![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> M Rohde Construction v Markham-David [2006] EWHC 814 (TCC) (20 March 2006) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2006/814.html Cite as: [2006] EWHC 814 (TCC), [2006] BLR 291, [2006] CILL 2364 |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND
CONSTRUCTION
COURT
March 2006 |
B e f o r e :
MR
JUSTICE JACKSON
____________________
M. ROHDE CONSTRUCTION | Claimant | |
v | ||
NICHOLAS MARKHAM-DAVID | Defendant |
____________________
Official Court Reporters
Cliffords Inn, Fetter Lane, London, EC4A 1LD
Telephone: 0207 269 0370
MISS
ELIZABETH REPPER appeared on behalf of
M.
ROHDE
CONSTRUCTION
MR
NICHOLAS
MARKHAM-DAVID,
the defendant, appeared in person.
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
MR
JUSTICE JACKSON:
Part 1 - Introduction
Mr
Martin
Rohde,
trading as "
M
Rohde
Construction".
The defendant is
Mr
Nicholas
Markham-David.
Construction
and Regeneration Act 1996 ("the 1996 Act"). Section 107 of the 1996 Act provides:
"(1) The provisions of this Part apply only where theconstruction
contract is in writing, and any other agreement between the parties as to any
matter
is effective for the purpose of this Part only if in writing.
The expressions "agreement", "agree" and "agreed" shall be construed accordingly.(2) There is an agreement in writing-
(a) if the agreement ismade
in writing (whether or not it is signed by the parties),
(b) if the agreement ismade
by exchange of communications in writing, or
(c) If the agreement is evidenced in writing.
(3) Where the parties agree otherwise than in writing by reference to terms which are in writing, theymake
an agreement in writing.
(4) An agreement is evidenced in writing if an agreementmade
otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement."
"(1). A party to aconstruction
contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this Section.
For this purpose the word "dispute" includes any difference.
(2) The contract shall
(a)enable a party to give notice at any time of his intention to refer a dispute to adjudication;
(b)provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice;
(c)require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
(d)allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred;
(e)impose a duty on the adjudicator to act impartially; and
(f)enable the adjudicator to take the initiative in ascertaining the facts and the law.
(3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
The partiesmay
agree to accept the decision of the adjudicator as finally determining the dispute ……
(5) If the contract does not comply with the requirements of subsections(1) to(4), the adjudication provisions of the Scheme forConstruction
Contracts apply."
"(1) The parties are free to agree on themanner
of service of any notice or other document required or authorised to be served in pursuance of the
construction
contract or for any of the purposes of this Part.
(2) If or to the extent that there is no such agreement the following provisions apply.(3) A notice or other documentmay
be served on a person by any effective
means.
(4) If a notice or other document is addressed, pre-paid and delivered by post-(a) to the addressee's last known principal residence or, if he is or has been carrying on a trade, profession or business, his last known principal business address, or(b) Where the addressee is a body corporate, to the body's registered or principal office,it shall be treated as effectively served."
Construction
Contracts, which is referred to in Section 108(5) of the 1996 Act, is set out in the Schedule to the Scheme for
Construction
Contracts, (England and Wales) Regulations 1998. In this judgment I shall refer to the Scheme for
Construction
Contracts as "the Scheme".
"1. The adjudicator shall reach his decision not later than-
(a) twenty eight days after the date of the referral noticementioned
in paragraph 7(1), or
(b) forty two days after the date of the referral notice if the referring party so consents, or(c) such period exceeding twenty eight days after the referral notice as the partiesmay,
after the giving of that notice, agree …
(3) As soon as possible after he has reached a decision, the adjudicator shall deliver a copy of that decision to each of the parties to the contract".
made
the previous orders. The change of judge to
myself
occurred because of listing difficulties last week. Following the recent reforms, I should perhaps
make
it clear that this court will (so far as practicable) reclassify and reassign cases at short notice, in order to avoid standing any case out of the list.
must
now turn to the facts.
Part 2 - The facts
valuation
of
variations.
The defendant
made
payments on account, but the claimant contended that substantial additional sums were due.
marriage
came to an end. The defendant and his wife separated. In due course the defendant
moved
to a new address in Salisbury, namely 3 Wordsworth Road. The defendant's wife also
moved
to a new address in Salisbury, namely 12 Wyndham Road.
manage
a quarry known as Callow Quarry at Buckholt in Herefordshire.
March
2001 the claimant decided to refer to adjudication his claim for the balance of
monies
owing to him. On the 30th of
March
2001
Messrs
Castons (a firm of quantity surveyors acting for the claimant) served or purported to serve a notice of adjudication upon the defendant. The address to which Castons sent the notice of adjudication was 22 Hamilton Road, Salisbury.
