![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Air Design (Kent) Ltd v Deerglen (Jersey) Ltd [2008] EWHC 3047 (TCC) (10 December 2008) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2008/3047.html Cite as: [2009] CILL 2657, [2008] EWHC 3047 (TCC) |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AIR DESIGN ( KENT) LIMITED |
Claimant |
|
| - and - |
||
DEERGLEN ( JERSEY) LIMITED |
Defendant |
____________________
Gaynor Chambers (instructed by Speechley Bircham) for the Defendant
Hearing dates: 25 November 2008
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
Mr Justice Akenhead:
Introduction
Air
Design
(
Kent)
Ltd
("
Air
Design"),
a small mechanical services company based in Yalding,
Kent
seeks to enforce against the main contractor,
Deerglen
(
Jersey)
Ltd,
which employed
Air
Design
as a sub-contractor on a project known as Liberty Wharf Phase 3 in
Jersey
in the Channel Islands. Issues are raised to the effect that the adjudicator had no or insufficient jurisdiction because there were two, three or four sub-contracts between the parties and there were multiple disputes. If the decision is enforceable,
Deerglen
seeks a stay of execution.
The factual and contractual background
Deerglen
was the main contractor employed in August 2006 by Islands Development
Ltd
("IDL") to
design
and build a 6 storey office building known as Liberty Wharf Phase 3. The standard form JCT with
design
contract was subject to the Law of
Jersey.
Deerglen
and
Air
Design
entered into a written contract dated 16 April but signed on 17 April 2007 whereby
Air
Design
undertook to carry out mechanical services work for this project; these works were sometimes referred to as the "basebuild" works. The contract ("the Basebuild Contract") was in relatively simple terms set out on one page headed "Scope of works for the mechanical installations" and there was listed a number of documents which were to be incorporated as well as some simple terms such as that "all works shall be completed by the end of September 2007". The "contractual basis" was stated to be "JCT intermediate". There was a mild argument as to whether this was the 1998 or the 2005
version.
Nothing turns on that point but the parties accepted that English Law applied. It is accepted that the First Sub-Contract contained an adjudication clause which incorporated the statutory Scheme.
Air
Design
to
Deerglen
was one of the documents incorporated in to the First Sub-Contract and it confirmed that the agreed price was £1,358,950 and that this price did not "form part of CPA fitout". This was a reference to the fact that one of IDL's tenants, for the 3rd to the 5th floors, was to be CPA and presumably the let areas were to be fitted out as agreed with the tenant. Another incorporated letter was dated 21 March 2007 from
Air
Design
to
Deerglen
which spelt out what work was to be done from the basement to the roof. The First Sub-Contract works duly commenced.
Deerglen
asked
Air
Design
to quote for the mechanical services work for and in connection with the CPA fitting out works which were to be added as a
variation
to their main contract with IDL. Tender drawings (dated 6 February 2007), provided by IDL's engineers Janowski, and specifications provided by CPA were given to
Air
Design
upon which to quote.
Air
Design
quoted the sum of £325,000, which was confirmed in their letter dated 23 May 2007 to
Deerglen;
that letter confirmed that on 21 May 2007
Deerglen
had instructed
Air
Design
to proceed with these CPA works. This letter was repeated almost
verbatim
in a later letter dated 29 May 2007. Both letters provided a financial breakdown of the sum of £325,000 and went on to say:
"…we have made no allowance for the following…:
1…7
8. Building Management System
9. No leak detection has been allowed. [This was added by the later letter]
Our contract conditions are based upon the original base build contract and the figures stated above offers [sic] no reduction to base build prices and includes additions only. Please refer to previous correspondence regarding CPA contract. We refer to the recent base build contract and technical submissions."
Deerglen
sent a "Letter of Intent" to
Air
Design.
It was entitled "Liberty Wharf Phase 3-CPA Fit Out-Letter of Intent" and went on:
" We herewith assign you to perform the Mechanical Installations for the CPA mechanical fit out for the above named building project.
The scope of the work is:
1. The tender documents, drawings (as listed in the attachment) provided by Janowski… and the specifications 'Part D' provided by CPA.
