![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
|
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Cooper & Anor v Thameside Construction Company Ltd [2016] EWHC 1248 (TCC) (27 May 2016) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2016/1248.html Cite as: [2016] EWHC 1248 (TCC) |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
| (1) Mr Marcus Cooper (2) Mrs Katie Amelia Cooper |
Claimants |
|
- and - |
||
Thameside Construction Company Ltd (in administration) |
Defendant |
____________________
Neil Moody QC and Andrew Miller QC (instructed by Kennedys Law LLP) for the Defendant
Hearing dates: 10th, 11th, 12th, 16th and 19th May 2016
____________________
Crown Copyright ©
Mrs Justice Carr:
A. Introduction
Thameside
Construction Company Limited ("
Thameside"),
its servants or agents.
Thameside
is a building contractor. Between 2005 and 2009
Thameside
carried out substantial works to the property, converting it into a single residence, refurbishing it and building substantial extensions to the rear and basement, pursuant to a JCT Contract on Intermediate IFC 98 Form (Revision 4) dated 3rd February 2005 between Mrs Cooper as "Employer" and
Thameside
as "Contractor" ("the JCT contract"). The allegations made against
Thameside
relate to the faulty installation of a Polyplumb straight connector ("the Polyplumb connector") onto plastic (polybutylene) piping which ran up to the tap box above the basin in an ensuite bathroom attached to a sixth bedroom on the second (top) floor of the property ("bedroom 6") ("bathroom 6"). The installation included the fitting of the piping into the Polyplumb connector. The piping was to be secured by the use of a grab ring located within the Polyplumb connector. It is said that the grab ring used within the Polyplumb connector was damaged or deformed from previous usage. Alternatively, the (lower) pipe was not inserted fully into the Polyplumb connector, such that the pipe was not secured by the grab ring. In any event, the installation of the pipework and the pipework itself was not reasonably fit for purpose. Nor was the installation carried out in a proper and workmanlike manner with reasonable skill and care. Nor was it installed with materials which were reasonably fit for purpose and of a satisfactory quality. The flood occurred when the pipe separated from the Polyplumb connector as a result of these alleged breaches. The property is not yet re-occupied and remains uninhabited.
Thameside,
namely Darenth (Southern) UK Limited and/or Darenth Southern (London) Limited and/or Frank Cosgrove trading as Darenth Southern (together "Darenth").
Thameside
is liable to indemnify Mr and Mrs Cooper for losses arising out of Darenth's activities at the property. Alternatively, the possibility is left (even if only faintly) open that it was another sub-contractor of
Thameside
that carried out this installation work and for which
Thameside
is responsible.
Thameside
now accepts that the Polyplumb connector was defective, alternatively that the pipe below it was not inserted properly. It also now accepts that the flood would not have occurred but for these defects. However, it denies liability. Its primary, indeed only defence now, albeit one raised for the first time by way of amendment almost a year after the commencement of proceedings, is that neither it, nor any of its servants or agents, installed the Polyplumb connector that failed. The Polyplumb connector was not installed as part of
Thameside's
work under the JCT contract and was not installed by anyone acting on behalf of
Thameside,
its servants or agents, including Darenth.
Thameside,
its servants or agents as part of the works under the JCT contract or was it installed by other contractors or sub-contractors outwith the contract and responsibility of
Thameside?
Thameside
has variously advanced other defences, including that the cause of the flood was wholly independent of the works undertaken by
Thameside,
its servants or agents. It was suggested that the pipework failed because of modifications to the domestic hot water system in about April/May 2009 and October 2010 undertaken on the instruction of Mr and Mrs Cooper and by third parties outside the JCT contract, namely the installation of a heat exchanger and/or the incorporation of a double check valve by Darenth. These were said to have caused pressure surges. It was also suggested that a plastic pipe was not suitable for use in a continuously operated re-circulating system. However, all these contentions have fallen away in the light of the defence experts' final conclusions.
a) For Mr and Mrs Cooper: Mr and Mrs Cooper; Peter Beer of Ottima (Specialist Joinery and Furniture) Limited ("Ottima") ("Mr Beer"); Jonathan Evans of Metropolitan Development Consultancy Limited ("MDC") ("Mr Evans"). A written statement from Mr Bachelard of Dr JH Burgoyne and Partners LLP ("Burgoynes"), was agreed;
b) ForThameside:
Frank Cosgrove of Darenth ("Mr Cosgrove"); Paul Johnson, a self-employed plumber contracted to Darenth ("Mr Johnson"); Paul McBryde, a carpenter who worked on the property for
Thameside
("Mr McBryde"); Glenn Gradwell, contracts manager and a former director of
Thameside
("Mr Gradwell"); Michael Lynch, construction site manger for
Thameside
at the property ("Mr Lynch").
a) For Mr and Mrs Cooper: Dr Simon Jones of Burgoynes. Dr Jones is a chartered mechanical engineer specialising in the investigation of incidents of mechanical failures;
b) ForThameside:
![]()
i) Mrs Daphne Wasserman of Cadogan International Limited ("Cadogans"). Mrs Wasserman is a chartered engineer;
ii) Mr Gerry Brannigan also of Cadogans. Mr Brannigan is a building services consulting engineer.
a) Section B: The JCT contract and duties owed byThameside;
b) Section C: The Polyplumb connector and the cause of the flood;
c) Section D: A general chronological overview of events;
d) Section E: The documentary evidence relating specifically to bathroom 6;
e) Section F: The burden of proof and the fact-finding exercise;
f) Section G: The witnesses;
g) Section H: The access hatch and panel;
h) Section I: Did Mr Johnson (or another Darenth plumber) install the Polyplumb connector?
i) Section J: Possible alternative explanations for the installation of the Polyplumb connector;
j) Section K: Possible adverse inferences;
k) Section L: The position of Ludek;
l) Section M: Conclusion.
B. The JCT contract and duties owed by
Thameside
"Intentions of the Parties
Contractor's obligations
1.1 The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in accordance with the Contract Documents identified in the Second recital and with the Health and Safety Plan…
3. Control of the Works
…
Sub-contracting
3.2 The Contractor shall not sub-contract any part of the Works other than in accordance with clause 3.3 without the written consent of the Architect/the Contract Administrator whose consent shall not be unreasonably delayed or withheld. The Contractor shall remain wholly responsible for carrying out and completing the Works in all respects in accordance with clause 1.1 notwithstanding the sub-contracting of any part of the Works.
