You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Alfred McaLpine Capital Projects Ltd v Siac Construction (UK) Ltd & Ors [2005] EWHC 3139 (TCC) (19 December 2005) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2005/3139.html Cite as: 105 Con LR 73, [2006] BLR 139, [2005] EWHC 3139 (TCC) |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND
CONSTRUCTION
COURT
B e f o r e :
____________________
ALFRED McALPINE CAPITAL PROJECTS LIMITED (formerly ALFRED McALPINE CONSTRUCTION LIMITED) |
Claimant |
|
- and - |
||
(1) SIAC CONSTRUCTION (UK) LIMITED (2) SIAC CONSTRUCTION LIMITED (3) NORMAN & DAWBARN LIMITED (in creditors' voluntary liquidation) (4) WHITE YOUNG GREEN CONSULTING LIMITED |
Defendants |
|
A N D B E T W E E N : |
||
(1) SIAC CONSTRUCTION (UK) LIMITED (2) SIAC CONSTRUCTION LIMITED |
Part 20 Claimants |
|
- v - |
||
| (1) NORMAN & DAWBARN LIMITED (in creditors' voluntary liquidation) (2) POWELL TOLNER & ASSOCIATES (3) WHITE YOUNG GREEN CONSULTING LIMITED (4) PARKER DESIGN ASSOCIATES |
Part 20 Defendants |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
____________________
MS. KATE GRANGE (instructed by Osborne Clarke) appeared on behalf of
SIAC.
MR. SIMON HARGREAVES (instructed by Reed Smith) appeared on behalf of Norman & Dawbarn.
MS. KATE
VAUGHAN-NEIL
(instructed by Hill Dickinson) appeared on behalf of Powell Tolner Associates.
MS. S. SOOD and MR. KEITH SELL (Solicitors of Beale & Co.) appeared on behalf of White Young Green Consulting
Ltd.
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
MR. JUSTICE JACKSON:
McAlpine's
application to join Norman as defendant in the main action; Part 7, the position of White Young and Powell Tolner.
PART 1: INTRODUCTION
McAlpine
Projects
Ltd.
(to which I shall refer as "
McAlpine").
The first defendant is
SIAC
Construction
UK
Ltd.
The second defendant is
SIAC
Construction
Ltd.
The second defendant is the parent company of the first defendant and is involved in these proceedings by reason of a parent company guarantee. For present purposes nothing turns on the relationship between the first and second defendants or upon their respective roles. I shall therefore refer to these defendants collectively as "
SIAC".
Ltd.
(a company which has recently gone into liquidation) as "Norman". I shall refer to the firm Powell Tolner & Associates as "Powell Tolner". I shall refer to White Young Green Consulting
Ltd.
as "White Young". I shall refer to the firm Parker Design Associates as "Parker".
Ltd.
I shall refer to this company as "Tilebox". The subcontract which was made between
McAlpine
and
SIAC
on 21st March 2002 will be referred to as "the subcontract". In this judgment I shall refer to the Civil Liability (Contribution) Act 1978 as "the 1978 Act". I shall refer to the Pre-action Protocol for
Construction
and Engineering Disputes as "the Protocol".
PART 2: THE FACTS
McAlpine
to carry out substantial works at Onslow House in Guildford. These works comprised the removal of the existing building envelope, the strengthening and extension of the building's primary concrete structure and the replacement of the original façade and roof with new curtain walling and roofing systems to form a part four storey and part five storey air conditioned office block.
McAlpine
engaged Norman to act as architects and Powell Tolner to act as structural engineers. Subsequently
McAlpine
engaged White Young to act as structural engineers in place of Powell Tolner.
McAlpine
engaged
SIAC
as subcontractors to carry out the façade works to Onslow House. These façade works comprised the design and installation of curtain walling, glazing, roofing and secondary steelwork.
SIAC
commenced work on site on 7th January 2002. On 21st March 2002 the subcontract between
McAlpine
and
SIAC
was entered into.
