You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Roche Diagnostics Ltd v The Mid Yorkshire Hospitals NHS Trust [2013] EWHC 933 (TCC) (19 April 2013) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2013/933.html Cite as: [2013] EWHC 933 (TCC), [2013] PTSR D35 |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Buy ICLR report: [2013] PTSR D35]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ROCHE DIAGNOSTICS LIMITED |
Claimant/ Applicant |
|
| - and - |
||
THE MID YORKSHIRE HOSPITALS NHS TRUST | Defendant/ Respondent |
____________________
Mr Nigel Giffin QC (instructed by DAC Beachcroft LLP) for the Defendant/Respondent
Hearing date: 26 March 2013
____________________
VERSION
OF JUDGMENT
Crown Copyright ©
The Hon. Mr Justice Coulson:
1. INTRODUCTION
hospitals
in West
Yorkshire.
It is currently seeking to let a Managed Service Contracts ("MSC") for the provision of laboratory services at three main centres, in Wakefield, Dewsbury and Pontefract. The MSC is intended to last for 10 years. Although, in recent years, an unhappy combination of the political imperative to privatise services of this kind that used to be performed by public authorities, and the need to comply with the complexities of the Public Contract Regulations 2006 (as amended), has led to a major increase in procurement disputes, the tender exercise in this case has been particularly protracted: I am told that this is the fifth attempt to let this MSC. The claimant has been successful in at least one of the earlier, abandoned exercises, but was not the successful tenderer in the most recent evaluation.
Diagnostics
Ltd
("Abbott"). The claimant now seeks to challenge the fairness of this procurement exercise.
2. THE PROCUREMENT DISPUTE
"To calculate the amount payable in Year 6, Schedule 8 paragraph 1.1.1 [of the ITT] states clearly that the amount payable per test will be the relevant Unit Price up to and including the AssumedVolume.
The Unit Price remains the same unit price that
Roche
provided in its spreadsheet. The same fixed costs per test apply and the same marginal costs per test apply. However the effect of the increase in the Assumed
Volume
means the total fixed costs increases as the number of tests within the Assumed
Volume
envelope has increased."
In the claimant's solicitors response of 30 November, there was an attachment prepared by Mr Monster, the claimant's Finance Director. In dealing with this change of position at year 6 he said:
"As the two critical foundations for the re-baseline of Year 6 are the actualvolume
and the actual total cost of year 5 and as the actual
volume
of year 5 has been transposed correctly to year 6, it follows naturally that the actual costs for year 5 should have been transposed as well. Any other outcome is not only contrary to the ITT and a financial failure, but also a failure of logic."
3. THE APPLICATION FOR SPECIFIC DISCLOSURE
"31.12(1)
(1) The court may make an order for specific disclosure or specific inspection.
(2) An order for specific disclosure is an order that a party must do one or more of the following things –
(a) disclose documents or classes of documents specified in the order;
(b) carry out a search to the extent stated in the order;
(c) disclose any documents located as a result of that search."
v
Eurostar International Limited [2010] EWHC B32(Ch),
Vos
J made an order for specific disclosure in a procurement case because of the potential importance of the information relating to the tender evaluation, known only to the defendant. In reaching that conclusion, he relied on his earlier decision in Arsenal Football Club
v
Elite Sports Distribution Limited [2002] EWHC 3057 (Ch), in which he had set out the principles governing pre-action disclosure, and explained the overlap between that process and the ordering of specific disclosure at an early stage in the proceedings.
Vos
J followed the approach in Black
v
Sumitomo Corporation [2002] 1 WLR 1562, a pre-action disclosure case, in which Rix LJ said:
"What, however, these authorities on the unamended section of my judgment reveal, and usefully so, is as follows: first, that at any rate in its origin the power to grant pre-trial disclosure was not intended to assist only those who could already plead a course of action to improve their pleadings, but also those who needed disclosure as avital
step in deciding whether to litigate at all or as a
vital
ingredient in the pleading of their case. Secondly, however, that, as what I would call a matter of discretion, it was highly relevant in those cases that the injury was clear and called for examination of the documents in question. The disclosure requested was narrowly focussed and bore directly on the injury complained of and responsibility for it in the documents would be decisive on the conduct or even the existence of the litigation."
v
Northern Ireland Water [2012] NIQB 7. That was a procurement case in which, pursuant to rather different procedural rules, the judge declined an application for discovery of documents prior to delivery of the statement of claim. However, I do not consider that that case sets out any statement of principle. It is apparent that the judge's approach was informed by his clear conclusion that the claimant's application in that case was a pure fishing exercise.
v
HM Treasury [2009] BLR 425 and Croft House Care
Ltd
and Others
v
Durham County Council [2010] EWHC 909 (TCC), do not arise for consideration.
view,
the following broad principles apply to applications for early specific disclosure in procurement cases:
(a) An unsuccessful tenderer who wishes to challenge the evaluation process is in a uniquely difficult position. He knows that he has lost, but the reasons for his failure are within the peculiar knowledge of the public authority. In general terms, therefore, and always subject to issues of proportionality and confidentiality, the challenger ought to be provided promptly with the essential information and documentation relating to the evaluation process actually carried out, so that an informedview
can be taken of its fairness and legality.
