You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd [2021] EWHC 1116 (TCC) (30 April 2021) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2021/1116.html Cite as: [2021] EWHC 1116 (TCC), 196 Con LR 85, [2021] PNLR 22, [2021] TCLR 5 |
||
[New search]
[Context
]
[View without highlighting]
[Printable PDF version]
[Help]
BUSINESS AND PROPERTY COURTS
TECHNOLOGY AND CONSTRUCTION COURT (QB)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
(1) Beattie Passive Norse Limited (2) NPS Property Consultants Limited |
Claimants |
|
- and |
||
| Canham Consulting Limited |
Defendant |
____________________
Rupert Higgins (instructed by Reynolds Colman Bradley LLP)
for the Defendant
Hearing dates: 3, 4, 8, 9, 10 and 19 March 2021
Draft distributed to parties 21 April 2021
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment is to be handed down by the judge remotely by circulation to the parties' representatives by email and release to Bailii. The date for hand-down is deemed to be 30 April 2021.
Mr Justice Fraser:
A. Introduction
B. The Issues
E. The Experts
F. Negligence
G. Causation and the Decision to Demolish
H. Conclusions
A. Introduction
Beattie
Passive
Norse
Ltd ("BPN") and NPS Property Consultants Limited ("NPS") as claimants against the defendant, Canham Consulting Ltd ("Canham"), a practice of consulting engineers.
Beattie
Passive Build System Ltd ("BPBS") formed a construction joint venture company, that company being BPN. NPS is therefore a shareholder of BPN. Someone called Mr Ron
Beattie
(who was not called as a witness by the claimants) was at the time a director both of BPBS and also BPN. BPBS has the licence for the
Beattie
Passive Build System, which is a PassivHaus approved system of construction.
Beattie
on behalf of the First Claimant and/or on behalf of the Second Claimant and BPBS engaged the Defendant to carry out the civil and structural design". That averment plainly elides together a range of potential contractual relationships, all into one rather general statement. It cannot be right, and I do not accept, that one person was acting on behalf of all three different companies at the same time, in engaging Canham as the designer. It is now accepted by Ms White for the claimants (quite correctly and sensibly) that Canham was engaged by BPN, the date of that being agreed as 20 April 2014.
Beattie
Passive Construction Ltd ("
Beattie
Construction"), another company in which Mr
Beattie
was involved, was contracted by BPN to perform the construction works. BPN was engaged by Hastoe Homes on 15 May 2014.
Beattie
Construction was engaged by BPN on a JCT Design and Build 2011 Contract on 12 August 2014. Mr Ron
Beattie
was a director both of
Beattie
Construction and also BPN (as well as being a director of BPBS). This contractual arrangement is described by the claimants in their submissions as being "back to back". This expression means that the contractual obligations of
Beattie
Construction to BPN matched the contractual obligations that BPN owed to Hastoe. BPN must therefore have been engaged by Hastoe on the same JCT terms.
Beattie
Construction. To be fair to Foxdown in this judgment (which as with all judgments, will be publicly available), the most recent revisions of the drawings issued by Canham to BPN, the company that engaged Canham, do not seem to have been issued for construction by
Beattie
Construction to Foxdown. Foxdown were issued with an earlier, superseded, set of drawings. Although
Beattie
Construction and BPN appear to be controlled by the same people (or some of the same people), there is limited evidence available concerning the exact working of the relationship between them. There is therefore limited evidence about whether BPN (who received the Canham drawings from Canham) issued them onwards in a full and timely fashion to
Beattie
Construction. Whether they did or not,
Beattie
Construction did not pass them on to Foxdown. That is clear on the face of emails originating from Foxdown. Foxdown used the Revision A version of the drawings for construction, and these were issued to Foxdown "for construction". Foxdown cannot, therefore, be criticised for using them for construction. This factor became known in about 2016, well after Foxdown had constructed the foundations, and is heavily relied upon by Canham in these proceedings.
Beattie
Construction the Revision A drawings with shallower depths, and smaller dimensions of pads. This version of the design is therefore the one that was used for each of Block A and Block B, which meant that the foundations as constructed did not match the foundations as designed in the Revision B drawings for the two blocks.
Beattie
Construction in terms of the building of both Blocks A and B generally (including the superstructure) were found to be defective. The degree to which they were defective namely, whether they were seriously defective such that the whole of the structures required demolition in any event, or merely defective such that they required remedial works short of demolition is in issue. The decision to demolish Block A was made in May 2016 and demolition of that block commenced in July 2016. Remedial works were already underway to Block B when the demolition of Block A took place, as those remedial works had commenced in May 2016. A decision to demolish Block B was then made in September 2016, part of the way through the remedial work for that block, and that demolition commenced in November 2016.
Beattie
Construction had its engagement under the JCT Design and Build Contract form terminated by BPN on 27 August 2015. The works were therefore left uncompleted and another contractor, RG Carter Ltd ("Carter"), was engaged both to inspect the works performed by
Beattie
Construction prior to its termination, and also to complete the works left unfinished by
Beattie
Construction as a result of that termination. There is, again, extremely limited evidence concerning the process whereby one company, BPN, decided to, and then did, terminate the contractual engagement of another associated company,
Beattie
Construction, where both of those companies had at least some directors in common, not least Mr Ron
Beattie.