SIAC
engaged Parker to act as
SIAC's
structural engineer in connection with the subcontract works.
McAlpine
determined
SIAC's
subcontract. It is in issue between the parties whether
SIAC
was in default of its obligations under the subcontract and whether
McAlpine
was entitled to determine the subcontract in the manner that it did.
McAlpine
and
SIAC,
it became clear that
McAlpine
would not achieve completion of the main contract works by the specified completion date, namely 14th August 2002.
McAlpine
thus incurred a liability to Tilebox in damages for delay. In an attempt to reduce those damages,
McAlpine
commenced an action to establish that the liquidated damages clause in the main contract was not unenforceable as a penalty. However, that action was unsuccessful and I dismissed
McAlpine's
claim in a judgment dated 25th February 2005: see
McAlpine
v.
Tilebox [2005] EWHC 281 (TCC); [2005] BLR 271.
McAlpine
and
SIAC
against one another were
ventilated
in correspondence. On 8th December 2003
McAlpine
provided a copy of its expert report to
SIAC.
On 23rd April 2004
SIAC's
solicitors wrote a Protocol letter to
McAlpine.
McAlpine's
response to the Protocol letter came in two parts, respectively dated 30th July and 23rd August 2004.
SIAC's
formal reply to these letters came on 3rd March 2005.
McAlpine's
solicitors wrote to Norman, enclosing expert reports and other documents relating to the dispute about Onslow House. On the second page of their letter the solicitors wrote:
"As you will see,SIAC
UK are threatening to commence proceedings against AMCP (see page 2, paragraph 1.2 of Osborne Clarke's letter of 3rd March 2005). Equally, AMCP might have to sue
SIAC
UK. An issue has arisen concerning the allowances, if any, that were made in the cladding and glazing systems for structural and other movements in the building (see pages 16 and 17, paragraphs 1.5 to 1.12).
SIAC
UK suggest that if AMCP commences proceedings against them, they will bring contribution proceedings against Powell Tolner Associates and/or White Young Green (page 16, paragraph 1.9). As you know, they were the structural engineers on the
project
(the latter replacing the former). We do not know what
SIAC's
intentions, if any, are concerning you. Given your role on the
project,
we should be grateful for your comments on
SIAC's
allegations at paragraphs 1.5 to 1.12 on pages 16 to 17 of Osborne Clarke's letter of 3rd March 2005."
Capita
Symonds
Ltd.
responded to that letter as follows:
"We advise that as of 11th April 2005 Norman & DawbarnLtd.
entered into administration and its assets and business was subsequently acquired by
Capita
Symonds.
Capita
Norman & Dawbarn are now operating as a trading division of
Capita
Symonds. Prior to reviewing and commenting on your document, a new set of appointment documents will need to be put in place between
Capita,
Norman & Dawbarn and
Alfred
![]()
McAlpine
for this
project.
In addition, our involvement with this particular issue will be an additional service. We will therefore need to agree hourly rates to cover our time input."
McAlpine's
solicitors wrote to Norman & Dawbarn
Ltd.
(in administration) as follows:
"It is clear from the background documents (copies of which we have provided to you) that Norman & Dawbarn played a significant role in relation to the provision of required allowances for structural and other movements toSIAC.
Although it appears that
SIAC
will be alleging that the structural engineers involved in the
project,
PTA and WYG, were responsible for any inadequacies in the allowances for movement, from the documentation we have seen
SIAC's
allegation could apply equally to Norman & Dawbarn
Ltd.
In the event that
SIAC's
![]()
version
of events is correct, AMCP are entitled to compensation from Norman & Dawbarn
Ltd.
for the losses they have suffered as a result of the inadequate allowance for movement in the cladding installed by
SIAC
at Onslow House. AMCP therefore have a claim against Norman & Dawbarn
Ltd.