Named Persons as sub-contractors
…
3.3.1 Where it is stated in the Specification/Schedules of Work/Contract Bills that work described therein for pricing by the Contractor is to be executed by a named person who is to be employed by the Contractor as a sub-contractor the Contractor shall not later than 21 days after entering into this Contract enter into a sub-contract with the named person using Section III of the Form of Tender and Agreement NAM/T referred to in the First recital…
3.3.7 Whether or not a person who has been named as a sub-contractor under any of clauses 3.3.1 to 3.3.5 is responsible to the Employer for exercising reasonable care and skill in:
- the design of the sub-contract works insofar as the sub-contract works have been or will be designed by the named person;
- the selection of the kinds of materials and goods for the sub-contract works insofar as such materials and goods have been or will be selected by the named person; or
- the satisfaction of any performance specification or requirement relating to the sub-contract works,
the Contractor shall not be responsible to the Employer under this Contract for anything to which the above terms relate, nor through the Contractor, shall the person so named or any other sub-contractor be so responsible; provided that this shall not be construed so as to affect the obligations of the Contractor or any sub-contractor in regard to the supply of goods and materials and workmanship.
The provision of this clause 3.3.7 shall apply notwithstanding that the Sub-Contract Sum stated in article 2 of Section III of the Tender and Agreement NAM/T referred to in clause 3.3.1 or 3.3.2 included for the supply of any design, selection or satisfaction as referred to herein, and that such Sub-Contract Sum is included for within the Contract Sum or the Contract Sum as finally adjusted.
…
3.3.9 Save as otherwise expressed in the Conditions the Contractor shall remain wholly responsible for carrying out and completing the Works in all respects in accordance with clause 1.1 notwithstanding the naming of a sub-contractor for the execution of work described in the Specification/Schedules of Work/Contract Bills.
…
Work not forming part of the Contract
3.11 Where the Contract Documents provide for work not forming part of this Contract to be carried out by the Employer or by persons employed or engaged by the Employer, the Contractor shall permit the execution of such work on the site of the Works concurrent with his execution of the Contract Works. Where the Contract Documents do not so provide the Employer may nevertheless with the consent of the Contractor (which consent shall not be unreasonably delayed or withheld) arrange for the execution of such work.
Every person so employed or engaged shall for the purposes of clauses 6.1 [injury and damage] and 6.3 [insurance of the Works] be deemed to be a person for whom the Employer is responsible and not a sub-contractor.
6. Injury, damage and insurance
Injury to persons and property and indemnity to Employer
…
6.1.2 The Contractor shall be liable for, and shall indemnify the Employer against, any expense, liability, loss, claim or proceedings in respect of any loss, injury or damage whatsoever to any property real or personal in so far as such loss, injury or damage arises out of or in the course of or by reason of the carrying out of the Works and to the extent that the same is due to any negligence, breach of statutory duty, omission or default of the Contractor, his servants or agents or of any person employed or engaged upon or in connection with the Works or any part thereof, his servants or agents or of any person who may properly be on the site upon or in connection with the Works or any part thereof, his servants or agents…"
a) That the materials used in the Works would be reasonably fit for the purpose for which they were required in the works (section 4 (5) of the Supply of Goods and Services Act 1982 ("the Act"));
b) That the materials used would be of satisfactory quality (section 4(2) of the Act); and
c) That the works would be carried out with reasonable care and skill (section 13 of the Act).
Thameside
owed a duty of care in tort to both Mr and Mrs Cooper in carrying out the Works to like effect.
Thameside
owed a statutory duty to Mrs Cooper, pursuant to section 1 of the Defective Premises Act 1972, to see that the works it undertook were done in a workmanlike and professional manner with proper materials. The existence of any duty under this Act is not admitted by
Thameside,
but if there was such a duty,
Thameside
contends that it was limited to an obligation to ensure that the work was undertaken in a workmanlike and professional manner and with proper materials for the purpose of ensuring that the property was fit for occupation when completed. In the event, the allegation adds nothing to the outcome on the merits, and I do not address it further.
C. The Polyplumb connector and the cause of the flood
Thameside
accepts, if the Polyplumb connector was installed by it, its servants or agents,
Thameside
is liable in law both for breach of the express and implied terms of the JCT contract and in negligence.
D A general chronological overview of events
Thameside
agreed a "Priced Contract Schedule of works" for the second phase of works. Then, as already indicated, Mrs Cooper entered into the JCT contract on 3rd February 2005. Sheldon Andrews (later The Sheldon Studio Limited) (together "Sheldon") was appointed separately as interior designer.
a) the installation of the pipework necessary to deliver hot and cold water to the taps for the basin in bathroom 6 was included under the JCT contract;
b)Thameside
sub-contracted its mechanical and electrical and plumbing obligations under the JCT contract to Darenth;
c) Darenth was not a "nominated" sub-contractor.
a) Specialist joinery and furniture works were made the subject of a separate direct contract between Mr and Mrs Cooper and Ottima. Mr Beer was Ottima's owner and managing director. Ottima supplied the vanity unit above the basin in bathroom 6;
b) Specialist stoneworks were taken out of the JCT contract and made the subject of a separate contract between Signature Stone Limited ("Signature") and the Coopers either direct or via Ottima. Mr Jose Nona Balola ("Mr Balola") was a director of Signature from June 2005 to December 2011. It appears that Signature entered into creditors' voluntary liquidation in June 2012 and was dissolved in December 2013. Signature supplied the basin, and the stone for the wall below and around the basin in bathroom 6.
Thameside
in any way when acting in this arrangement with Ottima.
Thameside's
servant or agent, as set out and addressed in more detail in section L below. There is no suggestion that Ludek was ever engaged by
Thameside
to carry out plumbing works at the property. Ludek's quotation in July 2008 expressly excluded plumbing works. However, it appears that Ludek had the capacity to provide plumbing services. Thus in April 2011 Ludek was providing plumbing services (post-flood) at the property and also at the rental address where the Cooper family was then living.
Thameside
and Darenth. Darenth was simply paid on the basis of monthly valuations.
"Practical completion, as such, took place in January 2009. There is no certificate."