However, the investigation by Carter of the work actually performed by
Beattie
Construction, and also investigations by Canham itself, following the termination, led to conclusions that remedial works were required to Block B. Block A seems, on the evidence, to have been in something of a hopeless state generally, and the decision was taken to demolish that in May 2016, as I have explained. It was obviously thought at one stage that Block B could be remediated, those works commencing as I have already explained. A couple of months after that work commenced however, the decision to demolish Block B rather overtook the progress of those remedial works.
Beattie
Construction (one of the three companies involved of which Mr
Beattie
was a director) were woefully defective the term used in cross-examination was "catastrophic" in terms of the extent and type of defects present. A very long list of defects that could not be the responsibility of Canham was relied upon by Canham, essentially to make good the point that the blocks would have had to be demolished in any event.
Beattie
again the word used was catastrophic the quality of both the sub-structure and superstructure works at Block A, in particular, was so shockingly bad that it had to be demolished in any event. Block A was not the only block with problems. It was discovered that Building Control had not even been invited to inspect the Block B foundations prior to the concrete being poured, and so had not done so. This would be a clear breach of the building regulations, as Building Control is required by the regulations to inspect foundation footings before the foundations are constructed. It also was the case at the time that further, serious, defects in Block A were discovered during the process of demolishing it. The Defence asserted that so little of the entire structure of both blocks had been built as designed, and/or had been built so defectively, that the demolition of the blocks was inevitable regardless of the conditions of the foundations. Canham also relied upon the fact that BPN terminated the engagement of
Beattie
Construction under the JCT terms. Given Mr
Beattie
was involved in both those companies, that could be described as a curious factual situation. Remedial works were actually underway to the Block B foundations when a decision was taken to demolish that too, and even though causation is challenged, Canham allege that those remedial works (which were very limited, and would have cost about £10,000 only) would have been the reasonable solution for the admitted breaches of duty concerning the design.
1. Causation.
2. Reasonableness of the decision to demolish.
3. Loss.
Beattie
Construction's varied failures of its own contractual obligations to BPN. He did, however, put the same points to them in terms of their evidence.
B. The Issues
Issue 1 Reliance
1. Were the Cs (and their groundworks contractor) entitled to rely on the drawings and did they in fact do so? Were the Cs (and their groundworks contractor) entitled to rely upon any other information or instructions (including the instructions given by email in August and September 2014) provided to them by D as providing an instruction as to how to build the structural elements, including the substructure, of Block A and Block B, and did they do so?
Issues relevant to liability
Issue 2 what was built
2. What did Foxdown in fact build in each of Block A and Block B respect of the substructure? In particular, in respect of:
2.1 Foundations (in terms of pad depths and founding levels, which the GIR report required to be 1 metre below existing ground levels or 0.2m into the Wadhurst Clay, whichever was the deeper, and which would need to be at least a minimum of 900mm deep under Building Regulations);
2.2 Dowels connections between (i) pads and ground beam; (ii) between ground beams and (iii) floor beams and ground beams;
2.3 Sleeper wall (connections and extent of wall);
2.4 Clay heave protection.
Issue 3 what were the Claimants/Foxdown told to build
3. How does the as-built substructure in respect of (i) Block A and (ii) Block B compare to the information provided by Canham at the relevant time, including in the RevB drawings (204208-610-B for Block A and 204208-612-B for Block B) and any further instructions from D in respect of each of the items above? As part of the court's consideration of this issue, it is necessary to decide:
3.1 Whether Foxdown could and/or should reasonably have scaled off the AutoCad versions of the drawings, and whether they did in fact do so?
3.2 Whether Foxdown could and/or should reasonably have obtained information from other sources than the drawings and whether they did in fact do so?
3.3 Whether the Cs/Foxdown were entitled to rely on the drawings and emailed instructions to them, which told Foxdown to construct pads to particular depths and whether they did in fact do so?
Issue 4 were the as-built substructures adequate
4. On the basis of the contemporaneous and expert evidence available regarding the as-built substructure of (i) Block A and (ii) Block B
4.1 was either substructure adequate? The issues for the court to consider include whether the substructure would be subject to excessive differential settlement.
4.2 If not, did the inadequacy arise from D's inadequate design and/or drawings and instructions?
Issue 5 were the as-designed substructures adequate
5. If the court finds that the as-built substructure differed from the as-designed substructure of (i) Block A and (ii) Block B, if the substructure of the Blocks had been built in line with that design, would either substructure have been adequate?
Quantum and Causation
Issue 6 scope of duty
6. From what type of loss did Canham owe a duty to hold the Cs' harmless? In particular:
6.1 Did D owe a duty to hold the Cs' harmless from economic losses arising from D failing to provide an adequate design for the substructure of Blocks A and/or B?
6.2 Is this a case in which the normal measure of loss in actions against contractors and construction professionals, being the "cost of cure", applies?
6.3 Could the cost of cure include the costs of demolishing and rebuilding either of the Blocks insofar as doing so was a reasonable way to remediate defects in Block A and/or Block B caused by D's inadequate design services (subject to causation see below)?
In other words, is the cost of demolishing and rebuilding a loss that, in principle, falls within either of the limbs of Hadley v Baxendale?