2. Thevalue
of this contract is £325,000 as a lump sum…
Notwithstanding that we are not in a position to present you with a formal contract for implementation, it is our intention to instruct you to carry outvarious
elements of the proposed work.
Should, for any reason whatsoever, a formal contract not be implemented our liability pursuant to this letter will be limited to the reimbursement of the net cost reasonably and necessarily incurred by you in respect of this work.
I confirm that in the event that a formal contract will be signed, any money that may have been paid to you pursuant to this letter of intent shall be deemed to be interim payments and will be deducted from the contract sum.
I would be grateful if you would sign this letter as confirmation of your agreement to its terms and return a copy back to me"
Air
Design
duly signed and returned the letter on 15 June 2007. I will refer to this as the "CPA Arrangement".
Deerglen
sent to
Air
Design
a letter entitled "Liberty Wharf Phase 3 BMS and Comms Room Cooling" which materially stated:
"I hereby assign you to perform the following services in extension of the existing contract.
1. Building Management System
The scope of the works is based on the quote from 25/6/07 but not necessarily limited to this. The contractor shalldesign,
deliver, install, test and commission a complete and functionable building management system, minimum comprising the following…
2. Cooling CPA comms room
The contractor shalldesign,
deliver, install, test and commission a complete and functionable second cooling system for the comms room on 4th floor according to the tenants (CPA) specifications, minimum comprising the following…
3. Cooling CPA build room
The contractor shalldesign
a complete and functionable cooling system for the build room on 4th floor according to the tenants (CPA) specifications…
4. Price agreement
The total price for all the above listed works is agreed to be £53,500…
Please sign a copy of this instruction as confirmation of your acceptance of the conditions outlined therein and send it back to us."
The letter was duly returned signed by
Air
Design.
I will call this the "BMS Arrangement".
Air
Design
for the Base build, CPA and BMS works.
Jersey
Mechanical Installations". It stated as follows:
"Main Contract
AKL [Air
![]()
Design]
is assigned by
Deerglen
as follows:
Base-built £1,358,950.00
CPA fit-out £ 325,000.00
BMS £ 53,000.00
Total £ 1,736,950.00
An amount of £1,559,303.71 out of this contract sum has been paid byDeerglen,
the remaining amount is £177,646.28.
Deerglen
will pay this remaining amount reduced by £13,500 when AKC has cleared all major defects, carried out all remaining works, set all systems to proper operation and handed over the documentation…
The remaining £13,500 will be due for payment after completion of the base-built works on ground floor..
2.Variations
AKL'svariation
list from 20,11,2007 (items 1 to 45) was checked by
Deerglen
(checked
version
handed over to AKL).
Deerglen
accepts a total amount of £56,936.05 for the listed
variations
with an amount of £30,571.15 due for payment. Both sums are reduced by £10,571.15 for works that were caused by AKL and had to be carried out by others and were paid by
Deerglen.
![]()
Deerglen
will pay £20,000 on 30/11/2007.
The remaining amount of £26,364.90 will be paid on 30/11/2007 according to rendered works.
Maintenance
AKL will assign a local company for maintenance works and clearing minor defects…"
The
variation
list referred to contained
variations
both to the Base build and CPA works.
Air
Design
had finished the works, what was due to it and as to whether there were any remaining defects.
Air
Design
instructed a claims consultant, Knowles, who wrote to
Deerglen
on 27 March 2008 asserting that there was one contract albeit subject to the Supplementary Agreement and claiming a total of £341,992 which related to the sum of £177,646.28 declared to be due in the later agreement and the remainder for what
Air
Design
asserted was the true
value
of
variations.
Deerglen's
Solicitors' response of 1 April 2008 was:
"…It is agreed that there was a contract between our respective clients in respect of mechanical installations at the Liberty Wharf Phase 3 office building and that this contract was subject to the supplementary agreement dated 29 November 2007.
The purpose of that later agreement was perfectly clear…"
The issue taken was that the Supplementary Agreement was effectively a settlement of the money claims between the parties and set an agreed agenda for finishing of and putting right the work. That was challenged by Knowles shortly thereafter.
