![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Ledwood Mechanical Engineering Ltd v Whessoe Oil and Gas Ltd & Anor [2007] EWHC 2743 (TCC) (20 November 2007) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2007/2743.html Cite as: [2008] BLR 198, [2007] EWHC 2743 (TCC) |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
LEDWOOD MECHANICAL ENGINEERING LTD | Claimant |
|
| - and - |
||
(1) WHESSOE OIL AND GAS LTD(2) VOLKER STEVIN CONSTRUCTION EUROPE BV |
Defendants |
____________________
Ltd.,
6th
Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000 Fax No: 020 7427 0093 DX: 410 LDE
Email: info@martenwalshcherer.com
Website: www.martenwalshcherer.com
Mr Adam Constable for the Defendants.
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
Mr Justice Ramsey:
Introduction
Ledwood
Mechanical
Engineering
Limited ("
Ledwood"),
was engaged by the Defendants,
Whessoe
Oil
and
Gas
Limited and
Volker-Stevin
Construction Europe BV ("the Joint
Venture")
to act as subcontractor for fabrication and erection of pipework at the Dragon liquid natural
gas
import terminal at Milford Haven.
The Proceedings
Venture's
assessment of interim Application 19. The Joint
Venture
made deductions totalling some £1.5m (excluding
VAT)
from the application which
Ledwood
submitted in July 2007 in the sum of just over £2.2m (excluding
VAT).
The balance was paid to
Ledwood.
Ledwood
commenced adjudication under clause 20.4 of the subcontract which they had entered into on or about 3rd March 2005. The subcontract would not have contained a mandatory provision for adjudication under section 108 of the 1996 Act, as the operations in this case are not construction operations within the meaning of section 105(2) of that Act. The subcontract, however, incorporates the following provision:-
'Notwithstanding any other provision of this agreement, either party may decide at any time to refer a dispute to adjudication under section 108 of the Housing Grants (Construction and Regeneration) Act 1996 in accordance with the adjudication provisions of the Scheme for Construction Contracts (SI 1998 No. 649) ("the Scheme") subject to the amendments set out in the remainder of this clause 20.4.'
Ledwood
commenced the adjudication. The Adjudicator made his decision, dated 10th October 2007. He held that the Joint
Venture
had wrongly withheld £1,215,067.64 from its payment against Application 19 and expressed his decision in these terms at the conclusion:-
"(7) The total sum which can properly be deducted from Application 19 (exclusive ofVAT)
is £325,390.36.
Whessoe
has wrongly withheld £1,215,067.64 (exclusive of
VAT).
(8) Interest at the rate of 1% above the Bank of England base rate shall run on the total of the wrongly deducted amount (£1,215,067.64) for the period from 3rd August 2007 to the date of actual payment."
Venture
indicated that it would make payment of the outstanding sums by 19th October 2007, it did not make payment. Instead, the Joint
Venture
wrote to
Ledwood
on 19th October 2007 and issued revision 2 of a payment notice in respect of Application 22, in which it stated that the sum due to
Ledwood
was a negative sum of £224,099.43. It, therefore, made no further payment.
Ledwood
issued these Part 8 proceedings and directions were given which led to a hearing on 16th November 2007. At that hearing,
Ledwood
was represented by James Howells and the Joint
Venture
was represented by Adam Constable.
The Issues
Ledwood's
entitlement to payment of costs by reference to target hours. (2) Should the Adjudicator's decision be given effect by applying his decision to Application 19 or Application 22? (3) If the risk/reward régime applies to applications for payment prior to completion, can the Joint
Venture
set off a sum in respect of an adjustment for risk/reward? I shall consider these issues in turn.
The risk/reward regime.
"Payment for the subcontract work shall be made on the basis of the subcontract price as determined in accordance with the subcontract based on the target cost, subject to adjustments."
"The subcontractor shall submit a draft statement in two hard copies and one electronic copy to the contractor within five days after the end of each month in a form approved by the contractor, showing in detail the amounts to which the subcontractor considers himself to be entitled together with all necessary supporting documentation (in accordance with the details of payment particulars as required by Exhibit E) and a comparative analysis against the target cost. The draft statement shall include the following items as applicable in the sequence listed … (d) all necessary adjustments as Exhibit E."
"Full and concise details are presented in the agreed notes of commercial meetings Nos. 1 to 11 inclusive (signed by both parties) as contained in Exhibit F."
variations.