Please confirm that this claim has been notified to your insurers and provide us with their identity and contact details. We consider it
very
much in your interest to assist AMCP in clarifying Norman & Dawbarn
Ltd.'s
role in respect of allowances for movement without the need for formal action to be taken by our client."
McAlpine
to Norman or the administrators indicated that it was a possibility, but not a certainty, that Norman would be joined in the litigation.
McAlpine
and representatives of
SIAC
in accordance with the Protocol. This meeting did not give rise to a settlement. However,
McAlpine
did agree to give disclosure of documents relating to their consultants.
SIAC
needed these documents in order to decide whether to bring Part 20 proceedings against Norman and/or Powell Tolner and/or White Young.
SIAC
also needed these documents in order to formulate any Part 20 claim which they might bring.
McAlpine
and
SIAC
remained divided. Accordingly, in order to resolve those issues
McAlpine
commenced the present proceedings.
PART 3: THE PRESENT PROCEEDINGS
Construction
Court on 28th July 2005,
McAlpine
claimed against
SIAC
damages for breach of the subcontract. In its particulars of claim, served on the following day,
McAlpine
alleged: (a) that
McAlpine
had lawfully determined the subcontract on 19th May 2003 and (b) that
SIAC's
work failed to comply with
SIAC's
obligations in 123 different respects.
McAlpine
claimed approximately £17 million as damages, representing
McAlpine's
liability for delay to Tilebox, the cost of remedial works, and so forth.
McAlpine's
particulars of claim. This schedule sets out the 123 alleged breaches of the subcontract as follows: items SPN 1 to SPN 55 relate to the span wall system; items KAW 1 to KAW 52 relate to the Kawneer system; items INT 1 to INT 7 relate to the interface between the span wall system and the Kawneer system; items ROOF 1 to ROOF 4 relate to the roofing; items GEN 1 and GEN 2 are alleged breaches of a general nature.
SIAC
indicated that they were considering the possibility of joining Norman, Powell Tolner, White Young and Parker as Part 20 defendants. After hearing argument from leading counsel for
McAlpine
and for
SIAC,
I directed that
SIAC
should serve their defence and their Part 20 claims (if any) by 30th November 2005. I also fixed the start date of trial as 10th January 2007. This date was three months later than the agreed trial date of October 2006 proposed by
McAlpine
and
SIAC.
I took this course because it seemed to me that the Part 20 defendants would need further time in order to be ready for trial. This was the best estimate that the court could make without the benefit of hearing submissions from the Part 20 defendants. I also gave directions (by consent) for a mediation to take place during February and March 2006.
SIAC
served their defence and counterclaim against
McAlpine.
SIAC
also served Part 20 claims against Norman, White Young and Parker. (It is not yet known whether Parker will take any points as to the
validity
of service upon their French office; no such points have yet been indicated). On 9th December
SIAC
served a Part 20 claim on Powell Tolner.
SIAC's
Part 20 claim against Norman relates to eight of the breaches alleged in
McAlpine's
schedule, namely items SPN1, SPN 2, SPN 19 to 23 inclusive, and KAW1.
SIAC
contend that Norman was in breach of a contractual duty to
McAlpine
in two principal respects: One, failure to inform
SIAC
about differential movements in the building structure, which is relevant to items SPN1, SPN 2 and KAW1. Two, failure to carry out appropriate checks prior to selecting the "C-shaped" panels, which is relevant to items SPN 19, SPN 20, SPN 21, SPN 22 and SPN 23.
SIAC
claim against Norman a contribution or indemnity pursuant to the 1978 Act in respect of
SIAC's
liability (if any) to
McAlpine.
SIAC's
Part 20 claim against Powell Tolner relates to three of the breaches alleged in
McAlpine's
schedule, namely items SPN 1, SPN 2 and KAW 1.
SIAC
contend that Powell Tolner was in breach of contractual duty to
McAlpine
in a number of respects, in particular failing to advise about the likely differential movement and the allowances which should be made for such differential movement.