Air
Design
served on
Deerglen
a Notice of Intention to refer a dispute to adjudication on 7July 2008 referring to there being one contract dated 16 April 2007
varied
by the Supplementary Agreement of 29 November 2007 and to carrying out "
varied
and additional work". The RICS nominated Mr Harvey Mason as adjudicator. There is no challenge to the way in which he was appointed.
"1.1Deerglen
… contracted with
Air
![]()
Design
… by an Agreement dated 16 April 2007 for AKL to carry out mechanical services installations at
Deerglen's
site known as Liberty Wharf Phase 3.
1.2 The agreement referred to in Paragraph 1.1 stated that 'the contractual basis is JCT Intermediate', …
1.3 AKL carried out the work contracted for, includingvaried
and additional work.
1.4 Prior to AKL's completion, at a meeting on 29 November 2007, the parties reached agreement tovary
the payment arrangements to the remainder of the contract. …
1.6 The IC Sub/D/C form of contract at Section 8 provides for Adjudication …
2.1 The Contract was concluded by the Agreement dated 16 April 2007 …
3.1 By a Supplementary Agreement dated 29 November 2007 [there is then a summary of that Agreement] …
3.3Deerglen
failed to make further payments either as agreed or at all and consequently repudiated the Agreement, in any event.
3.4 AKL have subsequently sought payment for both the sums listed in the Supplementary Agreement and by reason of AKL'sVariation
Account, but have been paid no further moneys."
Air
Design
listed "matters to be decided by the Adjudicator":
"1. The Adjudicator is asked to decide if the Agreement dated 29 November 2007 did not extend to thevaluation
of the final account and/or the
variation
account but was solely an agreement that the sum was to be paid as interim payment.
2. The Adjudicator is asked to decide that AKL'svariation
account be
valued
at £309,277.71 or such other sum as the Adjudicator shall decide.
3. The Adjudicator is asked to decide that AKL be paid a further £468,704.09 as balance of their account or such other sum as the Adjudicator shall decide.
4. The Adjudicator is asked to decide that AKL be paid interest for late payment …
5. The Adjudicator is asked to decide that AKL have currently no further obligations with regard to defects and/or incomplete work.
6. The Adjudicator is asked to decide thatDeerglen's
contra charges are both unjustified and unsubstantiated …"
Deerglen
took the point that there were four contracts between the parties. It sought to argue that disputes relating to at least three if not four separate contracts were being sought to be referred to adjudication and that since there was no adjudication clause in what was said to be separate contracts relating to the CPA Works Arrangement and the BMS Arrangement (and possibly the Supplementary Agreement), the Adjudicator had no jurisdiction over disputes which arose out of those contracts.
Air
Design's
response to this was to say that the Adjudicator did have jurisdiction essentially arguing that the CPA and BMS Arrangements were simply
variation
agreements and that the Supplementary Agreement was simply
varying
terms and timings of payments.
Deerglen
prefaced their submissions as follows:
"These submissions and the Responding Party's continued participation in this adjudication are served without prejudice to the Responding Party's contention that the Notice and Referral are deficient and/or that the Adjudicator in any event had no jurisdiction as is set out below. For the avoidance of doubt, the Responding Party reserves the right to expand on these arguments in any enforcement proceedings in due course should the necessity arise, and/or to take any or all points on jurisdiction which are available to it."
At
various
points in the
various
submissions
Deerglen
asked the Adjudicator to do
various
things, for instance:
"(a) Therefore the Adjudicator should enquire into his jurisdiction and determine that he does not have any." (Para 8 Submissions on Jurisdiction)
(b) … As the letter [12 September 2007 relating to the BMS Arrangement] of itself contains all the necessary ingredients to form a binding contract the Adjudicator is invited to find that this is what in fact occurred." (Para 21 ibid)
(c) Accordingly, the Notice and the Referral are deficient and the Adjudicator should decline to reach any determination on the matters AKL has sought to refer. (Paragraph 31 ibid)
(d) It is accordingly indisputable that this reference is flawed and that the Adjudicator should decline to make any decision or determination in this matter. (Paragraph 58n ibid)
(e) Therefore, as the Adjudicator finds that there was in fact more than one contract (whichDeerglen
is clear that he must) the reference can go no further and the Adjudicator must decline to continue to act. (Paragraph 2 Reply Submissions)
(f) This argument [relating to the Supplementary Agreement] cannot be sustained and should again be rejected by the Adjudicator."(Paragraph 15 ibid).