Thameside
originally contended that it was the installation of the heat exchanger and check valve that had caused the flood, because it would have led to significant pressure fluctuations in a closed system. However,
Thameside's
experts now agree that, given the presence of a pressure relief valve on the heat exchanger set at 7 bar, any pressure increase would have been limited to approximately 2 bar (from 5 bar to the maximum 7 bar). The effect of this is that the pressure within the system would have fluctuated between 4 and 7 bar. A properly made joint would not have failed in the event of such relatively small fluctuations in pressure. The redesign cannot therefore be said to be the cause of the flood. However, it may (and in my judgment does) explain the timing for the flood, in the sense that even small temperature related pressure increases could lead to the joint separating.
Thameside
and then his emergency plumber, Mr Mark Hebden. Mr Hebden was the only person he was able to speak to. Mr Cooper tried to find the cause of the leak and tried himself to stem the water with his hands. He tried to find the mains water tap. He put buckets around and took his family to safety, fearing an electrical accident.
Thameside
at around 7pm and asked to attend a problem in one of the top floor bathrooms. He arrived at about 7.20pm, was met by Mr Cooper, and headed straight to the top floor. He found the failed joint, pushed the pipe back in, went downstairs and turned the water off at the pump set. He called a plumbing contractor and a cleaning company, both of which arrived at around 8pm. Mr Cooper had also called a plumber. The two plumbers who arrived made sure that a new joint was installed and turned the water back on. In his evidence, Mr McBryde confirmed that the plumber whom he called and who subsequently arrived was Mr Johnson. Mr Cooper did not remember meeting Mr McBryde. Mr Hebden was not called to give evidence. But on 7th December 2010 he wrote a document stating that he was called at around 8.15pm on the evening of the flood, arriving at around 9pm. He found a burst pipe in bedroom 6. He temporarily rejoined the pipe and turned the hot water supply off in the basement plant room. There was no obvious damage to the fittings or pipe but as a precaution he replaced the joint. Mr Johnson's evidence is consistent with that of Mr McBryde. Mr Johnson states that he arrived at the property at around 8 to 8.30pm, at about the same time as another plumber, Mr Hebden. Mr McBryde told Mr Johnson that he had switched the water off. Mr Johnson went up to bathroom 6 with Mr Hebden (and an apprentice of Mr Hebden). When he got there, there was no water gushing out and the pipe beneath the basin was in its fitting. He turned the water back on and returned to bathroom 6 where there was no leaking. Mr Cooper wanted the fitting changed, so after switching off the water again, Mr Johnson installed a new HEP20 fitting in the presence of Mr Hebden who was observing. Either he or Mr Hebden provided the new fitting.
Thameside
emailed Mr Cosgrove stating that Mr Johnson had repaired the failed joint and taken it away. It needed to be returned immediately. Mr Cosgrove responded on the same day to say that Mr Johnson had left the body of the fitting on site. Mr Johnson had not been able to get the clip rings off the pipe so he pushed the rings and their respective threaded nuts further up the pipe so that he could get another fitting in place. The new fitting had been supplied by Mr Cooper's plumber.
Thameside
(or anyone else) at the time or immediately after the flood that Darenth had not installed the failed joint. It is suggested that this is "nothing short of astounding", if it was true that Darenth had not installed the failed joint. I return to this below.
Thameside,
although he was working on another project for Darenth with
Thameside;
he had been working for Darenth, not
Thameside
at the property.
Thameside
this directly, even though Darenth was working for
Thameside
on another project. Burgoynes were on site investigating. He assumed that all matters had been discussed and that
Thameside
was fully aware of the true position. He simply informed his insurance brokers of the incident and was told not to make any statements about the incident and to forward all future correspondence to them. He could not understand how
Thameside
came to make the admissions that it did.
Thameside's
insurers were notified on 2nd December 2010 of a potential claim. By 21st December 2010
Thameside's
insurers had instructed loss adjusters, Cunningham Lindsey Constructions ("Cunninghams"). As at March 2011 Cunninghams' position was that the works effected by Darenth were likely to have included installation of the failed joint. In July 2011 Cunninghams admitted that the design and installation of the failed joint was undertaken by a mechanical sub-contractor to
Thameside,
and "to the best of their knowledge and belief" by Darenth.
Thameside
served a defence in September 2014. It expressly admitted that the Polyplumb connector had been installed in bathroom 6 by Darenth. However, on 6th March 2015
Thameside
successfully sought permission to amend its defence so as to withdraw that admission and to deny that Darenth had carried out the relevant work.
Thameside
directly for an account of events. Nor was he ever approached by any loss adjuster. The first time he was approached and interviewed (and then by
Thameside's
solicitors) was November and December 2014. The first time that Mr Cosgrove was so interviewed was in December 2014.
E. The documentary evidence relating specifically to bathroom 6
Thameside
enclosing a priced sanitary specification with added anticipated costs for installation. For bathroom 6 (and bathroom 5) the specification referred to a "wall mounted basin mixer".
Thameside
as follows:
"...As there has been little progress on site over the past few months I am therefore detailing services information that is still outstanding and which must be confirmed before any real progress can be achieved:
1. O[t]tima are now fitting finished furniture in Bathrooms but to-date there is no sanitary/brassware schedule. Although all of our services are in position in partitions, final fix of the ply cladding cannot occur until the carcassing of the brassware is complete. In most cases this means the rear of the diverters/taps must be in position and wastes positioned exactly to accept the sanitary ware…."
Thameside
wrote to MDC, following receipt of the revised sanitary schedule from Sheldon, enclosing a detailed costed supply and installation summary of items, as prepared by Darenth. In relation to bathroom 6 (and bathroom 5), reference was made for the first time to a "deck mounted monoblock mixer tap". This appears to have emanated from Sheldon's schedule, which referred to "deck mounted" as opposed to "wall mounted" tap for the first time. On the same day Mr Cosgrove wrote to
Thameside
enclosing a schedule based on the same revised sanitary specification.
Thameside
wrote to MDC stating that it understood that Darenth had requested elevational drawings of each of the bathrooms to enable the correct positioning of the various appliances, and particularly the control brassware that would be hidden behind various panelling. Installation works would be unable to commence before this information was issued.
Thameside
as follows with a progress report:
"Bathrooms 5 & 6, Vanity's [sic] made fitted, removed and brought back to workshop. Now being redesigned. Waiting for sanitary ware and plumbing before stone can be fitted. Vanity being repriced along with solid stone basin. Existing ones to be save[d] to see what can be reused..."