6.4 Could D's duty include a duty to prevent the Cs suffering costs (i) paid to third parties and/or (ii) wasted as a result of D's breaches of duty?
Issue 7
7. In respect of remedial works:
7.1 What remedial works would have been required to rectify the defects in the substructure for which Canham is responsible in (i) Block A and (ii) Block B?
7.2 Taking into account the scope and likely impact of those works on the superstructure of (i) Block A and (ii) Block B, as well as any other matters the court decides is relevant (such as predicted cost, delay etc), was the decision to demolish and rebuild each Block reasonable?
7.3 On the basis of the above, what costs are the Cs entitled to recover in respect of the demolition and rebuild of (i) Block A and (ii) Block B?
7.4 What costs are the Cs entitled to recover in respect of their other heads of loss (Wasted Costs of construction, LADs, design fees)?
C. The Two Claimants
"It is never sufficient to ask simply whether A owes B a duty of care. It is always necessary to determine the scope of the duty by reference to the kind of damage from which A must take care to save B harmless."
D: The Witnesses of Fact
Norse
Group Ltd ("
Norse
Group"). That company is not a claimant.
Norse
is the sole shareholder and parent of NPS, the second claimant, and a joint shareholder of BPN, the first claimant. Mr Hersey explained that he had been told by the
Norse
finance department that all of the invoices issued by Canham were paid either by NPS "through the
Norse
bank account" or from the NPS bank account. He also stated in his witness statement (although he did not provide the source of this knowledge) that "up to June 2015 there was only one bank account for
Norse
and all subsidiary companies" (emphasis added). This is an odd state of affairs, given limited companies are distinct and separate legal entities. Even on Mr Hersey's own evidence, some of the invoices were paid through the
Norse
bank account, and not from the bank account of NPS. I do not know, and it was not explained, why this collection of different companies should have organised their business affairs in this way. However, in my judgment it does not matter. It reinforces (if reinforcement were necessary) that the fact that NPS paid Canham's invoices does not impact upon the conclusion that Canham did not owe NPS a duty of care. The initial invoices were addressed to BPN and it is accepted that Canham and BPN had a contractual arrangement.
Beattie,
a co-director of his, how it was that Foxdown (under the contractual relationship it had with
Beattie
Construction, another company of which Mr
Beattie
was a director) had come to construct the foundations to the design contained on the Revision A drawings, and not to the Revision B design. The foundations on Revision B were far more substantial, and had very different dimensions. Mr Hersey also could not say whether anyone else had asked Mr
Beattie
about this either. His actual answer was:
"Personally, I didn't [ask MrBeattie].
I honestly cannot recall whether anybody else in our organisation may or may not have tried."
Beattie
Construction was replaced as the contractor. All that was said by Mr Hersey in his witness statement was: "at this point in time, the main contractor's (
Beattie
Passive Construction Ltd ("BPC")) employment had been terminated and, in BPC's place, RG Carter Ltd were carrying out the works". That is, in my judgment, an inadequate way to deal with such a major incident on any construction project, but particularly so here where one of the claimant companies, and the main contractor having their engagement terminated, shared a director, and where the contemporaneous documents showed that the works performed by
Beattie
Construction were so defective. These are telling omissions in the claimants' evidence of fact. Anyone with any experience of the construction industry would readily accept that terminating the employment of the main contractor on a project is a rather significant event. It is particularly significant if the work that main contractor had performed, prior to termination, proved to be so substantially defective. Giving that topic all of one limited sentence is, again, inexplicable.
Q. So just so we are absolutely clear, nothing in relation to the substructure then -- once those investigations had concluded, there were no issues with the substructure which necessitated the demolition of block B because the pads were fine, the dowels had been retrospectively fitted or were being retrospectively fitted when the decision was taken?
A. Yes.
Q. Mr Hersey, having established that there were no problems with the foundation to Block B, you mentioned after you were describing to his Lordship the other problems on Block B that it was structurally moving, was it not?
A. Yes.
Q. That was the superstructure moving and just so that we are clear you are not suggesting and have never suggested that that movement had anything to do with the foundations, are you?
A. I think from my perspective I was just relying on our consultant engineers' advice as to what the issue was.
Q. But nobody has suggested to you that the movement in the superstructure, which necessitated Block B's demolition, had anything to do with the foundations?
A. Not directly, no.
Q. Or indirectly?
A. No. The only thing I would say is that in my mind I was keen to exhaust what parts of the structure or the superstructure or the substructure to make sure that we fully understood what may be the contributory factors to the movement myself.
MR JUSTICE FRASER: Having done that, would you like to put your question again?
MR HIGGINS: Yes. (To the witness): Having done that, you were quite happy that none of those issues were related to the foundations?
A. That's correct.
Beattie
Construction's engagement had been terminated. All that he had said in his statement was:
"On 27 August 2015, BPN served a notice on the Contractor terminating its employment under the Building Contract. This letter was sent from me, as director of BPN".
Beattie
Construction, or the very widespread incidence of construction defects that could not possibly be laid at the door of Canham. Nothing was stated in respect of the assertion by Canham (which had been clearly pleaded in the Defence) that Foxdown had not constructed the foundations as designed, either. Where causation is so fundamentally in issue, this is somewhat surprising.