SIAC's
Part 20 claim against White Young relates to 15 of the breaches alleged in
McAlpine's
schedule, namely items SPN 1 to SPN 7 inclusive, SPN 9, SPN 11, KAW 1, KAW 7, KAW 10, KAW 11, KAW 21 and KAW 22.
SIAC
contend that White Young was in breach of contractual duty to
McAlpine
in a number of respects, including design, co-ordination, checking and so forth.
McAlpine's
application to join Norman as third defendant in the main action and (b) Norman's application for a stay of the Part 20 proceedings, in order to facilitate compliance with the Protocol. These linked applications were heavily contested on all sides and the argument continued until 6.00 p.m. By then it was too late to give judgment. I said that I would give my decision on these two applications at 9.00 a.m. on Monday morning. This I now do.
PART 4: HOW DOES THE PROTOCOL APPLY TO ADDITIONAL PARTIES WHO ARE BROUGHT INTO A MULTI-PARTY ACTION?
"The objectives of this Protocol are as set out in the Practice Direction relating to Civil Procedure Pre-Action Protocols, namely:
(i) to encourage the exchange of early and full information about the prospective legal claim;
(ii) to enable parties to avoid litigation by agreeing a settlement of the claim before commencement of proceedings;
(iii) to support the efficient management of proceedings where litigation cannot be avoided."
"The general aim of this Protocol is to ensure that before court proceedings commence:
(i) the claimant and the defendant have provided sufficient information for each party to know the nature of the other's case;
(ii) each party has had an opportunity to consider the other's case, and to accept or reject all or any part of the case made against him at the earliest possible stage;
(iii) there is more pre-action contact between the parties;
(iv) better and earlier exchange of information occurs;
(v)
there is better pre-action investigation by the parties;
(vi)
the parties have met formally on at least one occasion with a
view
to:
• defining and agreeing the issues between them; and• exploring possible ways by which the claim may be resolved;
(vii)
the parties are in a position where they may be able to settle cases early and fairly without recourse to litigation; and
(viii)
proceedings will be conducted efficiently if litigation does become necessary."
"COMPLIANCE
If proceedings are commenced, the court will be able to treat the standards set in this Protocol as the normal reasonable approach to pre-action conduct. If the court has to consider the question of compliance after proceedings have begun, it will be concerned with substantial compliance and not minor departures, e.g. failure by a short period to provide relevant information. Minor departures will not exempt the 'innocent' party from following the Protocol. The court will look at the effect of non-compliance on the other party when deciding whether to impose sanctions. For sanctions generally, see paragraph 2 of the Practice Direction - Protocols 'Compliance with Protocols'."
"2.1 The Civil Procedure Rules enable the court to take into account compliance or non-compliance with an applicable Protocol when giving directions for the management of proceedings (see CPR rules 3.1(4) and (5) and 3.9(e)) and when making orders for costs (see CPR rule 44.3(5)(a)).
2.2 The court will expect all parties to have complied in substance with the terms of an approved Protocol.
2.3 If, in the opinion of the court, non-compliance has led to the commencement of proceedings which might otherwise not have needed to be commenced, or has led to costs being incurred in the proceedings that might otherwise not have been incurred, the orders the court may make include:
(1) an order that the party at fault pay the costs of the proceedings, or part of those costs, of the other party or parties;
(2) an order that the party at fault pay those costs on an indemnity basis;
(3) if the party at fault is a claimant in whose favour an order for the payment of damages or some specified sum is subsequently made, an order depriving that party of interest on such sum and in respect of such period as may be specified, and/or awarding interest at a lower rate than that at which interest would otherwise have been awarded;
(4) if the party at fault is a defendant and an order for the payment of damages or some specified sum is subsequently made in favour of the claimant, an order awarding interest on such sum and in respect of such period as may be specified at a higher rate, not exceeding 10% above base rate (cf. CPR rule 36.21(2), than the rate at which interest would otherwise have been awarded.