"Bathroom 6 mark 2 Smaller unit to be drawn and costed. The unit will also need steel support arms for the sink to be made."
"Further to our telephone conversation yesterday I have now fully investigated the sanitary ware schedule ordered from Wash with the Bathroom drawings issued on 26th January 2007 for the three second floor shower rooms …
En suite Bathroom 6
…Basin
Gessi Retangolo deck mounted monoblock mixer tap chrome 20001
The Ottima drawing details a chrome wall mounted tap discharging into the bespoke basin. Should the tap be chrome 20085? There is no waste specified and we assume this will be supplied with the bespoke basin…."
(Chrome 20085 taps were wall mounted. Chrome 20001 were deck mounted). The same comment was made for bathroom 5.
Thameside's
case is that by the end of March 2007, the first fix plumbing works were complete. Mr Johnson went on holiday for some 6 weeks or so on 2nd April 2007, his entry abroad being recorded in his passport.
Thameside)
wrote to MDC as follows:
"1. Set out and size of wall slot required to shower rooms 5 & 6 to receive cabinet and basins.Thameside
… to remove ply fitted by Ottima and prepare opening accordingly…"
Thameside
produced a revised list of tasks including:
"Showerrooms 5 & 6 units & stone 10 days start Tuesday 010507 finish mon 140507"
Thameside
recorded the tiler being on site and asked who was co-ordinating the works. On the same day MDC emailed
Thameside
as follows:
"Ottima have programmed to be onsite on Tuesday 24th April at which time they will be getting on with all ensuite bathrooms…
Ottima are supposed to be co-ordinating with Signature... and Darren [of Sheldon]."
Thameside
recording that the majority of the sanitary ware had now been "piped up, located and in the case of brassware the final fix removed and stored". In relation to bathrooms 5 and 6, the towel rails could not be located as positioned and had been relocated between the Ottima cabinet and the shower. This involved the re-routing of radiator feeds to new positions.
"1.52 Ottima and Signature Stone to start bathroom 5 and 6 this week. Outstanding."
Thameside
in relation to bathroom 6 recording that the following works had been carried out:
"… Extend cables to heated mirror pad now that Ottima basin is installed."
Thameside
emailed confirmation of "verbal" site instructions for second fix plumbing as follows:
"… To second fix bedrooms and ensuites 4, 5 & 6 electrically, with white plates to the power. Light fittings as approved. Protect the stone in 5 & 6, have the sloped soffits plastered and fit the sanitaryware, taps and shower fittings."
Thameside
denies this. The photograph does not show a hatch. But because of the angle from which the photograph was taken, it is possible that it would not appear, even if it was there. I address this dispute in more detail in section H below.
Thameside
dated 9th August 2007) as being on site.
"Bedroom 6 Ensuite
… 1.35 Supply and fix stone below basin. Ottima"
(with an identical entry for bathroom 5).
Thameside)
emailed MDC to complain about non-attendance by Ottima or Signature – with no more than 5 days' attendance over the previous 10 weeks.
"Bedroom 6 ensuite
1.01 Supply stone access panel and fix on ply access board fixed on magnets and pull catches below basin and mastic in place. Outstanding Signature Stone/Ottima"
with an identical entry for bathroom 5.
Thameside
as follows:
"Can you please organise for the following bits to be completed as soon as possible on the second and first floor so that Ottima and Jose can get the top floor finished and continue with the first:
The ply access panels under the basins in en suites to bedrooms 5 and 6 need fixing properly so Jose can fix the stone to it…"
"…This has been going on from before Christmas… The holes Signature… have drilled are not only too large but slightly egg shaped. Signature… have tried to recess the outer rim of the waste to be flush with the stone which has not been sufficiently accurate as they have tried to carry out the work on site instead of drilling the stone on a jig."
"... Supply stone access panel and fix with a mastic joint – Signature Stone/Ottima"
"2nd Floor Bathrooms – all stonework completed except for architraves Awaiting basin waste detail. JB [Signature] agreed to remake the basins. Shower screen and mirror trim details required. Vanity units to be returned to site by 14th July 2008."
"Access for Maintenance. [Mr Beer] and [Mr Balola] requested details of the bath access panels and [MDC/Sheldon Studios] to sort out. [Mrs Cooper] advised that all areas had to be readily accessible and she did not want to be breaking out stone etc so that ordinary maintenance could be carried out. [MDC/Sheldon Studios] to take this on board and this will require alterations to areas elsewhere where the practical side of things has been totally forsaken for design. URGENT – 7 DAYS"
"… 1.38 JB [Signature] to either source new waste for approval by DG that fits the holes already in the basins or he is to change the basin bases and recut the holes to suit the waste on site."
"2nd Floor Bathrooms – all stonework completed except for architraves. Awaiting basin waste detail. JB [Signature] agreed to remake the basins and will be delivered this week. Shower screen and mirror trim details required. Vanity units not yet returned to site. Will mostly be dealt with within LT [Ludek] contract period. Shower trays to be broken out and replaced with Dallmer styled outlets with removable tops so that proper access can be afforded…"
"32. The ensuites to bedrooms 4, 5 and 6 can now be completed and should be as soon as possible. Mastic contractor to be appointed by Darren – Ludek to advise when the rooms will be ready for him. OUTSTANDING Ludek/Signature.../Ottima/DG [Sheldon]"
F. The burden of proof and the fact-finding exercise
Thameside
or one of
Thameside's
sub-contractors carrying out works under the JCT contract. For the claim to succeed it does not have to be proved why or when the Polyplumb connector was so installed, though of course issues of rationale and timing may be relevant to the question of who it was that carried out the installation. Equally,
Thameside
does not have to prove that some other party installed the Polyplumb connector. But if there is no possible alternative other than that Mr Johnson or someone else at Darenth or otherwise engaged by
Thameside
could have installed the Polyplumb connector, then that will clearly be relevant to the question of liability.
"In approaching this question it is important that two matters should be borne constantly in mind. The first matter is that the burden of proving, on a balance of probabilities, that the ship was lost by perils of the sea, is and remains throughout on the shipowners. Although it is open to underwriters to suggest and seek to prove some other cause of loss, against which the ship was not insured, there is no obligation on them to do so. Moreover, if they chose to do so, there is no obligation on them to prove, even on a balance of probabilities, the truth of their alternative case."