Beattie
Construction, and which were certainly not the responsibility of Canham. These were widespread, as shown in a great many of the contemporaneous documents.
Beattie
Construction, or even the pleaded averment in paragraph 31(2) of the Reply that
Beattie
Construction had itself suspended its works prior the termination. Due to the clause in the JCT contract relied upon by
Beattie
Construction, that suspension was probably due to non-payment. The reasons for that non-payment were not addressed in any evidence from the claimant at all.
Beattie
Construction, and nothing to do with the foundations, Mr Higgins turned to the issue of Foxdown constructing the foundations to the earlier, superseded design in Revision A which had been issued to it, rather than the later Revision B drawings with quite different depths and dimensions.
Q. And so when you learned on 18th April 2016 that in addition to this catalogue of errors somebody had failed to send Foxdown the correct construction drawings, you knew perfectly well who was to blame for that, did you not?
A. No.
Q. That is why you did not have to make any enquiries and you did not have to email anybody, did not have to instruct Birketts, for example, did not have to make any enquiries of anybody other than RonBeattie
because you knew that Ron
Beattie,
who was responsible for this catalogue of errors, was the obvious person who, in addition to everything else, had dropped the ball over the drawings being issued to Foxdown, was he not?
A. Are you suggesting that Canham Consulting hadn't issued the drawings to Foxdown direct and they were issuing them through somebody else?
Q. That is exactly what I am suggesting. It is a matter of record that, as one would expect, Canham issued drawings to RonBeattie
and Benedict Binns, who were both of
Beattie
Passive, were they not?
A. Yes.
Q. Yes. And so you knew as early as this, April 2016, that, in fact, the reason these pads had been constructed so shallowly had absolutely nothing to do with anybody misinterpreting Canham's drawings. You knew, did you not, that the whole thing was because RonBeattie
and Benedict Binns had failed to issue Foxdown with the right drawings in the first place?
A. I can't categorically say.
Q. So when it is suggested in this court on your behalf, Mr Gawthorpe, as it has been, that that is the reason why these foundations were built so poorly, that it was because somebody was misunderstanding Canham's correct drawings, you knew that the real reason is that Foxdown were not using the right drawings, did you not?
A. I can't categorically say that.
Q. Well, I am suggesting to you that that is the case, but whether you can categorically say it or not, it strikes me, if I may say so, as a rather surprising answer. Are you denying that you did not know that that was the real reason why these pads had been constructed so shallowly and, if so, why did you not know that?
A. Can you repeat that question?
Q. Are you suggesting that you did not know at this stage that the real reason these pads had been constructed so shallowly was that Foxdown had issued the wrong drawings?
A. Have we got -- I would need to look back and to look at the drawing issues from Canhams, because there were a couple of revisions of these, weren't there?
Q. Two.
A. Yes, that's right, so I'm not sure in my mind of where the dates are for Revision A and Revision B. So that's why I don't feel as though I can comfortably say what you want me to say.
"To be honest, I don't know exactly what was provided to Foxdown directly myself. I would only be able to maybe look at the drawing register."
Beattie
Construction (and/or the architect) did not forward to Foxdown the Revision B drawings, and instead issued Foxdown the Revision A versions which were stated to be "for construction". There is nothing in the documents to suggest that Foxdown were at fault in terms of constructing to the Revision A version. Foxdown did what it was instructed to do. This was clear from the contemporaneous documents, and also from the factual evidence of Mr Hersey and Mr Gawthorpe.
Beattie
Construction's contractual involvement in the project had been terminated by the letter from BPN (sent by Mr Gawthorpe), BPN were notified of a range of problems with the structures of both Blocks A and B. The overwhelming majority of these defects were structural and construction defects that could not have been, and were not, the fault of Canham. BPN was also notified by RG Carter, amongst others, that the wrong, earlier version of the design for the foundations had been used for construction by Foxdown. In an email of 18 April 2016 from RG Carter this was made clear. This email states:
"Please see the attached from Foxdown, sent last week.
We noticed on site on Friday with Rowland Smith from Carter that these are not the latest revisions of these drawings but are the ones issued to Foxdown for construction".
(emphasis added)
"Nigel
You need to be aware that pad foundations do not appear to have been constructed in accordance with your latest drawings 610 Rev.B .."
Beattie
Construction. Notwithstanding this, the Particulars of Claim that were served entirely omitted this important fact. The point was then clearly raised in paragraph 11.9 of the Defence, which stated the following:
"The Defendant will say that its foundation design would have been perfectly adequate for the loads and bearing pressures applied, had all the foundations been constructed in accordance with that design. As the Claimants well knew, they were not".
"The allegations made in paragraph 11.9 are unparticularised .."
E. The Experts
1. Mr Hughes constantly embellished his criticisms of Canham, and, I regret to say, exaggerated. He has been subject to some strong criticism by Mr Higgins in Canham's written closing submissions in this respect, who described one part of his evidence (where he was seeking to be more specific about breaches of Building Regulations and NHBC requirements) as "frankly farcical, descending into hysteria". Mr Hughes had said:
"If you have one foundation failing you will end up with the structure becoming uninhabitable and you will have the building possibly falling down on top of people and injuring people."
