significant issues to be considered in the course of the adjudication.
Birse
claims that
CIB
was determined to have an award by the end of January 2004 or shortly afterwards.
Birse's
contentions in relation to the slip have been already fully set out. It is right to add, in relation to the slip, that in her final submission Miss Hannaford said that in the adjudication, "It has taken account of some deduction but not the total figure for the cost of remedial works". Miss Hannaford explained the slip by saying that in paragraph 14.20
Birse
was not responsible for costs in category Z2, Z3 and Z4. She says that it follows from the finding that not only the costs in category Z but those in Mr Hart's category B and Mr Crowter's categories B, X and Z should be deducted. Put another way, Miss Hannaford sees procedural unfairness in the Adjudicator declining to express a
view
on whether or not he had made a slip and for that reason she says that the decision should not be enforced.
CIB's
Contentions
CIB's
contentions can be summarised by saying that by 14th November 2003
Birse
had had a proper opportunity to respond positively to the 30 day demand received by
Birse
at the latest by 6th August 2003. In relation to the claim of unfairness in starting the adjudication,
CIB
says that this was not unfair. The 2002 adjudication which
Birse
had started did not resolve the dispute because
Birse
would not concede that
CIB
was entitled to terminate the contract under clause 14.2.4. It was clear that at that stage both parties were looking to see what sums should be paid. The parties were, in effect, in dispute at that stage and this was acknowledged by both parties who agreed to have a mediation in March 2003.
Birse
was put on notice in late 2002 that
CIB
reserved the right to take any steps to resolve the dispute and it must have been clear to them that this included adjudication.
CIB
says that the reason why
Birse
asked the
various
questions and failed to consider expeditiously the documents disclosed by
CIB
was that
Birse
was anxious to be able to say that the dispute had not been crystallised and, therefore, any adjudication would be premature.
CIB
contends that the dispute had crystallised long before 14th November 2003.
CIB
says that the Adjudicator took the initiative in the procedure as he was entitled to do. The timetable which extended the period of 42 days was agreed as a result of the meeting on 22nd December 2003 when the twelve month timetable was put forward. It might have been a different position if
Birse
had refused any extension to the 42 day period and said that the issues were too complicated to be adjudicated in the time, but this was not the case here.
CIB
contends that it was for the Adjudicator to decide what documents he needs in order fairly to determine the issues before them. This he did in this case.
CIB,
argues:
1) That in his letter dated 19th March 2004 the Adjudicator indicated that the figures in his adjudication represented his consideredview;
![]()
2) The decision is explicable by the fact that the Adjudicator was unable to accept in full either of the experts' figures and came to his own conclusion which was properly reflected in his award;
3) That in saying that he is prepared to review his decision if the parties agreed that he had made an error or that he would review it if the decision of the court was that he was required to do so, he was not making any concession or admission that he had, in fact, made an error.
Conclusions
CIB
on 28th July 2003 was disputed by
Birse
and that the dispute had crystallised by the date of the referral to adjudication on 14th November 2003. In the 15 intervening weeks there had been a proper opportunity for
Birse
to consider the claim and provide a
constructive
response which may or may not have led to further discussions. Instead,
Birse
attempted to manoeuvre tactically so that it could make the claim that the dispute had not crystallised. Both sides had, for a long time before the start of the adjudication, been engaged in tactical manoeuvres. Looking at the history it is impossible to conclude that
Birse
was ambushed by
CIB.
CIB
may have said in general terms that it was prepared to have a further meeting with
Birse
but this was not on the understanding that it would delay any steps to enforce its rights, including adjudication, until such a meeting had taken place.
CIB
was entitled to refer the dispute to the Adjudicator on 14th November 2003.
CIB
before the notice of adjudication did not render the whole process unfair or put
Birse
at an overwhelming disadvantage. It is clear that this was a
very
complex dispute and that
Birse
would require more than the 30 days originally stipulated in which to consider the claim. There was a 15 week period in which
Birse
could have made a
constructive
response.
CIB
at all stages carefully reserved its legal rights.