Mr
Andrew Pennifold was appointed adjudicator.
Mr
Pennifold received submissions and evidence from the claimant. On the 18th of
May
2001 he promulgated his decision, which was that the defendant owed to the claimant the sum of £37,589.00.
various
communications were sent to the defendant at 22 Hamilton Road, Salisbury. All such communications were returned as undelivered. This is evidenced, for example, by Castons' letters to the adjudicator, dated 17th April, 8th
May
and 23rd
May
2001.
marriage
was acrimonious and his former wife was not passing documents to him.
matters
and both parties can be cross-examined.
me
now return to the narrative. The adjudicator's decision was not implemented. The defendant did not
make
any further payments to the claimant, beyond the sums which had previously been paid on account.
Part 3 - The present proceedings
Construction
Court on 7th November 2001, the claimant claimed against the defendant the sum of £37,528.00 as awarded by the adjudicator.
method.
On the 18th of January 2002 this court
made
an order for service by the following
means:
"Service to be effected by process agents by hand delivering to a person appearing to be in occupation of 22 Hamilton Road, Salisbury Wilts and a further copy of the documents to 12 Wyndham Road, Salisbury Wilts."
March
2002 this court gave judgment in default against the defendant for the following sums: debt plus interest to date of judgment £41,066.56, costs £480.00, total £41,546.56.
matters
rested for some time. During 2004 the claimant commenced other litigation against the defendant and his daughter, in the Hereford County Court. The claimant obtained judgment in default in both actions.
me
that the default judgment was set aside and the whole action against his daughter was struck out.
month
he became aware of the judgment and, through solicitors, he tried to obtain copies of the relevant documents. On 19th December 2005 the defendant applied to set aside the default judgment, which had been entered on 18th
March
2002.
March
2006.
March
2006. The defendant appeared in person. The claimant was represented by counsel,
Miss
Elizabeth Repper. During the course of the hearing both parties furnished to
me
additional bundles of documents of
varying
degrees of legibility. I said that I would consider all the
material,
including some additional authorities handed up during the hearing, and give
my
decision on
Monday,
20th
March.
This I now do.
Part 4 - Does the defendant have a real prospect of successfully defending the claim?
matter,
which I am required to consider, pursuant to Civil Procedure Rules, rule 13.3(1).
matters,
such as the procedure for dealing with
variations.
I have come to the conclusion that a defence based upon non-compliance with section 107 of the 1996 Act is unlikely to succeed.
Messrs
Castons, with whom the claimant is currently in dispute. Nevertheless, drawing reasonable inferences from the available documents, I think it probable that the adjudicator's decision was delivered in time. In any event, a slight delay is not fatal to the decision: see Barnes and Elliott Limited
v
Taylor Woodrow Holdings Limited [2003] EWHC 3100 (TCC); [2004] 1BLR 111; Simons
Construction
Limited
v
Aardvark Developments Limited [2003] EWHC 2474 (TCC). I have therefore come to the conclusion that this proposed line of defence is likely to fail.
matter,
which I
must
address, is the defendant's ignorance or probable ignorance that the adjudication was proceeding.
Miss
Repper, quite rightly, draws attention to section 115 of the 1996 Act. She points out that the notice of adjudication and other documents concerning the adjudication were all sent to the claimant's last known principal residence.
Miss
Repper points out that this constitutes effective service, under section 115(4) of the 1996 Act.
via
the quarry. The claimant deliberately used a
method
of service, which was unlikely to bring the documents to the defendant's attention.
make
any finding of disingenuous conduct on the claimant's part. There is, however, a serious factual issue to be tried in this regard. I would formulate the issue in these terms: did the claimant have available during the adjudication a ready
means
of contacting the defendant, which the claimant chose neither to use nor to communicate to the adjudicator?
me
in relation to the question of law.
Miss
Repper kindly did some research during the short adjournment on Thursday, but she did not find any relevant authorities. In the circumstances the issue of law has not been fully argued on either side. I
make
no complaint about that, because I am simply dealing with an interlocutory application.
Construction
Limited
v
Devonport Royal Dockyard [2005] EWCA Civ 1358 Lord Justice Chadwick, giving the judgment of the Court of Appeal, said this at paragraphs 85 to 87:
"85. The objective, which underlies the Act and the Statutory Scheme requires the courts to respect and enforce the adjudicator's decision, unless it is plain that the question which he has decided, was not the question referred to him or themanner
in which he has gone about his task is obviously unfair. It should only be in rare circumstances that the courts will interfere with the decision of an adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case, which (contrary to DML's outline submissions to which we have referred in paragraph 66 of this Judgment)
may
indeed aptly be described as "simply scrabbling around to find some argument, however tenuous, to resist payment".