This evidence was somewhat extreme. There was no question, on the engineering evidence obtained at the time (not only by Canham, but by other consultancies such as MLM Consulting Engineers) of these "foundations failing", nor was that issue even raised by the engineering experts in these legal proceedings. Potential structural failure would be a relevant consideration in terms of the decision to demolish, but was not even a pleaded allegation in this case. Structural stability of foundations and their integrity is obviously important, and failures in this respect can (in some extreme cases) lead to collapse and issues of risk to personal safety, and even death. However, these proceedings do not concern such matters, not even remotely, at least not so far as the pleaded allegations against Canham are concerned. The issue in respect of which Mr Hughes gave this answer was differential settlement of less than 5mm, something upon which Mr Marychurch had given expert geotechnical evidence, and which he had explained was well within acceptable limits. I accept Mr Marychurch's more realistic evidence in this respect.
2. Mr Hughes constantly introduced new concepts or issues. One example of this is his distinction between two different types of Wadhurst clay of different colours, which is nowhere specifically identified as being an important distinction in his report, nor was this point even put to Mr Marychurch in cross-examination. I am confident that Ms White would have done so, had this been a live or relevant issue at the beginning of the second week of the trial when Mr Marychurch was called. The first time this was raised by Mr Hughes as a specific and important feature in any detail was in his oral evidence in the witness box, which was the next day. Another example was his explanation of why remedial works would not be suitable to timber framed structures. He said that repairing foundations to timber framed buildings would damage the structure, as the vibration and impact of the remedial works would cause the nails to vibrate and loosen. Again, this was new, and his report did not identify as a specific (or even general) point that demolition was required because timber structures would be damaged by repairs to the foundations. He appeared to be seeking to bolster the Claimants' case.
3. Mr Hughes also, in cross examination, relied on material that, in my judgment, had no relevance to the issues under consideration in this trial. One single example of this is what occurred in respect of Approved Document A. He had generally referred in his report to breaches of Building Regulations. When questioned, he said those he intended to refer to were contained in Approved Document A, which is a document issued under the Building Regulations 2010. When asked in further detail about this, he answered questions in respect of thickness by reference to Table 10 in Approved Document A (a document not appended to his report, but of which the claimants' solicitors had multiple copies pre-prepared and hence available). That table is headed "minimum width of strip footings" and has a cautionary piece of text below stating in express terms "The table is applicable only within the strict terms of the criteria described within it". Yet the foundations under consideration in this case are not strip footings at all, they are pad foundations with ground beams. They are of a different type to those specified in Table 10. Mr Hughes said that the same table would apply to pad foundations, but there is no relevant entry in Approved Document A that he identified in justifying this assertion. Nor would the text in the document cautioning against using that table other than "within the strict terms" support Mr Hughes in this respect.
4. Mr Hughes changed his agreement with, and reliance upon, the work of his associate Mr Baghi, whose report and work formed an appendix to his written report. Mr Baghi had concluded that the effect of eccentric loading upon the pad would not be significant enough to impact on the stability of any particular pad. Mr Hughes agreed that Mr Baghi had stated this, but said he disagreed with Mr Baghi. However, both in his written report and also in his confirmatory evidence in chief orally, he had expressly stated that he agreed with Mr Baghi. His report had stated "I have reviewed an expert report written by Mr Hooman Baghi of Diales and I agree with its findings". For reasons that are not at all clear, he changed this during his cross-examination when he was taken to the specific finding by Mr Baghi in respect of eccentric loading. This suggests to me that because the eccentric loading point did not assist the claimants' case, he disavowed it.
5. Mr Hughes agreed in cross-examination with Mr Owain Evans that clay heave protection was not required to the pads, but maintained that it would have been needed to some of the ground beams. The basis for this was wholly unclear, as he had not specified the extent of this in any detail in his report. The basis of his justification for this seemed to be that he, Mr Hughes, disagreed with Mr Marychurch's evidence that the Wadhurst clay was of medium change potential. However, this is a geotechnical point in respect of which Mr Marychurch's evidence is to be preferred in any event, due to the nature of the issue and the nature of Mr Marychurch's specific expertise. However and in any event, this point had not even been put to Mr Marychurch when he was cross-examined, as it ought to have been. It is, however, an example of Mr Hughes going further than was justified in terms of his own expertise. He is qualified in structural engineering and was not called as a geotechnical engineering expert. Mr Higgins submitted that this demonstrates a lack of objectivity on the part of Mr Hughes, a submission which I accept.
6. Mr Owain Evans sensibly agreed with points put to him, whether they advanced Canham's case or not. He had, in any event, already agreed in the Joint Statement that, in certain respects, Canham had been negligent. He approached his expert exercise applying, and his cross-examination demonstrated, a completely objective approach to the expert issues. The same could not be said of Mr Hughes.
7. Mr Owain Evans gave me the impression that his evidence would have been exactly the same had he been instructed by the claimants. Mr Hughes, regrettably, did not, and in my judgment, he constantly sought to advance the claimants' case at the expense of expert objectivity.
8. Mr Hughes introduced a concept into his cross-examination of "maximum robustness", when he was seeking to explain why localised remedial works of the foundations would not be sufficient. However, that is not the issue for the court, which has to consider reasonableness. Nor, in my judgment, is it the correct issue that would or should have been considered by a designer of foundations for buildings such as these. Canham were not instructed to design foundations of "maximum robustness". This concept appeared to have been introduced by Mr Hughes during his oral evidence for reasons of his own.