Birse
was aware, although
CIB
did not make it explicit, that this included the likelihood of a referral to adjudication of part or all of the claim. At an earlier stage
Birse
itself had sprung an adjudication on
CIB.
Birse
I conclude that
CIB
did not act in bad faith before the referral in not explicitly referring to the possibility of adjudication in having discussions and taking part in the mediation and in relation to the copying of the 52 files, and also in relation to providing further information on corporate structure.
CIB
did not prejudice the adjudication by conduct which rendered the adjudication which followed an unfair proceeding.
Birse's
problems were largely caused by its own tactical decision to play for time.
v
Whitefriars City Estates [2004] EWCA CIV 1418, handed down while this Judgment was being revised, I should note that the Court of Appeal held that a party has no absolute right to make submissions on the issue of jurisdiction even though, if the adjudicator considers that he has jurisdiction, the immediate consequences set out in paragraphs 9 and 11 of this Judgment will follow.
Birse's
challenge must also fail on this ground.
Birse's
proposal at the hearing on 22nd December 2003 that a timetable should be agreed, that there should be an extended procedure lasting one year or that adjudication should be followed by a dispute resolution procedure which would be concluded similarly by December 2004. He was acting entirely within his jurisdiction to set a timetable which he felt would enable the adjudication to be fairly concluded in the early part of 2004.
Birse's
request for extensive disclosure made in the course of the adjudication. These requests were inappropriate and may well have been made largely for tactical reasons.
CIB
agreed). He sought and obtained the agreement of
Birse
to extensions of time which enabled him to reach a fair conclusion having given both parties a proper opportunity to put their case.
Birse
is not to be criticised for agreeing to extensions of time but, having agreed to do so, this enable the Adjudicator to reach a decision on the matters referred to him after making a due and impartial enquiry.
Birse
has taken the position that it objected to the adjudication on the grounds that it was irrevocably prejudiced by
CIB's
conduct and the complexity of the dispute which it had to deal with in a relatively short time. I have concluded that it was not prejudiced because (a) it had fifteen weeks from the demand in which to make a substantive response and (b) in the course of the extended adjudication it had a full opportunity to make further investigations and to put its substantive case to the Adjudicator within the limits imposed by the adjudication process, and it did so.
construction
contract to refer a dispute or difference to adjudication. There is a duty on the Adjudicator to reach a decision provided that the conditions in section 108(2) are met. This means that the Adjudicator must be able to discharge his duty to reach a decision impartially and fairly within the time limit stipulated in section 108(2)(c) and (d). A defendant is not bound to agree to extend time beyond the time limits laid down in the Act even if such a refusal renders the task of the Adjudicator to be impossible.
very
limited conclusion that in certain circumstances an Adjudicator may, on his own initiative or at the request of a party, correct an accidental error or omission. In this case
Birse
asks me to extend the principle to circumstances where the Adjudicator declines to take any such step. I do not understand the Adjudicator's letter dated 19th March 2004, properly read, to constitute an invitation to the court to reach a conclusion in relation to the alleged slip and to indicate whether or not the Adjudicator should correct it. Even if he has gone this far I should have to consider the Adjudicator's invitation in the context of the decision of Dyson J in Bouygues
v
Dahl-Jensen upheld by the Court of Appeal. The conclusion in that case was that if the Adjudicator was answering the right question, the decision ought not to be reviewed. It seems to me that Parliament intended the procedure to be an interim procedure which, if carried out fairly and in a manner which is procedurally correct, is not subject to review by the court. I conclude that even if the Adjudicator had invited the court to carry out a review the court should decline to do so. However, I do not understand the Adjudicator's letter to be making such a request but rather to be saying politely that if the court concludes that he has made a slip and orders him to correct it, of course, he will do so.
Birse's
contention are concerned I will merely give the indication that I incline to the
view
expressed by
CIB
that this was not a slip at all and that the decision is explicable by the conclusion that the Adjudicator was unable to accept in full the figures of either expert and, doing the best he could, he came to his own conclusion which was reflected in his final monetary decision which was a sum substantially less than the original referral to adjudication of £14,687,205.63.
Birse
to pay
CIB the sum of £2,164,892.