"The second matter is that it is always open to a court, even after the kind of prolonged inquiry with a mass of expert evidence which took place in this case, to conclude, at the end of the day, that the proximate cause of the ship's loss, even on a balance of probabilities, remains in doubt, with the consequence that the shipowners have failed to discharge the burden of proof which lay upon them."
a) A judge is not bound always to make a finding one way or the other. This is a point "of great importance". The unsatisfactory state of the evidence may make this the only just course for him to take;
b) The dictum can only apply when all relevant facts are known, so that all possible explanations, except a single extremely improbable one, can properly be eliminated;
c) The legal concept of proof of a case on a balance of probabilities must be applied with common sense. If a judge concludes on a whole series of cogent grounds that the occurrence of an event is extremely improbable, a finding by him that it is nevertheless is more likely to have occurred than not, does not accord with common sense.
"64. It is not an uncommon feature of litigation that several possible causes are suggested for the mishap which the court is investigating. If the court is able, for good reason, to dismiss causes A, B and C, it may be able to reach the conclusion that D was the effective cause. But the mere elimination of A, B and C is not of itself sufficient. The court must also stand back and, looking at all the evidence, consider whether on the balance of probabilities D is proved to be the case. See Nulty v Milton Keynes Borough Council [2013] EWCA Civ 15 at [34] per Toulson LJ and Graves v Brouwer [2015] EWCA Civ 595 at [24] to [30]".
"34. A case based on circumstantial evidence depends for its cogency on the combination of relevant circumstances and the likelihood or unlikelihood of coincidence. A party advancing it argues that the circumstances can only or most probably be accounted for by the explanation which it suggests. Consideration of such a case necessarily involves looking at the whole picture, including what gaps there are in the evidence, whether the individual factors relied upon are in themselves properly established, what factors may point away from the suggested explanation and what other explanation might fit the circumstances. As Lord Mance observed in Datec Electronics Holdings Limited v UPS Limited [2007] UKHL 23, [2007] 1 WLR 1325, at 48 and 50, there is an inherent risk that a systematic consideration of the possibilities could become a process of elimination "leading to no more than a conclusion regarding the least unlikely cause of loss", which was the fault identified in The Popi M. So, at the end of any such systematic analysis, the court has to stand back and ask itself the ultimate question whether it is satisfied that the suggested explanation is more likely than not to be true. The elimination of other possibilities as more implausible may well lead to that conclusion, but that will be a conclusion of fact: there is no rule of law that it must do so. I do not read any of the statements in any of the other authorities to which we were referred as intending to suggest otherwise."
a) The court is entitled to engage in a systematic analysis of competing theories and eliminate one in favour of the other;
b) That, in itself, may lead to the conclusion that the preferred theory is more likely than not to be true; but
c) The court must always then stand back and ask itself the ultimate question as to whether or not the preferred explanation is more likely than not to be true.
Thameside/Darenth
has been discharged. Nothing by way of alternative competing theory or evidence is sufficiently plausible to displace that conclusion.
a) Mr Balola of Signature;
b) Mr Tucny of Ludek.
Thameside
invites me to draw adverse inferences from the failure to call these witnesses on the part of Mr and Mrs Cooper, a submission that I address in section K below. Leaving that to one side, the position is that there are many evidential lacunae. The result has been much speculation; theories have been mooted and abandoned during the course of the trial; new theories have been advanced for the first time in the very closing stages of trial.
G. The witnesses
Thameside.
He had no recollection of any access panel below the basin being made. Ludek would have installed the catches for the access panel with a cordless screwdriver. His evidence was that Ottima did not touch the plumbing at all. Darenth was the only plumber on site. He used Ludek to install Ottima's joinery at the property and confirmed that it was Ludek that installed and removed the basin as it went in and out the first time. I have addressed or will address specific further aspects of his evidence either above or below in the context of the particular issues arising.
a) He readily accepted his original errors and explained that he identified them once he was shown the relevant documentation. I found his explanations for his errors to be genuine and that the making of the errors was not such as to undermine fundamentally his reliability for all purposes. The events in question took place a long time ago. He does not appear to have been shown much, if any, of the relevant contemporaneous documentation to assist him with dates and detail at the time of his first statement, or to have understood the importance or relevance of certain issues. Thus I accept his evidence that he did not understand the importance of sequencing at the time of his original statement;
b) It was he who, shortly before trial, found – by chance – his 2006 diary and his passport showing his movements in 2007. He quite rightly volunteered them up;
c) He made fair concessions without hesitation, for example as to the effect of the facing wall on access to the pipework; on the difficulties of using a spanner in the space available; that the facing wall with its tiling prevented any access to the pipework under the basin. He confirmed that he had never seen the facing wall demolished and had never seen any operatives of Ludek carrying out any plumbing work on site. He made fair concessions in relation to paragraph 11 of his first witness statement, conceding that Darenth had used Polyplumb fittings on some of the waste and soil pipes, which formed part of the plumbing on the project, although he was able to maintain that only HEP20 fittings were used by Darenth on pressurised delivery pipework.
Thameside's
contracts manager on the project at the property and one of
Thameside's
three directors during the project. He was hesitant at first in the witness box. He was uneasy with the question of Ludek's position as finishing contractor: having stated in bald terms in his second witness statement that Ludek as finishing contractor was never engaged by
Thameside
as a subcontractor, in oral evidence his position was more subtle. He believed that there was a subcontract entered into between
Thameside
and Ludek, but only as a mechanism to reduce VAT. Ludek was not a subcontractor in the sense of ever having been under the control or supervision of
Thameside.
"I cannot remember precisely when, but I do recall that on one particular day, post June 2007, during one of my walks around the site, I noticed that stone below the basin in ensuite 6, had been taken off. I also noted that the wash basin remained in place.
The reason why I noticed the hacked off stone was because I was concerned that there could be damage to other fittings and fixtures in the ensuite and thatThameside
would be blamed for any such damage and have to make good the damage.
I specifically remember speaking to someone at Signature Stone informing them that if they were carrying out works and taking off the stone that they should ensure that they protected the wash basin. I was told by the Signature Stone representative that there was no need to worry about damaging the wash basin while removing the stone because the basin was going to be changed. I did not need to take this matter further as such works were not withinThameside's
ambit."