various
submissions as follows:
"The purpose of this letter is to set out myviews
on the claim by the Responding Party that I do not have jurisdiction to continue with this adjudication based on the case advanced through the Referral Notice …
In summary, it is the case forDeerglen
that the dispute that has been referred to me is not a dispute under one contract, but under three if not four contracts … There is no dispute that I have jurisdiction to deal with the dispute that arises under the Basebuild Contract …
The CPA Works and the BMS System can be considered together. The question is whether is these Works constituted separate contracts as contended for byDeerglen
or
variations
to the Basebuild Contract as contended for by
Air
![]()
Design.
It must follow that should I agree with the submissions on behalf of
Deerglen
then I do not have jurisdiction to deal with anything other than a dispute arising under the Basebuild Contract in this adjudication …
This situation is clearly one that would have benefited from better paperwork being put in place. I have difficulty in accepting the statement of Mr Frenzel with regard to the way that applications were submitted byAir
![]()
Design
and paid by
Deerglen.
It is not at all difficult to see why applications might have been made in the way that they were but as part of a simple contract. This is particularly true of a project such as this where certain costs need to be passed on outside of the immediate contractual arrangement and Mr Frenzel makes reference to this in Paragraph 12 of his statement.
I find nothing in the submission before me to support the contention ofDeerglen
that they entered into three separate Works Contracts and I agree with the submissions of
Air
![]()
Design
that the Works were all instructed and carried out as part of a single contract for the reasons they have set out. …
I do not consider this [the Supplementary Agreement] to be anything more than an agreement tovary
the payment terms under the Contract on the achievement of certain milestones.
As the representatives of the parties will be aware, I do not have power to decide my own jurisdiction. I can only investigate any challenges to it and report my non-bindingview.
It follows from the foregoing that I do not agree with the challenge to my jurisdiction on behalf of
Deerglen
and, as a consequence, I am able to and should continue with the adjudication as referred on behalf of
Air
![]()
Design.
…."
verbatim,
his response to the jurisdictional challenge of 4 August 2008. Although reasons were not specifically requested, the Adjudicator proceeded to give reasons for his decision on the merits of the
various
claims and contra charges. He found that the Supplementary Agreement "did not extend to the
valuation
of the final account and/or the
variation
account". He effectively decided that that Agreement simply dealt with further interim payments. He proceeded to consider all disputed items on the
variation
account including those relating to the CPA and BMS Arrangements in effect as arising under one contract. He considered the contra charges relating to defects and snags. Although he substantially reduced
Air
Design's
claims, he found that
Deerglen
should pay
Air
Design
£139,964 exclusive of
VAT
and that interest should be paid in the sum of £5,487.58 and daily after his Decision at the rate of £39.20 per day. He ordered
Air
Design
to pay part of his fees and
Deerglen
to pay the sum of £14,504.12 inclusive of
VAT.
These proceedings
Deerglen
having not paid the sum decided by the Adjudicator to be due,
Air
Design
issued proceedings in the Technology and Construction Court seeking to enforce by way of summary judgment that Decision. Witness statements were exchanged.
The Adjudicator's Finding on Jurisdiction
Air
Design
is that the parties gave the Adjudicator jurisdiction to decide the issue of jurisdiction. If that was the case,
Air
Design
would have a good point. However it is a point which cannot succeed for the following reasons:
(a) It is abundantly clear that in their submissions to the Adjudicator the clearest possible reservation on jurisdiction was made byDeerglen
at the beginning of their written submissions (see above).