9. Mr Hughes also sought to defend the decision by the claimants to demolish both blocks, and maintained that this was required to remedy the foundations. This is notwithstanding the evidence of fact from Mr Hersey to which I have referred at [45] and [46] above. Experts should not take positions on contested issues of fact, a point that has been made in many cases, and one that is so obvious as to go without saying. Additionally, if a witness of fact makes a telling concession of this nature in respect of an important or central issue (here, the decision in respect of demolition and Block B), this is something that experts ought to take into account when they come to give their own oral evidence. The effect of such evidence ought at least to be considered. Mr Hughes did not change or alter his opinion in any respect after Mr Hersey gave the evidence I have referred to in respect of the foundations of Block B. He effectively ignored it, again (probably) because it was not helpful to the claimants' case. Mr Hughes seemed to feel that he had to defend the decision to demolish the blocks as a result of failures on the part of Canham.
F. Negligence
1. The Ground Investigation Report by Listers ("GIR") suggested foundations not greater than 1m in width, which suggests strip footings (point 7 of the Joint Statement). However, Mr Owain Evans considered that the GIR did not preclude the use of pad foundations and I agree. Mr Marychurch also agreed with this. Mr Owain Evans considered that pad footings were an appropriate solution provided they were designed properly, and I accept that evidence.
2. It was reasonable for Canham to rely on the safe bearing capacity of 150kPa and the settlement figure of 25mm provided in the GIR (point 8).
3. The allowable bearing pressure of 100kN/m2 stated on Canham's drawings was not adequate for the structural design of the foundations (point 11). I would just record that Pa is the SI unit for pressure which is the same as N/m2 (or Nm-2). Pascals and N/m2 are used more or less interchangeably throughout the Joint Statement, but they are both the same SI unit, one of pressure.
4. Canham should have provided on the drawing that the foundations should be installed to a depth of no less than 1m below ground level, or 0.2m below the top of the Wadhurst clay formation (point 13).
5. A number of the foundation pad depths shown did not comply with Building Regulations Approved Document A and NHBC Standards (point 17). However, Mr Owain Evans has identified that only 4 of the pad footings fell into this category, and those extended to a depth of 860mm below the final ground level rather than the recommended 900mm contained in the Building Regulations. He therefore concluded that the non-compliance was marginal and unlikely to result in any significant structural issues.
6. The bearing pressures under some pad footings exceeded the 150kN/m2 advised in the GIR (point 19). However, Mr Owain Evans concluded that this did not mean that the settlement of the footings would be excessive, a point with which Mr Marychurch agreed. This also arose in respect of point 20, which was that the risk of differential settlement had not been reasonably mitigated by the size of the pad foundations. However, again, Mr Marychurch had considered the matter of differential settlement as a result and concluded that it was within acceptable margins. There was no competing geotechnical evidence adduced from the claimants in this respect.
7. There were some foundations where Canham did not correctly estimate the applied loads on the substructure and load paths through the structure (point 26). The consequences of this were, however, considered by Mr Marychurch who concluded that excessive settlement would not occur.
8. There were foundations that were eccentrically loaded (point 27) and the effect of this loading was not considered by Canham (point 28). This was in respect of only a limited number of pad footings and the consequences of this were considered by Mr Marychurch, and his conclusions were that reinforcement was not required.
9. Canham's design did not show a connection between the adjacent ground beams (point 30). Mr Owain Evans accepted that the beams should be connected to the pads, and if this were done adjacent ground beams did not need connecting to one another as well.
10. There was no steel dowel connection between ground beams and pads adequately specified on the Canham drawings (point 31). These should have been provided.
11. The Canham drawings should have indicated formation levels or pad depths on the paper drawings issued to the contractor (point 33). From the other evidence, what this means is that these dimensions should have been provided by way of label on the .pdf drawings.
12. Canham should have shown the setting out of the structural elements including the ground beams on the .pdf drawings. This was not done (point 34). However, the setting out was shown on the architects' drawings. I consider that this must have been done by the architects by using the setting out provided in Canham's design.
13. Any and all structural elements required by Canham to achieve their design should have been shown on the drawings issued by Canham (point 36). This included the dowel connections.
14. A connection was required between the ground beams and the pads and this was not specified by Canham (point 37).
15. The Canham drawings did not show the sleeper walls extending to the underside of the precast concrete floor (point 39) However, the architect's drawings did so. The contractor was therefore aware of this requirement.
16. There were several notes on the Canham drawings that were inaccurate, unclear or incomplete (point 40). These were notes 5, 6, 11 and 15. Note 5 referred the contractor to design calculations, and the experts were agreed that it was unreasonable to do so. Note 6 was the error to which I have already referred when dealing with Mr Evans' evidence of fact, namely that concerning bearing pressure, where the figure of 100kN/m2 was stated and it should have been 150kN/m2 (Mr Evans' "typographical error"). Note 11 was an irrelevant note referring to strip foundations, which was not applicable to this design of foundations at all, because they were not strip foundations. It should not therefore have been included at all. Note 15 was also irrelevant as it stated "In the event of clay soils being encountered on site, unknown to the engineer, the engineer is to be informed immediately". The whole site had Wadhurst clay as the underlying ground condition.