(b) That this should be the general approach is confirmed by the short time limits imposed by the Regulations on those who wish to challenge the award of public contracts. The start of the relevant period is triggered by the knowledge which the claimant has (or should have) of the potential infringement. As Ramsey J said in Mears
Ltd
![]()
v
Leeds City Council [2011] EWHC 40 (QB), "the requirement of knowledge is based on the principle that a tenderer should be in a position to make an informed
view
as to whether there has been an infringement for which it is appropriate to bring proceedings".
(c) However, notwithstanding that general approach, the court must always consider applications for specific disclosure in procurement cases on their individual merits. In particular, a clear distinction may often be made between those cases where a prima facie case has been made out by the claimant (but further information or documentation is required), and those cases where the unsuccessful tenderer is aggrieved at the result but appears to have little or no grounds for disputing it.
(d) In addition, any request for specific disclosure must be tightly drawn and properly focused. The information/documentation likely to be the subject of a successful application for early specific disclosure in procurement cases is that which demonstrates how the evaluation was actually performed, and therefore why the claiming party lost. Other material, even if caught by the test of standard disclosure, is unlikely to be so fundamental that it should form the subject of a separate and early disclosure exercise.
(e) Ultimately, applications such as this must be decided by balancing, on the one hand, the claiming party's lack of knowledge of what actually happened (and thus the importance of the prompt provision of all relevant information and documentation relating to that process) with, on the other, the need to guard against such an application being used simply as a fishing exercise, designed to shore up a weak claim, which will put the defendant to needless and unnecessary cost.
"1. In relation to each and every error made by the Defendant in its evaluation of bids, documents (electronic or otherwise) which evidence (1) the date that the error was discovered; (2) the error; (3) its correction and the date of that correction; (4) its effect on the NPV of our client's bid; and (5) the effect on the percentage difference between the NPV of our client's bid and that of Abbott.
2. Documents relating to any independentverification/audit
of the Defendant's initial and all subsequent evaluations, particularly following the Defendant's discovery of
various
errors in its evaluation.
4. All documents (electronic or otherwise) relating to the Defendant's initial evaluation and any subsequent evaluations of the Claimant's bid and that of Abbott, regardless of whether any re-evaluation was undertaken in relation to only one or both bidders. These documents should be contemporaneous (rather than an extract or copy created specifically for the Claimant) and should demonstrate how the Defendant has calculated each bidder's costs in accordance with all of the content in the ITT (including instruction 5 of Spreadsheet 1). For the avoidance of doubt, this should include the Defendant's treatment of Fixed Costs and its calculation of the same for year 6 and also the Defendant's evaluation of additional assays. Furthermore, the documents should show the impact on the calculation of NPV for each bid.
5. All documents containing any instructions and/or guidance provided to the Defendant's internal team for evaluation of bids.
6. Any internal reports, minutes and notes of any meetings (whether handwritten or electronic) and any emails created and/or circulated in relation to the Defendant's initial and any subsequent evaluations, and particularly relating to the Defendant's reasoning for awarding the contract to Abbott."
view
that the evaluation process has been inept? Even if, by the time of the trial, the question has narrowed down to a simple matter of construction, the claimant is entitled to reach its own conclusion on that point and, in my judgment, it can only do so by seeing the documents relating to the evaluation actually performed.
view,
as the unsuccessful bidder challenging this (somewhat chequered) procurement process, the claimant is entitled now to see
various
specific categories of documents by way of specific disclosure. This will allow the claimant the opportunity of taking a considered
view
of the evaluation process; it will allow each side to approach what happened at the evaluation on the basis of the same information; it will make it more likely that the parties will be able to reach agreement at the forthcoming 'without prejudice' meeting; and it will save costs.
versions
of the spreadsheets have been provided. Thus, in my
view,
the claimant is entitled to see the instructions that were given to the evaluation team setting out the methodology that they were instructed to follow.