Exhibit E also includes at paragraph 8 provisions as to risk/reward. It provides:
"The risk/reward is limited to the costs relating to target labour hours and commensuratevalues
only as set out in the schedule. For the purposes of clarity, the supervision, plant etc are not subject to the target cost and therefore do not form part of the risk/reward schedule."
Venture
benefits by 40% and
Ledwood
by 60%, without limitation on the amount of underspend. Where the overspend is up to 20% of the cost of the target hours, then the overspend is shared 50%/50%, but where it exceeds 20% of the cost of the target hours,
Ledwood
bears the full 100% of the overspend. In fact, the table was later
varied
by a settlement agreement made between the parties on 11th April 2007, so that the Joint
Venture
benefits in respect of 100% of underspend,
Ledwood
bears 100% of the overspend up to 7.5% of the final target man hours and above that the overspend is shared 50%/50%. What is not stated in Exhibit E is when the relevant calculation is to be carried out.
Ledwood
refers to Exhibit F, which is a series of notes of 11 commercial meetings, which took place between 20th December 2004 and 11th February 2005, prior to the subcontract. In general terms, at these meetings the parties set out their positions and when these led to agreements they were then incorporated into Exhibit E.
Ledwood
to provide their agreement".
"Ledwood
set out the following for the JV review. Main board policy dictated the maximum overspend exceeding 20% of the subcontract target
value
be capped at £600,000 where
Ledwood
were 100% liable. Thereafter
Ledwood
require reimbursement without any addition of 10%. JV stated in consideration of this new departure they would reassess the savings relative to any capping. JV to review in the context of the original agreement."
Ledwood
capping." At meeting 7, the matter was stated to be in abeyance and, at meeting 9, the JV was to action the item. At meeting 10, it was stated that:
"For the purpose of absolute clarity, it was agreed the risk/reward was limited to the labour hours and commensuratevalues.
JV still to review."
It was also noted that all outstanding matters, with the exception of risk/reward, had been addressed.
Venture
said that
Ledwood's
proposal of capping the risk element of the risk/reward was unacceptable. After a discussion, the conclusion was that the Joint
Venture
and
Ledwood
would review the notes and, as a post-meeting note, it stated:
"Ledwood
agreed to adhere to the original risk/reward principles, ie no capping."
There was no discussion on the figures in the table or the words in parenthesis "calculated and paid on completion".
various
agreements contained in the notes of the meetings into one exhibit. He submits that the phrase "calculated and paid on completion" is not a matter which can be added to Exhibit E by relying on the reference in Exhibit E to "full and concise details" being included in Exhibit F.
mechanism
is to be applied is not dealt with in Exhibit E, although, for instance, the timing of the payment of retention is dealt with in paragraph 9 of Exhibit E. I do not consider that the opening words of Exhibit E can incorporate into Exhibit E matters which are other than "full and concise details" of the agreement set out in Exhibit E.
Ledwood
dropped their requirement for a cap or limit on the risk element, there is no mention of when risk/reward was to be applied. Many matters were discussed in the meetings, and I do not consider that such matters can be relied on as being agreed unless there is evidence of such agreement.
mechanism
is to be applied in relation to interim payments.
Application 19 or Application 22?
Ledwood
made Application 19 in July 2007. Before the Adjudicator made his decision, there had been three further applications for interim payment, Applications 20, 21 and 22. Application 22 was made on 4th October 2007 and, on 11th October 2007, the Joint
Venture
issued a revised payment notice showing an amount of £267,332.73 (plus
VAT)
due to
Ledwood.
No adjustment was made at that stage in respect of risk and reward. When the Joint
Venture
received the Adjudicator's decision, they issued a further revision to the payment notice in relation to Application 22, in which they gave effect to the Adjudicator's findings on deductions, but assessed a deduction for risk and reward in the sum of £1,817,227. That revised payment notice, dated 19th October 2007, led, as I have said, to a negative sum due to
Ledwood.
Venture
contends that the Adjudicator did not decide that any payment was due and it was therefore entitled to treat his findings as applying to Application 22 and to revise the payment notice under clause 14.3 of the subcontract so that no net payment was due to
Ledwood.