Beattie
Construction. There were a wide range of other construction defects that had nothing to do with Canham or the design of the foundations.
G. Causation and the Decision to Demolish
Beattie
Construction, which may be why both Mr Hersey and Mr Gawthorpe chose to ignore them. Indeed, notwithstanding the heading in his own witness statement where Mr Hersey posed the question "What informed the Claimants' decision to demolish Blocks A and B, what additional issues, workmanship or otherwise, were encountered in the construction of the blocks, and did they contribute to the decision to demolish?", this was a subject almost completely avoided by him in the passages of his written evidence that followed that heading. Nor was any evidence provided by him in his written evidence about the reasons for the termination of
Beattie
Construction, or the very widespread incidence of defects that could not possibly be laid at the door of Canham. Nor was anything stated in respect of the assertion that Foxdown had not constructed the foundations as Canham had designed them. Where causation is so fundamentally in issue on the pleadings, this is (putting it at its lowest) surprising. It is certainly an absence of direct evidence on a very important area of the case, if not on the central issue in the case.
Beattie
Construction, but again, in extraordinarily limited detail. Nothing was stated at all in this written evidence about the defects which the contemporaneous documents record as being present. His statement in this respect was as follows:
"On 27 August 2015, BPN served a notice on the Contractor terminating its employment under the Building Contract. This letter was sent from me, as director of BPN".
Beattie
Construction itself suspended works and then had its engagement by BPN under the JCT contract form terminated. Given there was at least one director in common between both BPN and
Beattie
Construction, namely Mr Ron
Beattie,
this absence of evidence or further explanation is most surprising. Mr Gawthorpe in his oral evidence said that the termination was due to "procedural matters". This refers implicitly to the JCT contract conditions that permit termination under certain circumstances not connected with the quality of work. However, this statement almost raises more questions than it answers. Given Mr Ron
Beattie
was a director both of BPN and
Beattie
Construction, the brevity of evidence available in respect of BPN terminating
Beattie
Construction's employment does not begin to address, or explain, the very real issue of
Beattie
Construction's defective work.
Beattie
Construction undoubtedly existed, as demonstrated by Mr Hersey's admission that the superstructure of Block B was actually moving, for reasons unconnected with the foundations.
Beattie
Construction, the absence of any positive evidence from the claimants on this becomes even more marked.
Beattie
Construction (or other sub-contractors), which was not the responsibility of Canham, was very considerable. That important evidence was not included in their witness statements because it appeared to be unfavourable to the claimants' case.
1. Foxdown's failure to construct the foundations designed by Canham contained in the Revision B drawings, and the construction of those foundations by Foxdown to an earlier superseded design contained in Revision A.
2. The failure of supervision by the different entities on site that this represented. Mr Gawthorpe's question back to Mr Higgins when asked about this, when he said to Canham's counsel "are you suggesting that Canham Consulting hadn't issued the drawings to Foxdown direct and they were issuing them through somebody else?" demonstrated in my judgment that he considered Canham to be responsible for this failure by Foxdown (or by the supervising architect) in any event. I have also dealt with this at [56] above.
3. The fact that Building Control were not given the opportunity to inspect, and did not inspect, the Block B foundations at the stage when they were excavated and prior to the concrete being poured.
4. The widespread and serious defects in the other work constructed by
Beattie
Construction, including (but not only) that the superstructure of Block B was found to be moving for reasons not connected to the foundations.
5. The relationship between
Beattie
Construction and BPN, and the decision taken by the latter to terminate the former's contractual engagement. The complex or detailed decision making that must have taken place (given Mr Ron
Beattie
was a director of both companies) was entirely ignored. This omission may have been related to the issue to which I have already referred, namely
Beattie
Construction's quality of work. It may have been for other reasons. It is not necessary to speculate on any of this.
Beattie
Construction itself suspended performance of the works prior to the termination. This too was not dealt with in the evidence.
6. The discovery of other defects that were present in Block A as it was being demolished. Contemporaneous documents demonstrate that any confidence there might have been in Block B gradually diminished, as more and more work was discovered to be defective in Block A. There plainly was some confidence in Block B in about May 2016, as the localised remedial works to the Block B foundations actually commenced. By September 2016, a decision had been taken to demolish Block B too. Nothing further was discovered about the Block B foundations after those remedial works had started that would, of itself, justify or explain demolition. The period between May 2016 (when it was decided to perform localised remedial works to Block B) and September 2016 (when it was decided to demolish Block B too) is the period when Block A was being demolished. The foundations of Block B had not changed during that period. The state of knowledge concerning the type of defects present in Block A had, however, been advanced.
1. Mr Higgins for Canham has some justification in his objection that this way of putting the case was simply not pleaded. These emails are not included in the claimants' own pleaded definition of what the design produced by Canham consisted of.
2. The emails are plainly, on their own terms, provided to Foxdown so that Foxdown could prepare its own pricing. I accept Mr Evans' explanation that this was why the emails were sent, but the same point can be made by reading the whole string of emails in context.
3. The emails equally plainly only deal with thickness. This is entirely understandable and justified given point 2 above, and in any event demonstrates that the emails do not deal with depth of foundations, and they cannot properly be read in that way. Depth of foundations, and their thickness, are two entirely different dimensions.