(b) One needs to read the contents of those submissions in the light of thatvery
clear reservation. Requests in those submissions to the Adjudicator to "find" or "determine" this or that are clearly subject to the reservation. In any event Paragraph 8 of the first set of submissions makes it clear that all that
Deerglen
were asking the Adjudicator to do was to "enquire into his jurisdiction and determine that he does not have any" jurisdiction.
(c) I am satisfied that the Adjudicator did not and did not purport to reach a decision as such on jurisdiction. As set out above, he makes it clear that he believed that he did "not have the power to decide [his] own jurisdiction". All he did was to "investigate any challenges to" his jurisdiction and "report [his] non-bindingview".
The fact that he repeated
verbatim
the contents of his letter of 4 August 2008 in his formal decision does not in logic affect this
view.
One, two, three or four contracts
views:
(a) The Basebuild Contract was one which incorporated the standard JCT Intermediate Form of sub-contract. That contains provisions for the ordering ofvariations.
(b) In context, the BMS Arrangement was clearly agreed to be part of the Basebuild Contract. Its reference to the "existing Contract" must have referred to the Basebuild Contract. The CPA Arrangement was not the subject of a "formal contract" since the signed Letter of Intent clearly envisaged that there would be a formal contract to be implemented. Thus on its face the BMS Arrangement was clearly intended to be dealt with as if it was part of the Basebuild Contract. The fact that it refers to work in the CPA part of the Project is neither here nor there. It was still all mechanical services work.
(c) The Supplementary Agreement of 29 November 2007 at thevery
least was simply determining or
varying
existing or previous contract arrangements relating to payment or payments,
variations
and maintenance. It was an agreement in writing which
varied
either one or a number of pre-existing agreements.
(d) The CPA Arrangement is a signed Letter of Intent which envisages that, following its issue, if no formal contract was implemented,Air
![]()
Design
would be entitled to the "net costs reasonably and necessarily incurred by" it in respect of such work as was done. It envisaged a formal contract but what it did, simply, was to identify that it was
Deerglen's
"intention to instruct"
Air
![]()
Design
to carry out
various
elements of the proposed CPA Work. In fact, it was the case that instructions had already been given before this Letter of Intent was sent out. One then has to ask upon what basis instructions to carry out such work were being given. The pre-existing Basebuild Contract contained provisions for instructions requiring
variations
to be carried out. The CPA Work was clearly a
variation
to the Basebuild Contract Works. Properly classified, it is probably the case that the instructions calling for the CPA Work issued in connection with this Letter of Intent would be classified as instructions issued under the Basebuild Contract. The quotation giving rise to the instruction made it clear that
Air
![]()
Design's
"contract conditions are based upon the original base build contract" and that is a clear reference back to the Basebuild Contract. The fact that a formal contract relating to the CPA Work was envisaged does not take the matter
very
much further. If a formal, separate and separable contract had been signed by the parties (and none was available for consideration at the time of this Letter of Intent), it is at most possible that it would have been negotiated as an entirely separate contract, that is, one that was considered as entirely separate from the Basebuild Contract; commonsense would suggest that the greater possibility is that it would like the BMS Arrangement have been tied back to the Basebuild Contract.
(a) The substantive decision-making process upon which the Adjudicator had to embark in relation to the disputed claim put before him necessarily involved a consideration of whether there was more than one contract. It was thus within his jurisdiction to decide in effect that there was one contract, albeit one that may have beenvaried
by agreement.
(b) It was thus a part of his jurisdiction to decide whether or not and if so to what extent the Basebuild Contract had beenvaried
by the CPA and BMS Arrangements and indeed whether there were yet further
variations
ordered to the Basebuild Contract. There may be cases, and this is clearly one, where substance and jurisdiction overlap so that it is within the Adjudicator's jurisdiction to decide as matters within his or her substantive jurisdiction whether there have been in effect
variations
to the contract pursuant to which he or she has properly been appointed Adjudicator. It cannot then in those circumstances be a
valid
challenge to his or her jurisdiction that upon analysis he or she may be wrong as a matter of fact or law in determining that such
variations
were made to the originating contract as opposed to a series of later legally unconnected contracts.