Thameside.
He was foreman/assistant site manager in 2007. He had no recollection of any works for an access hatch under the basin in bathroom 6. He then left the project and returned again. He was in charge of snagging. As already indicated above, he attended the property at the time of the flood. He described how he switched the water off at the pumpset, something which he as a tradesman knew would stop the water.
Thameside
(when Mr McBryde was not there) from the beginning of 2008. He had no recollection of
Thameside
being involved in the decision to install an access panel below the basin in bathroom 6, or of seeing the access panel itself. He did not recall
Thameside
or its subcontractors being involved in its construction (or the making of an access hatch). Once a particular room was completed it was handed over by
Thameside
to prevent any damage during finishing and furnishing works, although he would still have had access as site manager.
Thameside
worked from the top of the house down. He stated that he never saw Ludek carrying out plumbing works on site, but they were quite capable of doing so, and worked different hours to
Thameside
– weekends and late evenings.
Thameside
had no control over Ludek. They worked as they wanted and independently. He had no recollection of any flood at the property prior to 18th November 2010.
H. The access hatch and panel
Thameside,
of damage to the pipework. If the hatch did exist before then, then there was no need for any stone removal works thereafter.
a) Not a single drawing for bathroom 5 or 6 shows an access hatch or panel below the basin. An access panel was shown in the vanity units. Without an express instruction before 3rd July 2007, of which there is no evidence at all, the hatch and panel would not have been created by then;
b) The first document to mention the need to fix stone below the basin in bathroom 6 is dated 15th July 2007 (some 6 days after Signature was on site on 9th July 2007). Express reference to an access panel below the basin in bathroom 6 is first made on 21st August 2007;
c) This is consistent with the question of access for maintenance generally at the property being something of an afterthought, perhaps triggered here by someone seeing the fully tiled stonework right up to the basin in bathroom 6 in early July 2007. The minutes of a site progress meeting on 1st July 2008 record that design had been prioritised over practicality/access for maintenance;
d) Mr Cosgrove's evidence, which I accept on this issue, is that he was never aware of an access hatch or panel below the basin in bathroom 6;
e) Mr Johnson was very clear that there was no hole below the basin when he carried out the second fix. The wall was stone clad up to the basin – a finished wall. I accept his firm evidence on this issue;
f) In particular, Mr Johnson's unchallenged recollection of the second fix is important in this context. He stated that as part of the second fix he placed a chrome flange over a horizontal (first fix) pipe and placed it up against the tiling. The flange, which can be seen on photographs, allows for any discrepancy in the cutting and fixing of the tiles around the chrome pipe. He would not have been able to do this if there had been an open hatch without an access panel in place. This would be a remarkable embellishment of recollection if it were not true. I accept his evidence on this issue.
I. Did Mr Johnson (or another Darenth plumber) probably install the Polyplumb connector?
a) Did Mr Johnson do the plumbing to the basin in bathroom 6?
b) If so, did he install the Polyplumb connector?
c) If not, did another Darenth plumber do the plumbing in bathroom 6?
d) If so, did that other plumber install the Polyplumb connector?
Did Mr Johnson do the plumbing to the basin in bathroom 6?
a) That the letter shows that both horizontal and vertical pipes had been laid by 13th November 2006;
b) By reference to Mr Johnson's 2006 diary, that Mr Johnson could not have carried out the laying of the horizontal or vertical pipes.
Thameside's
letter of 15th December 2006 to MDC confirms that installation works could not commence without elevational drawings setting out the correct positioning, including control brassware. Mr Beer's letter of 10th January 2007 also confirms that the vertical pipes were yet to be installed. The reference to "plumbing before stone can be fitted" in Mr Beer's letter of 10th January 2007 also confirms that vertical pipes had yet to be fixed as at that date. Mr Cosgrove's letter of 23rd April 2007 refers to the majority of the sanitary was having been "piped up" at that stage.
"Nobody else put in the horizontal piping. I put it in."
"It's not something that takes a long time, it's just a pain drilling it all, but to pull the pipe through from one end of a bathroom is…..you know, it's not a difficult job."
Thameside's
letter of 4th April 2007) would not have posed any impediment to him doing the vertical piping before 2nd April 2007. Mr Cosgrove's letter of 23rd April 2007 confirmed that by that date the majority of the sanitary ware had "been piped up". It is right that other plumbing works were being done in bathroom 6 when Mr Johnson was away. But none of them appear to have related to the plumbing under the basin. Nor is there any suggestion that Mr Johnson, the foreman plumber, was told on his return from holiday that his plumbing works had been touched or altered in any way, which might have been expected, had it happened.
If it was Mr Johnson, did he install the Polyplumb connector?
a) He was working on a bare stud wall with no fixtures or fittings in place;
b) All he had to do was connect a length of pipe between the T-joint and join a piece of pipe long enough to reach the tap box connections. He used a single length of pipe for each of the hot and cold water supplies;
c) There was simply no reason for him to make the length of pipe shorter. Connecting two different lengths of pipe would not only result in additional work and materials but would not be good practice;
d) If for some reason he had misjudged the length of pipe needed, he would simply have discarded those lengths of pipe and cut another piece. He would not have pieced together two small pieces of pipe with a joint connection and then repeated the same for the other piece of pipe. Such small pieces of piping are not used and are always thrown in the skip. There was no shortage of pipe material on site as it was drawn from a large 50m coil.