2.4 The court will exercise its powers under paragraphs 2.1 and 2.3 with the object of placing the innocent party in no worse a position than he would have been in if the protocol had been complied with."
"There can often be a complaint that one or other party has not complied with the Protocol. The court will consider any such complaints once proceedings have been commenced. If the court finds that the claimant has not complied with one part of the Protocol, then the court may stay the proceedings until the steps set out in the Protocol have been taken."
Construction
Court, where litigation arises out of a major building
project
(as in the present case) in which numerous subcontractors and professional firms have been involved.
Ltd.
v.
Park West Club
Ltd.
[2004] BLR 223. Judge Wilcox held that a Part 20 claimant is obliged to comply in substance with the terms of the Protocol. The judge made a costs order in that case to compensate the Part 20 defendant for certain non-compliances with the Protocol which had occurred. Daejan was a case in which, so it appears, the Part 20 claimant had a proper opportunity to comply with the Protocol before commencing Part 20 proceedings. I respectfully agree with the reasoning of Judge Wilcox in that case.
(1) When was it known that the party in question was going to be joined in the action?
(2) What information about the action and the underlying dispute was given to that party before joinder and when?
(3) How large a part does the new party play in the action as a whole?
(4) What stay, if any, could be accommodated in the proceedings against the new party without jeopardising the overall timetable?
(5) Does justice require that the whole timetable should be put back and that a new trial date should be fixed?
(6) Could the new party be compensated in costs for any non-compliance with the Protocol? If so, should the question of costs be addressed immediately or should that question be addressed at the end of the action?
(7) Is there any way (other than a stay) within the parameters of the existing timetable by which the new party could be put in the same position that it would occupy if the Protocol had been followed?
PART 5: NORMAN'S APPLICATION FOR A STAY OF THE PART 20 PROCEEDINGS
SIAC
commenced those proceedings without first complying with the Protocol. In support of his application, Mr. Hargreaves took me through the correspondence in some detail, including, but by no means limited to, the letters referred to in Part 2 above. It can be seen from the correspondence that it was
McAlpine
rather than
SIAC
who communicated with Norman. Norman was sent a good deal of information about Onslow House and the related claims. However, Norman never received any formal letter of claim under the Protocol. It can also be seen that at some point in 2005 Norman went into creditors'
voluntary
liquidation. Norman and its representatives never sent any substantive response to the
various
letters intimating claims or possible claims. Norman's insurers did not accept that insurance cover would extend to the claims concerning Onslow House until 3rd November 2005. Furthermore, those insurers did not instruct solicitors and counsel to act on Norman's behalf until 13th December 2005. That was just three days before the second case management conference.
SIAC
had ample opportunity to go through the Protocol procedures between 27th September 2005 (the date of the first case management conference) and 30th November 2005 (the date for service of the Part 20 proceedings). It is not clear to me, however, that this is so. It must be remembered that
SIAC
first gained access to
McAlpine's
correspondence with the professionals during the summer of 2005. I am not sure what progress
SIAC
had made on digesting this correspondence by 27th September. Certainly
SIAC
had not made a decision as at that date about which professionals it would join.
SIAC
would join Norman as a Part 20 defendant. Second consideration - a considerable amount of information about the claims concerning Onslow House was provided by
McAlpine
to Norman in and after April 2005. Third consideration - in the Part 20 proceedings only eight of the alleged breaches are pursued against Norman and I have previously identified which breaches those are. Fourth consideration - in my
view,
a stay of Part 20 proceedings against Norman for any significant period would jeopardise the trial date of January 2007. Mr. Hargreaves stated during argument, when asked by me, that he was looking for a stay until mid February, i.e. a period of some two months. Fifth consideration - in all the circumstances, I do not consider that justice requires that the whole timetable should be put back. Sixth consideration - if and insofar as Norman has suffered loss as a result of
SIAC's
non-compliance with the Protocol, this loss can be redressed by the costs order at the end of the litigation. Seventh consideration - in my
view,
Norman's difficulties can be accommodated within the present timetable.