86. It is only too easy in a complex case, for a party who is dissatisfied with the decision of an adjudicator, to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels, "excessive jurisdiction" or "breach of natural justice". Itmust
be kept in
mind
that the
majority
of adjudicators are not chosen for their expertise as lawyers. Their skills are as likely (if not
more
likely) to lie in other disciplines. The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution, which
meets
the needs of the case. Parliament
may
be taken to have recognised that in the absence of an interim solution the contractor (or sub-contractor) or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The Statutory Scheme provided a
means
of
meeting
the legitimate cash and flow requirements of contractors and their subordinates. The need to have the "right" answer has been subordinated to the need to have an answer quickly. The Scheme was not enacted in order to provide definitive answers to complex questions. Indeed, it
may
be open to doubt whether Parliament contemplated that disputes involving difficult questions of law would be referred to adjudication under the Statutory Scheme; or whether such disputes are suitable for adjudication under the Scheme. We have every sympathy for an adjudicator faced with the need to reach a decision in a case like the present.
87. In short, in the overwhelmingmajority
of cases, the proper course for the party who is unsuccessful in an adjudication under the Scheme
must
be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator's decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense, as we suspect the costs incurred in the present case will demonstrate only too clearly."
make
representations in the adjudication, then I consider that this
may
be one of those rare and exceptional cases in which the court will decline to enforce an adjudicator's decision by reason of breach of natural justice.
me
now draw the threads together. For the reasons set out above, I have
made
no binding findings of fact on the evidence. I have reached no decision on the question of law. I am however, satisfied that the defendant has available a defence with a real prospect of success. Accordingly,
my
answer to the question posed in part four of this Judgment is "yes".
Part 5 - In the exercise of its discretion, should the court set aside the default judgment?
"In considering whether to set aside orvary
a judgment entered under Part 12, the
matters
to which the court
must
have regard include whether the person seeking to set aside the judgment
made
an application to do so promptly."
Miss
Repper
makes
the point that it is now four years since the default judgment was entered. That factor weighs heavily against exercising any power to set aside. The defendant, on the other hand, contends that he was unaware of the present action until October 2005. Since then he has
moved
promptly to set aside the judgment.
made
the original investigations on behalf of the claimant, was
Mr
Rossinger.
Mr
Rossinger also effected service on the 18th of February 2002, by the
method
which this court had specified. I have
Mr
Rossinger's two reports dated 5th December 2001 and 18th February 2002, as well as his witness statement dated 18th February 2002. I note that in his report dated 5th December 2001
Mr
Rossinger says this: "A search revealed a Georgina
Markham-David
living at 12 Wyndham Road, Salisbury, which is one street away from Hamilton Road. I attended this property and spoke with an adult female, who identified herself as Nicholas's ex-wife. She would not give out any information regarding her ex-husband, stating that she did not wish to get involved".
more
complex. There was an issue during the hearing as to when those tenants
moved
out. It is difficult for
me
to resolve that issue. Nevertheless, I can find no reason to reject the defendant's evidence that he was in conflict with those tenants because of non-payment of rent.
me,
is the inherent probability. The defendant's two witness statements are forceful and articulate. Furthermore, at the hearing on Thursday, the defendant presented his case with
vigour
and clarity. It seems to be unlikely that a person such as the defendant would do nothing to contest the proceedings, if he had been aware of them.
my
conclusion in a somewhat cautious and guarded
manner
for this reason. If the present action proceeds to trial, the credibility of both the claimant and the defendant will be seriously in issue. If the trial judge prefers the evidence of the claimant to the evidence of the defendant in relation to the crucial events of 2001, then the judge
may
take a different
view
from that expressed above in relation to events between 2002 and 2005.
me
now come to the crucial issue. I have come to the conclusion that the defendant has a defence with a real prospect of success. I have also come to the conclusion that I should proceed on the basis that the defendant was unaware of the present proceedings until October 2005. In those circumstances it seems to
me
that the defendant has
moved
with reasonable promptness to set aside the judgment.
Miss
Repper has
very
properly urged upon
me
the prejudice which the claimant will suffer if judgment is set aside. I accept that submission and I take into account the prejudice, which the claimant would suffer in this regard.
must
perform this exercise, having regard to the overriding objective set out in Part 1 of the Civil Procedure Rules.
me
that if the default judgment stands there is a real risk that the defendant will suffer injustice. The prejudice caused to the defendant by dismissing his application outweighs the prejudice caused to the claimant by setting the judgment aside. The defendant has
moved
with reasonable promptness to
make
his application. The proper course is to set aside the default judgment and let the action proceed to trial. Accordingly that is the order which I shall
make. The defendant succeeds in his application.