4. Ms White's case in this respect was not only not pleaded, but positively contrasted with the Reply where in paragraph 31(3), dealing with causation, the claimants themselves (again supported by a Statement of Truth) had stated the following:
"However, as to the depths and thickness of foundations, (a) it is denied that the Defendant specified depths for the foundations (as set out above) and (b) as to thickness of foundations, it is averred that no or no adequate dimensions were provided on the Defendant's drawings and that dimensions provided in its email of 11 August 2014 were incomplete." (emphasis added)
5. That pleading made a distinction between depth and thickness; to equate those two is contrary to that pleaded case (and, in any case, wrong). Further, the Reply stated that the email information was "incomplete", and Ms White's new argument in closing submissions was different, maintaining that it was positively incorrect. The argument is therefore not only not pleaded, it is directly contrary to what was pleaded.
"the fact that unforeseeable events combine with the breach to cause loss cannot alone be a sufficient reason for a decision that the unforeseeable events have superseded the breach of contract as the cause of the loss. The effects of the breach of contract may continue though other causes combine to produce the final result".
"[32] On the question of causation, Ramsey J considered that the overflowing of water from the sprinkler tank which resulted from the failure of the connection between the ball valve and lever arm was an effective cause of the flood. The blockage of the drains did not take away the potency of the overflow to cause damage, but rather failed to reduce it.
[33] I see no error in that approach. On the contrary, it would have been a rash lawyer who would have advised Siemens that it was likely to succeed on the causation issue, let alone that it could be confident of doing so."
Beattie
Construction and/or its subcontractors. For Block A, it was also the defective nature of the foundations, but they had not been constructed in accordance with the design produced by Canham in any event. In Foxdown's case, it would be unfair to make any finding adverse to Foxdown that it was at fault in constructing to the Revision A design, because these drawings were clearly issued to it "for construction". That was not the fault of Canham.
"If such a course of action is to be justified at all, it will ordinarily be because the building is dangerous or structurally unsound. That was simply not the case here."
In the instant case, the blocks were structurally unsound, but not as a result of anything that was defective with the foundations designed by Canham. The two blocks were structurally unsound because of the considerable amount of defective work, unconnected with the foundations (and hence unconnected to any breaches by Canham), which had been performed by
Beattie
Construction. One example of the grossly defective nature of the work is the damp proof membrane which is explained further in [128] below. I can do no better than quote the dicta of HHJ Newey QC in the well-known Great Ormond Street Hospital case, Board of Governors of the Hospital for Sick Children v McLaughlin & Harvey plc (1987) 19 Con LR 25, 96, cited with approval in McGlinn at [834]:
"However reasonably the plaintiff acts, he can only recover in respect of loss actually caused by the defendant. If, therefore, part of a plaintiff's claim does not arise out of the defendant's wrongdoing, but is due to some independent cause, the plaintiff cannot recover in respect of that part."
Beattie
Construction. Nor do I consider any different result is obtained if the matter is approached as a breach of duty by Canham, rather than a breach of contractual obligation. On the facts here, the reason for demolition was the work of
Beattie
Construction, and not the negligent design of the foundations by Canham.
Beattie
Construction or other entities involved in the construction of Block A, and not the fault of Canham.
Beattie
Construction had done was extremely defective. As one example only, in one of the blocks, the damp proof membrane or DPM had been installed below ground level. Given DPMs operate by means of the membrane preventing dampness from the ground rising through the walls of a structure, to have installed a DPM in the position it was in fact installed here, not only demonstrates abject incompetence on the part of the installer, but similarly abject incompetence on the part of whoever was supervising that work. Mr Higgins also put to Mr Gawthorpe that in addition to its inadequate location, the DPM was (as Mr Higgins put it) "completely shredded". Mr Gawthorpe agreed that it was "shot". By each of those terms, they meant that its integrity as a membrane was wholly flawed due to damage to the membrane itself. There were other structural issues too. The superstructure of Block B was actually moving, a point accepted by Mr Hersey.
Beattie
Construction, with the subsequent demolition and rebuilding, which I have found are losses that cannot in law be attributed to the negligence of Canham. Thirdly, the claim for delay and liquidated damages or LADs is not split out into different periods for which there is specific evidence which would allow me to assess how much, if any, was caused by the partial remedial works on Block B. In any event, that was being performed at the same time as other works in respect of Block A, namely its demolition and rebuilding.
Beattie
Construction's engagement; the defective construction of Blocks A and B; the investigations required; the inevitable decision to demolish Block A; the discovery during that of further serious defects in the superstructure; the loss of confidence in Block B; and the corresponding decision to demolish Block B too. None of them, I consider, have been caused by the negligence or breach of contract of Canham.
Beattie
Construction in terms of defects, and the fact that Foxdown constructed the foundations to the wrong design, and also that Building Control were denied the opportunity to inspect the foundations, I find that the report by MLM would have been required in any event. It was certainly not required as a result of the negligence or breach of contract on the part of Canham.
H. Conclusions
Beattie Construction) was not provided with the Revision B drawings, and did not rely upon them. Foxdown constructed the Revision A design, those drawings being issued to it "for construction". It is not known whose fault that was, but it was not the fault of Canham.