Ledwood
should be entitled to payment, he was deciding whether the Joint
Venture
was entitled to make the deductions which they had made in respect of Application for payment 19. In determining that the Joint
Venture
had wrongly withheld £1,215,067.64 (excluding
VAT)
and that they should pay interest on that amount to "the date of actual payment", the Adjudicator was clearly intending, in my judgment, that the sum withheld should be paid.
"In the absence of any directions by the Adjudicator relating to the time for performance of his decision, the parties shall be required to comply with any decision of the Adjudicator immediately on delivery of the decision to the parties in accordance with this paragraph."
Venture.
The essential purpose of adjudication of interim payments is to allow a party to obtain cashflow. In general, therefore, the claiming party is entitled to receive the payment it should have received at the date of the interim payment without taking into account subsequent events or other claims for set-off: see the summary of earlier decisions in the judgment of Mr Justice Jackson in Balfour Beatty Construction
v
Serco [2004] EWHC 3336 at paragraph 53, cited below.
Venture
to use an adjustment to the payment notice for Application 22 to give effect to the Adjudicator's decision would ignore the wrongful deduction from Application 19 and permit the Joint
Venture
to take account of subsequent events and other rights of set-off which it was not entitled to deduct and did not seek to deduct from the payment due on Application 19. In my judgment, the Adjudicator's decision should be given effect by applying that decision to Application 19 and not Application 22.
The ability to set off for risk and reward on Application 19.
Venture
refers to the Adjudicator's finding that
Ledwood
was entitled to be paid at 28,486 hours and that Adjustment 14 made to Application 19 by the Joint
Venture
should not have been made. The Joint
Venture,
therefore, submits that the effect of the Adjudicator's decision is that a further 28,436 hours should be added. This then gives rise to a risk/reward adjustment which should now be made in respect of Application 19.
v
Serco, where he considered the previous decisions and said this at paragraph 53:
"I derive two principles of law from the authorities, which are relevant for present purposes.
(a) Where it follows logically from an adjudicator's decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator's decision, provided that the employer has given proper notice (insofar as required).
(b) Where the entitlement to liquidated and ascertained damages has not been determined either expressly or impliedly by the adjudicator's decision, then the question whether the employer is entitled to set off liquidated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case."
Venture
is entitled to recover a specific sum by way of adjustment of the risk/reward element?
Ledwood
has accepted that if risk/reward is to be deducted from Application 19, then summary judgment should be based on the figure of risk and reward of £797,139 on the basis of the Joint
Venture's
figures, that does not mean that there is an undisputed or indisputable application of risk/reward. The first question which has to be determined is whether such a set-off can be made.
Ledwood.
Indeed, he says at paragraph 58 that, even at the end of September 2007,
Ledwood
had not expended more than the properly revised target hours.
Venture
can set off a sum for the risk/reward adjustment against the Adjudicator's decision relating to Application 19.
Summary
Ledwood
is entitled to summary judgment, based on the Adjudicator's decision, for the sum of £1,215,067.64 plus applicable
VAT,
together with interest on which I will hear submissions.
Costs
Ledwood
that it has been successful and, therefore, it should have its costs. On behalf of the Joint
Venture,
it is submitted that there was an important issue between the parties relating to the ability to apply the risk/reward régime prior to completion, which has been decided in favour of the Joint
Venture.
Ledwood's
claim to obtain summary judgment, which it has succeeded in obtaining. Therefore, it is clear, in my
view,
that prima facie they are entitled to their costs. However, as in many cases there are issues which can be usefully determined as part of a Part 8 application. In this case, in particular, the issue of whether or not risk/reward can be applied on an interim basis has been considered and determined in favour of the Joint
Venture
and was evidently a matter which needed resolution. In those circumstances, I consider that in my discretion I should take into account the fact that a great deal of the argument related to the issue of risk/reward on which the Joint
Venture
have succeeded. In my judgment, the appropriate way of dealing with it is to allow the Claimant 70% of their costs and to summarily assess those on a standard basis.
VAT
(which should be excluded in this case), shows a figure of £26,974 as costs. It is said on behalf of the Joint
Venture
that there may be some duplication within the attendances figure and the work done on documents. When the court is carrying out a summary assessment, it should be aware that it is carrying an assessment on a summary basis and that if a detailed assessment were carried out, there would be a more detailed enquiry into the matter. I consider that when assessing on a summary basis there is a need to be cautious about certain hours expended. The reasonableness of that is for
Ledwood to demonstrate.