SIAC's
Part 20 claim form conveys the same information as a Protocol letter. Mr. Hargreaves' queries about that pleading, which he raised in argument, can be addressed by a request for information. Furthermore, the present litigation timetable contains a window for mediation in February and March. This mediation could serve the same purposes as the meeting which is required under the Protocol. Furthermore, it seems to me that if any party so requests, it would be possible for the court to order a modest extension of the mediation window.
SIAC's
failure to comply with the Protocol. On the other hand, in the situation we are now in, it is not appropriate to stay the Part 20 proceedings. Insofar as Norman has suffered loss through non-compliance with the Protocol, that loss will have to be quantified at the end of the action and that loss can be compensated by costs in due course.
PART 6:
MCALPINE'S
APPLICATION TO JOIN NORMAN AS DEFENDANT IN THE MAIN ACTION
McAlpine's
solicitors has made a witness statement in support of
McAlpine's
application to join Norman as defendant in the main action. Paragraphs 10 and 11 of that witness statement read as follows:
"10. Although [McAlpine]
originally intended to pursue this litigation against only
SIAC
(the party which appears to [
McAlpine]
to be primarily responsible for the deficiencies in the curtain walling), [
McAlpine]
has (particularly since it became clear that
SIAC
intended to join other parties to the proceedings) been actively considering whether and if so to what extent it has claims against the other parties which
SIAC
has joined. [
McAlpine]
considers that it has claims against [Norman] and [White Young], which it wishes to pursue in these proceedings and have determined at trial together with its claims against
SIAC,
and
SIAC's
Part 20 claims against those (and other) parties. Accordingly [
McAlpine]
has prepared an Amended Claim Form which adds [Norman] and [White Young] as Third and Fourth Defendants in the main action… and is well advanced in preparing (a) Amended Particulars of Claim which incorporate claims against these two additional parties, and (b) an Amended
version
of the Non-Compliance Schedule which deals with [
McAlpine's]
claims against [Norman] and [White Young] by reference to the specific Non-Compliances. [
McAlpine]
expects to be in a position to serve final
versions
of these Amended Particulars of Claim and supporting documents within six days of the [case management conference] on 16 December, i.e. by 22 December 2005.
11. There is a significant degree of overlap between the Part 20 claims made bySIAC
against [Norman] and [White Young] and [
McAlpine's]
proposed claims against those parties, in that, as against each of [Norman] and [White Young]:
(a) plainly, bothSIAC's
Part 20 claim and [
McAlpine's]
proposed claim arise out of the same design, co-ordination and inspection work carried out by (and obligations owed by) the particular consultant in relation to the
Project;
(b) likeSIAC,
[
McAlpine]
proposes to claim against each consultant in relation to the movement joint allegations, i.e. there is complete overlap in the claims so far as these allegations (Spn01, Spn02, Kaw01) are concerned. As against [Norman], [
McAlpine]
first told [Norman] that it would claim against them in respect of these allegations on 25 April 2005. In early June 2005 [White Young] confirmed that they had produced a document for us setting out their position in respect of the movement joints allegations... We have yet to see this document;
(c) as regards the further Non-Compliances in respect of whichSIAC
pursues these consultants, listed at paragraph 9 above, [
McAlpine]
proposes to proceed against [Norman] and [White Young] in respect of some but not all of these. However, it is [
McAlpine's]
present intention to pursue [Norman] and [White Young] also in relation to further Non-Compliances which are not (presently) pursued by
SIAC
in relation to these consultants. In relation to [Norman] there are about 50 such further Non-Compliances, and in relation to [White Young] there are about six. Two thirds or more of these further Non-Compliances which [
McAlpine]
intends to pursue (particularly against [Norman]) relate purely to failures on the part of [Norman] to notice (and notify [
McAlpine])
of the Non-Compliances during the course of [Norman's] inspections of the works."