4. THE INTERIM CONTRACT
various
abandonments and delays, so the defendant knows that the claimant is keen to bid for all aspects of the MSC work. It appears that the laboratory services at Dewsbury were provided by a company called Beckman, but their contract was terminated in the
middle
of 2012. For reasons which currently remain obscure, Abbott was given an interim contract to perform the laboratory services at Dewsbury, which may have included the carrying out of certain building works at the site.
very
real risk of an overlap) between the works which are the subject of the claimant's procurement challenge, and the works and/or services which may have been let to Abbott pursuant to an interim contract, for which the claimant was not invited to tender.
value
of the interim contract is small, in part because it will come to an end as and when the procurement process in respect of the MSC has been resolved.
5. THE APPLICATION FOR PRE-ACTION DISCLOSURE
"(3) The court may make an order under this rule only where–
(a) the respondent is likely to be a party to subsequent proceedings;
(b) the applicant is also likely to be a party to those proceedings;
(c) if proceedings had started, the respondent's duty by way of standard disclosure, set out in rule 31.6, would extend to the documents or classes of documents of which the applicant seeks disclosure; and
(d) disclosure before proceedings have started is desirable in order to –
(i) dispose fairly of the anticipated proceedings;
(ii) assist the dispute to be resolved without proceedings; or
(iii) save costs."
v
Sumitomo (ibid). At paragraph 81 of his judgment, Rix LJ said:
"…for jurisdictional purposes the court is only permitted to consider the granting of pre-action disclosure where there is a real prospect in principle of such an order being fair to the parties if litigation is commenced, or of assisting the parties to avoid litigation, or of saving costs in any event. If there is such a real prospect, then the court should go on to consider the question of discretion, which has to be considered on all the facts and not merely in principle but in detail."
"8. Documents confirming why it was necessary for the Defendant to engage an alternative provider at Dewsbury.
9. Documents confirming whether Abbott was and is an incumbent provider of services at Dewsbury.
10. Documents confirming from whom and when the Defendant sought estimates/quotes for the contract at Dewsbury, which should include confirmation of when it first made enquiries of Abbott and (if such documents exist) why the Defendant did not approach the Claimant (whose interest in this procurement was known, not least because they have bid in previous abandoned procurements for these services).
11. Documents confirming why the Defendant chose to award the contract at Dewsbury to Abbott, the date of the award decision and the date of the start date of that contract with Abbott.
12. A copy of the Defendant's contract at Dewsbury with Abbott which should confirm the nature of the agreement and the sums payable to Abbott. These documents should enable the Claimant to properly determine whether the Defendant has in fact made an illegal direct award to Abbott with reference to the relevantvaluation
and aggregation rules in the Regulations.
13. In so far as it is not clear from the Defendant's contract with Abbott, documents confirming what tests the Defendant is currently commissioning from Abbott at Dewsbury, including confirmation of any optional tests commissioned (as defined in the current procurement).
14. Documents confirming what arrangements the Defendant has in place/intends to put in place for the testing at the other sites covered by the current tender.
15. Documents confirming:
15.1 What building works, if any, have already been undertaken at Dewsbury, or are due to be undertaken at Dewsbury, under the interim contract with Abbott;
15.2 What permanent works have been proposed by Abbott as part of their submission for the current tender; and
15.3 The impact of Abbott's appointment at Dewsbury on the Defendant's evaluation on the current tender."
very
least what might be regarded as enabling works for the MSC) could now be carried out pursuant to a contract for which the claimant never even had the opportunity to bid.
v
Sumitomo, I consider that it would help to dispose fairly of the anticipated proceedings, and/or would assist that dispute to be resolved without proceedings at all, if the documentation relating to the invitation to tender and the contract itself were provided to the claimant. They would be caught by standard disclosure in any litigation between these parties over the legality of the letting of the interim contract. Their disclosure now would certainly save costs. Moreover, as a matter of discretion, I consider that such documentation should be provided in order that the real issues can be identified and, if possible, resolved. Indeed I have already commented on my surprise that this basic information was not provided to the claimant
voluntarily.
very
least a potential overlap between the works at Dewsbury that were the subject of the ITT, and the works that were the subject of the interim contract. Indeed, it cannot sensibly be suggested otherwise. In such circumstances, item 15 in the schedule relates to documents which, in my judgment, are disclosable now, either under CPR r.31.16 or by way of specific disclosure under r.31.12. Either way, that material should be disclosed.
6. CONCLUSIONS
very grateful to both counsel for the economy and clarity of their submissions.
Note 1 I understand that in Germany, for example, public authorities are obliged to keep a file in which all the documentation produced as a result of a tender evaluation is retained. At the end of the bidding process, copies of that file are provided to all the tenderers. For the reasons apparent in this Judgment, I consider that that is an approach which has much to commend it. [Back]