a) This was a very poor piece of plumbing work indeed on a project which Mr Johnson knew was to be of the highest quality and standard. There was no sensible plumbing reason for the use of connectors, let alone the use of a second hand fitting. In opening, it was described for Mr and Mrs Cooper as "a piece of unbelievably shoddy plumbing". Yet Mr Johnson is and was a highly competent and experienced plumber. Mr Evans was clear that there were no problems with or complaints about Darenth's work on the project.Thameside
has continued to use Darenth on other projects. It is very difficult to associate Mr Johnson (or any other Darenth plumber) with such a piece of work. He is also accepted on all side as being an honest man. If he had made such a mistake, my assessment is that he would simply have admitted it;
b) No credible reason has been identified for Mr Johnson (or any other Darenth employee) to cut lengths of pipe that were too short, necessitating the use of connectors. The theory advanced has been that there was uncertainty as to whether or not the taps were to be deck mounted or wall mounted. Mr Beer recalled no discussion at any stage of deck mounted taps. From his point of view, the taps were always to be wall mounted. Mr Johnson, the relevant individual on my findings, at no time thought that the basin in bathroom 6 was to have deck mounted taps. This was clear to him from the drawings, and also from the size and configuration of the bathroom, which was small and very narrow. The designers made a mistake at one stage, but Mr Cosgrove picked that up and obtained clarification that it was indeed a mistake. Even if there was a period when Mr Cosgrove had to query the position on 1st February 2007, there was only a short period of uncertainty. And even if he had a doubt, he never positively believed that deck mounted taps would be used. The incorrect fittings were returned not used, as Mr Evans confirmed;
c) Even if the pipes were cut too short, Mr Johnson appeared genuinely unable to understand why the solution would be to insert straight connectors. He would just have started again to cut longer lengths of pipe, cheaply and readily available. He was working on an open stud wall. I am not persuaded that anything in Darenth's financial history undermines the evidence of both Mr Johnson and Mr Cosgrove that there was never any shortage of piping materials. Mr Cosgrove was clear that was never any shortage. Nothing in his conduct on the project in early 2007 suggested that he (or Darenth) was in turmoil: rather the contrary, his correspondence at that time appears careful, detailed and prompt;
d) The fact that the faulty joint was a Polyplumb connector, not a HEP20 connector, suggests that the work was not that of Darenth. Whilst both Mr Cosgrove and Mr Johnson were incorrect in saying that Darenth did not use Polyplumb products anywhere on site, there is no evidence to suggest that they were wrong in maintaining that none of Darenth's work on the pressurised hot and cold water installation system involved Polyplumb products, let alone second-hand Polyplumb products.
Thameside
on the night of the flood or in the immediate aftermath that he was responsible for installing the Polyplumb connector, Mr Johnson's evidence was that that was not his focus at the time. He did not give any thought to it. He just focused on dealing with the plumbing in what was a very stressful environment. He had been working all day and been called out at night from home in Surrey. It is not clear on the evidence whether he realised on the night that a rogue joint had been involved. In any event, Mr Johnson was clear that in the immediate aftermath he told Mr Cosgrove upon his return from holiday that the joints in the pipes were "rogue". He said then that matters went "oddly quiet". Mr Cosgrove confirmed that Mr Johnson had told him that the Polyplumb connector had not been installed by him.
a) they were not being approached byThameside
(or anyone else), to provide any information or answer questions in relation to the incident;
b) Mr Johnson had told Mr Cosgrove, for whom he had been working at the time, that he had not installed the Polyplumb connector;
c) Mr Cosgrove had informed his insurance brokers of the incident and was told not to make any statements in respect of the incident,
Thameside's
insurers/loss adjusters that Darenth was responsible for the installation of the Polyplumb connector, they may be seen as understandable in the sense that Darenth was the sole sub-contractor responsible for the plumbing works on the project. But they appear to have been made on the basis of assumption alone and without resort to Mr Johnson (or Mr Cosgrove).
Thameside's
fault.
J. Possible alternative explanations for the installation of the Polyplumb connector
"Definitely not. The debris and the way the stone was smashed with a hammer…"
Thameside
since he left the company.
a) The fact that he stated unequivocally in his second statement that Ludek was never engaged byThameside
as a sub-contractor. As appears in section L below, in fact, as Mr Gradwell accepted, the position is more nuanced than that. Two points can be made: i) this issue has nothing to do with seeing the demolition of the wall in bathroom 6 and ii) the statement was made the day before his oral evidence in response to the late positive case mounted for Mr and Mrs Cooper that Ludek as finishing contractor was
Thameside's
subcontractor. Although Mr Gradwell did of course sign and verify the statement, it smacks of being drafted over-enthusiastically by lawyers and in a rush during trial without full consideration of the relevant documents. When Mr Gradwell was taken to those documents, he readily explained the subtler position that there was a sub-contract between
Thameside
and Ludek in around July 2008, but it was only a mechanism;
b) The fact that he incorrectly suggested thatThameside
was denied access to the property from the end of 2007 through 2008. Mr Lynch said that as site manager, he did have access if he needed it. This point again does not strike at the heart of the matter: it is clear that there was handover of rooms as they were completed by
Thameside
to Ludek or for snagging purposes;
c) The fact that he allegedly downplayed his position withinThameside
as director. I do not consider this to be a fair criticism. It was clear from Mr Gradwell that he did not consider himself a main player in
Thameside.
He was a director, but his role was really that of contracts manager. He held only 5 out of 100 shares in
Thameside.
Nor am I impressed by the criticism of his failure to mention what he saw in bathroom 6 to
Thameside's
insurers. I accept that his evidence that he was not involved in the arguments being advanced on behalf of
Thameside.
Mr Harris was dealing with that side of things. Mr Gradwell's role was just to carry on with
Thameside's
projects.
a) The lack of documentary record of any instruction to demolish the wall. But if it was a necessary part of creating the hatch, this absence is not so telling. And the documentation before me appears incomplete;
b) The lack of any evidence of a claim for payment for such work. As already indicated, it is not clear precisely what was charged for and when, but in any event the absence of a claim for repair works at least is consistent with damage being caused through someone's fault (and so not claimed for). And again I am not convinced that all the documentation is available;
c) The fact that no other witness than Mr Gradwell saw the wall down. This is not surprising. The bathroom was a small room at the top of the property;
d) The lack of any evidence of a flood taking place. All the witnesses have been clear that they were never aware of a flood as such. But i) the system may not have been energised ii) even if it was, the entire system could have been isolated by use of the pump set, or the second floor system could have been isolated by use of the individual clearly labelled isolation valves in the plant room described by Mr Cosgrove. This could have been done before the works were carried out, or immediately upon the damage being caused. The damage would have occurred in the presence of at least one tradesman who could also have taken steps to clear up and minimise any flooding;
e) The fact that two pipes were compromised. This merely suggests that both pipes may have been cut to move them or damaged;
f) The fact that Signature was not a plumber. This does not rule out the possibility of Signature installing the Polyplumb connector: the job was relatively simple. The fact that it was done so incompetently suggests in any event that it was not carried out by a professional plumber. Additionally, it appears that Signature and Ludek worked closely together. If there was some sort of incident, Ludek may have helped Signature out;
g) The fact that there is no evidence of anyone seeing the wall down in bathroom 5. This is correct. The focus of the trial and evidence has been very much on bathroom 6. But the wall in bathroom 5 may have been taken down after Mr Gradwell saw the wall down in bathroom 6.