McAlpine's
application on the ground that
McAlpine
has failed to comply with the Protocol. Furthermore, Norman has lost touch with relevant staff and has lost relevant documents following the administration and the transfer of Norman's business. Furthermore, says Mr. Hargreaves,
McAlpine
are proposing to pursue a more extensive claim against Norman than the claim which
SIAC
are pursuing, but the full extent of
McAlpine's
claim against Norman will not be apparent until the amended particulars of claim are served, and it is not yet known which are the 50 additional non-compliances referred to in paragraph 11 of the witness statement.
McAlpine
has not complied with the Protocol as against Norman. On the other hand,
McAlpine
did provide a fair amount of information to Norman and received precious little response. It seems to me that Norman's present difficulties arise from matters unrelated to the Protocol, namely the departure of staff, the going into administration of Norman, and the loss of documents.
McAlpine's
non-compliance with the Protocol as against Norman, this is not an appropriate case in which (a) to refuse leave to join Norman as defendant or (b) to order a stay of
McAlpine's
claim for the purpose of going through the Protocol procedures. (ii) If and insofar as Norman can establish financial loss as a result of non-compliance with the Protocol, this can be compensated for by an appropriate costs order at the end of the case.
McAlpine
expands the claim against Norman in the manner indicated in paragraphs 10 and 11 of the witness statement, then Norman may have difficulty in keeping up with the trial timetable given the other handicaps mentioned above. It is not possible to gauge this matter until
McAlpine's
amended particulars of claim and amended schedule of non-compliance have been served.
McAlpine's
application is as follows. I grant permission for
McAlpine
to join Norman as defendant in the main action. If Norman wishes to apply for the trial timetable or the trial date to be put back, I will hear that application after the amended particulars of claim have been served.
PART 7: THE POSITION OF WHITE YOUNG AND POWELL TOLNER
McAlpine's
solicitors in the following terms:
"We confirm our client's consent to your application to join them as defendants in the main action. We confirm our client's agreement to the sensible proposed directions contained in your letter of 14th December with the following caveats. We note you accept our clients have agreed to a time for service of their defence without seeing the amended particulars and as such this may give rise to unforeseen difficulties with the timetable. We agree our client will be in a position to deal with this and raise it with the court during January if necessary. While we do not consider it is appropriate for experts to meet prior to the mediation, it would facilitate resolution if they prepare and exchange preliminary reports. We are grateful for your willingness to provide advanced disclosure as we anticipate some disclosure will clearly be of benefit to us in assessing the claim made against our client. It is likely that advanced disclosure will be sought from other parties."
view
of the substantial agreement between White Young and
McAlpine,
White Young did not instruct counsel to attend the case management conference. However, Ms. Sood of Beale & Co., White Young's solicitors, has attended the hearing and I am grateful for her assistance. Ms. Sood does not seek to resile from her letter dated 15th December. In the course of her brief submissions she said that White Young wished to move forward and to have the matter resolved. However, she expressed the fear that
McAlpine's
amended particulars of claim (when served) will be deficient. After some discussion between myself and her during her submissions, it seemed to me, and I think that she accepted, that the best way to deal with this concern is for me to hear any application which White Young may wish to make after it has received and considered the amended particulars of claim.
McAlpine
do not seek to join Powell Tolner in the main action. Powell Tolner did not indicate any application for a stay in advance of the case management conference. However, during the hearing and having heard Mr. Hargreaves' forceful submissions, Ms.
Vaughan-Neil for Powell Tolner submitted, perfectly reasonably, that if there is a stay of the Part 20 proceedings against Norman, then there should be a similar stay of the Part 20 proceedings against her clients. In the event I have held that there should be no stay of the Part 20 proceedings against Norman. In the circumstances, and having regard to all of the correspondence which I have read, I see no ground for granting a stay of the Part 20 proceedings against Powell Tolner.
______________