(c) The Supplementary Agreement is one which recognises in a way which has contractual effect that the parties were treating their contractual relationship as being in one "main contract". The total of the three sums agreed originally to be due with regard to the Basebuild, CPA and BMS Works are said to be a "contract sum"; thevariations
are being treated as a single
variation
list to be addressed; maintenance and defects liability obligations are being treated as arising in effect as a unified obligation. It is this one "main contract" which is effectively being
varied.
Thus, whatever the arrangement or arrangements contractually were before, as from the Supplementary Agreement the parties clearly agreed to treat their contractual relationship as stemming from one contract.
view
that the Adjudicator did have jurisdiction to rule on all the matters which he did decide in his Decision. Whether he was right or wrong to find or make the assumption that there was effectively one contract which was
varied
and whether he was wrong as a matter of fact or law in any other part of his decision is immaterial. Any such errors do not mean that he does not have jurisdiction. Even if I was wrong about that conclusion, then my analysis that effectively the CPA and BMS Arrangements and the Supplementary Agreement were simply
variations
of the Basebuild Contract would apply.
"In my opinion the construction of an arbitration clause should start from the assumption that the parties, as rational businessmen, are likely to have intended any dispute arising out of the relationship into which they have entered or purported to enter to be decided by the same tribunal. The clause should be construed in accordance with this presumption unless the language makes it clear that certain questions were intended to be excluded from the arbitrator's jurisdiction."
Whilst it could be argued that, if there were entirely separate contracts between the same parties which had obviously different dispute resolution clauses, there should be separate dispute resolution processes, in the current case all the disputes could properly be said to have arisen under the Basebuild Contract and the commercial parties could properly be said to have intended to have agreed to the adjudicator appointed under that contract to have jurisdiction to determine the
value
of sums due under that contract and any
variations
to that contract.
Stay of execution
Deerglen
have serious concerns that AKL will not be able to repay any sum paid by
Deerglen
pursuant to the Decision of the Adjudicator.
Deerglen
points to the accounts of
Air
Design
which show shareholders' funds as £48,870, £75,099, £20,555 and £831 for the years ending 31 January 2004, 2005, 2006 and 2007 respectively. The accounts for the year ending 31 January 2008 are not available. Being a relatively small company,
Air
Design
has not filed profit and loss accounts but only abbreviated balance sheets. It is said that this reduction in shareholders' funds or net assets infers a probability that
Air
Design
will be unable to repay the judgment sum if and when it is established that all or part of it should not have been paid over.
v
Derek
Vago
[2005] BLR 374, HHJ Coulson QC (as he then was) properly summarised the law in relation to stays of execution in adjudication proceedings at Paragraph 26:
"(a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) isdesigned
to be a quick and inexpensive method of arriving at a temporary result in a construction dispute.
(b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money.
(c) In an application to stay the execution of summary judgment arising out of an Adjudicator's decision, the Court must exercise its discretion under Order 47 with considerations (a) and (b) firmly in mind …
(d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell).
(e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House).
(f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if:
(i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or
(ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)."
Air
Design
is, currently insolvent. Indeed, the accounts for the year ending 31 January 2007 will obviously not have taken into account the fact that in the following accounting period over £1.3m was paid to
Air
Design
by
Deerglen;
that is without taking into account any other projects which
Air
Design
was working on (if any). It is not appropriate for the Court to speculate what the next set of accounts will or may show. As the onus is on the Defendant to establish insolvency, I am satisfied that it is has not proved that
Air
Design
is insolvent.
Air
Design's
financial position is the same or similar to its financial position at the time that the relevant contract was made. As the contract was made in April 2007, even if one assumed that its net assets were still no more than about £800, it would be in no worse financial position now than it was then. The fact that
Deerglen
had no access to the accounts for the year ending 31 January 2007 in April 2007 does not alter this
view:
the accounts show what the financial position was at the relevant time. The available accounts for the year ending 31 January 2005 which show only £20,555 as the net assets are not in relative terms much better than the accounts for the later year. In those circumstances, I decline to impose a stay of execution.
Decision
Air
Design for the sums claimed together with interest at the rates claimed. There will be no stay of execution.