Thameside
on this: but, fairly read, I do not think that paragraph 9I.5 of the Re-Amended Defence does more than deny access within bathroom 6 with the facing wall in place.) But there has been no evidence as to the state of the wall in bedroom 4. On the evidence before me, if this third scenario is a possibility at all, it is a very faint one.
K. Possible adverse inferences
"(1) In certain circumstances a court may be entitled to draw adverse inferences from the absence or silence of a witness who might be expected to have material evidence to give on an issue in an action;
(2) If a Court is willing to draw such inferences, they may go to strengthen the evidence adduced on that issue by the other party or to weaken the evidence, if any, adduced by the party who might reasonably have been expected to call the witness;
(3) There must, however, have been some evidence, however weak, adduced by the former on the matter in question before the court is entitled to draw the desired inference: in other words, there must be a case to answer on that issue;
(4) If the reason for the witness' absence or silence satisfies the court, then no such adverse inference may be drawn. If, on the other hand, there is some credible explanation given, even if it is not wholly satisfactory, the potentially detrimental effect of his/her absence or silence may be reduced or nullified".
Thameside
invites me to draw the inference that Messrs Balola and Tucny would have given evidence adverse to the claim. There was clearly a case to be answered by reference to the works of Signature and Ludek. No evidence was adduced as to why they were not called as witnesses.
L. The position of Ludek
Thameside.
It would only be relevant had I found that the Polyplumb connector was installed by Ludek after July 2008, which I have not. No positive case was pleaded on behalf of the Coopers to the effect that Ludek was a sub-contractor of
Thameside,
although it was not expressly admitted that Ludek was not a sub-contractor of
Thameside.
However, it became clear during the course of oral openings at least that it was being submitted for Mr and Mrs Cooper that Ludek, when appointed as finishing contractor in 2008, was a sub-contractor for
Thameside.
Thameside
contract". He said this because he believed that
Thameside
had paid Ludek. Mr Beer's evidence was that Ludek was contracted either to
Thameside
or Mr Cooper direct for the purpose of acting as finishing contractor. Mr Evans (of MDC) was clear that Ludek was acting as finishing contractor employed directly by Mr Cooper. However, Mr Gradwell (of
Thameside)
said otherwise when taken to the following documents.
"2. Contract Procedure. [MDC] explained that it had been agreed that all sub-contractors would now be under the control ofThameside
…and that everyone must report to [
Thameside]
about their programme on site, the information outstanding and any construction difficulties which they faced…
5. Ludek Build. Ludeck Tucny was introduced to the meeting as the finishing contractor for the works…..[Mr Tucny] had..to produce a price for acceptance by [Mr Cooper]. He will send this through to [Sheldon Studios] to check the content and to [MDC] for passing on to [Mr Cooper]. The intention is that [Thameside]
will hand over areas of the site to [Mr Tucny] who will then see that area through to completion."
Thameside
and Ludek, copied to others, to confirm that Mr and Mrs Cooper were happy to proceed with Ludek's proposed works and pricing as submitted:
"Accordingly please can you formalise Ludek's appointment and agree the programme going forward in order to get Ludek on site without delay."
Thameside
to take Ludek on as sub-contractor, and that he believed that that is what happened. He went on to say that this was a "mechanism" to save VAT for Mr Cooper.
Thameside)
it would be 5%, if not it will be 17.5%."
Thameside
recording receipt of £20,000 and asking for £10,000. On 11th September 2008 he was querying numbers on a payment certificate from
Thameside
and chasing payment on a fortnightly basis:
"Our company is not established for monthly payments and this was the reason why I agreed with Darren [of Sheldon Andrews] that only fortnight payments will allow me to step in to the Redington and work there…"
"…if Marcus wants to take it out of the responsibility ofThameside
and the contract that is fine. I will do whatever instructed. The downside is that neither
Thameside
nor ourselves have any control over the situation but if you can deal with it then that is fine (if Marcus agrees).
Thameside.
However that contract was only as a mechanism for reducing VAT for the Coopers. Ludek was never a sub-contractor in the sense of
Thameside
exercising any control or supervision of it.
Thameside
would be responsible for £25,000 to be paid on 31st July 2009. On 31st August 2009 payment would be made for whatever was outstanding in respect of the latest set of works by either Mr Cooper or
Thameside
or both as directed by MDC. Providing the final account was agreed, Ludek would be paid any outstanding balances by 11th September 2009.
Thameside
by about August 2008, but the terms of that agreement are uncertain. It is not at all clear to me that, if Ludek was responsible for the installation of the Polyplumb connector in or after August 2008, it was acting under that agreement. Indeed, Ludek's quotation suggests that it would not have been, given the express exclusion of plumbing works. It seems to me more likely that Ludek would have been acting under the "old" arrangement of working for Ottima/Signature. Had I therefore made a positive finding that Ludek was responsible for the installation of the Polyplumb connector at some stage after appointment as finishing contract, I would have concluded that it had not been established, on a balance of probabilities that it was then acting as the servant or agent of
Thameside
under the JCT contract.
M. Conclusion
Thameside
had very promising prospects at the outset of these proceedings:
a) It has always been common ground that the works under the JCT contract included the installation of the pipework beneath the basin in bathroom 6;
b) It has always been common ground that Darenth wasThameside's
plumbing sub-contractor under the JCT contract and the only contracted plumber on site;
c)Thameside
admitted that Darenth installed the Polyplumb connecter.
Thameside
and its insurers to provide their response to the claim, and in particular their response to the allegation that Darenth was responsible for installing the Polyplumb connector.
Thameside
installed the Polyplumb connector. In particular, I find that it is unlikely that Mr Johnson or anyone else at Darenth carried out that installation. Against an incomplete evidential picture, it is ultimately the combination of the credibility of Mr Johnson as to the essence of what he did and the real possibility that another non-Darenth tradesman on site performed the highly incompetent installation that leads me to the conclusion that the case against
Thameside has not been made out on a balance of probabilities.