![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales Lands Tribunal |
||
|
You are here: BAILII >> Databases >> England and Wales Lands Tribunal >> Severn Trent Water Ltd v Coal Authority [2004] EWLands LCA_38_1999 (14 April 2004) URL: https://www.bailii.org/ew/cases/EWLands/2004/LCA_38_1999.html Cite as: [2004] EWLands LCA_38_1999 |
||
[New search]
[Context
]
[View without highlighting]
[Printable RTF version]
[Help]
[2004] EWLands LCA_38_1999 (14 April 2004)
LCA/38/1999
(consolidating LCA/34-38/1999)
LANDS TRIBUNAL ACT 1949
COMPENSATION mining subsidence damage to sewers limitation preliminary issue knowledge of subsidence damage whether facts from which claimant might reasonably have been expected to acquire knowledge were observable or ascertainable by it more than six years before damage notice given Coal
Mining Subsidence Act 1991 s 3 burden of proof approach of sewerage
authority
to identification of damage claimant held to have failed to show that it could not reasonably have been expected to acquire requisite knowledge
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN
SEVERN
![]()
TRENT
![]()
WATER
LIMITED
Claimant
and
THECOAL
![]()
AUTHORITY
Compensating
Authority
Re:
Sewers at
(i)Waterfield
Farm, Old Clipstone,
Nottinghamshire
(ii) Greenwood Drive, Kirkby in Ashfield,
(iii) Beauvale Road, Hucknall,
Before: The President and N J Rose FRICS
Sitting at 48/49 Chancery Lane, London WC2A 1JR
on 17-19 and 25-27 November and 4 December 2003
The following cases are referred to in this decision:
Crockerv
British
Coal
Corpn (1995) 29 BMLR 159
Gascoinev
Ian Sheridan & Co [1994] 5 Med LR 437 at 441
The following further cases were also cited:
Liddellv
Middleton CA 7 July 1995, unreported.
Spencer-Ward and Anotherv
Humberts [1995] 1 EGLR 123
Glaisterv
Greenwood [2001] PNLR 602
El Ajouv
Dollar Land Holdings Plc and Another [1994] 2 All ER 685
Daviev
Edinburgh Magistrates [1953] SC 34
Richard Harding, instructed by Kent, Jones and Done of Stoke-on-Trent
for the Claimant
Paul Darling QC, instructed by DLA of Sheffield for the CompensatingAuthority
DECISION ON PRELIMINARY ISSUES
Introduction
Severn
Trent
Water
Limited, to compensation for damage to its sewers which it is agreed was caused by
coal
mining subsidence.
Severn
Trent
Water
Authority
was created under the
Water
Act 1973 as one of the ten regional
water
and sewerage companies. It became responsible for the
water
and sewerage networks within the catchments of the River
Severn
and the River
Trent.
Upon privatisation in 1989,
Severn
Trent
Water
Authority
became
Severn
Trent
Water
Ltd.
In this decision we refer to both simply as 'STW'.
(i)Waterfield
Farm, Old Clipstone ("
Waterfield
Farm")
(ii) Greenwood Drive, Kirkby in Ashfield ("Greenwood Drive")
(iii) Beauvale Road, Hucknall ("Beauvale Road").
"For each of the references did the claimant have the knowledge, as defined by section 3(4) of theCoal
Mining Subsidence Act 1991 ("the 1991 Act"), required for founding the claim made in that reference, more than six years before notice in respect of that claim was given to the Compensating
Authority
under section 3 of the Act?"
"(3) The period allowed by this section for giving a damage notice with respect to any subsidence damage is the period of six years beginning with the first date on which any person entitled to give the notice had the knowledge required for founding a claim in respect of the damage.
(4) For the purposes of subsection (3) above, the knowledge required for founding a claim in respect of any subsidence damage is knowledge
(a) that the damage has occurred; and
(b) that the nature of the damage and the circumstances are such as to indicate that the damage may be subsidence damage;
and a person's knowledge includes knowledge which he might reasonably have been expected to acquire from the facts mentioned in subsection (5) below.
(5) Those facts are
(a) any facts which were observable or ascertainable by him; and
(b) any facts which would have been ascertainable by him with the help of any expert advice which it was reasonable for him to seek."
Coal
Mining Subsidence Act 1957 ("the 1957 Act"). The 1957 Act contained no equivalent to the "constructive knowledge" provisions of the 1991 Act. The trigger date for the service of a notice was the date when evidence of the damage first appeared.
Waterfield Farm |
8 February 1994 |
| Beauvale Road | 7 August 1995 |
| Greenwood Drive | 7 August 1995 |
vicinity
of the sewers was as follows:
Waterfield Farm |
1985/86 |
| Beauvale Road | 1982/83 |
| Greenwood Drive | 1976/77 |
authority
that the damage in each claim may have been caused by mining, whether by the most recent mining or by earlier mining. It is common ground that the damage occurred shortly after mining had taken place. It is agreed, however, that STW did not have actual knowledge of the damage to the relevant sewers until 1994/5. The question that arises on the preliminary issue is whether in each case STW had the required knowledge of the damage more than 6 years before the damage notice was served, ie before the following dates:
Waterfield Farm |
8 February 1988 |
| Beauvale Road | 7 August 1989 |
| Greenwood Drive | 7 August 1989 |
Coal
Authority
Act 1975, together with the regular inspections of the NCB's plans showing details of the mining that was currently under way or proposed. It denies that either that knowledge or any previous instances of damage should have caused it to carry out more investigations into possible further damage than those which it in fact did.
authority
(the
Coal
Authority)
contend that STW ought to have known about the damage to the relevant sewers more than six years before it in fact did, because of knowledge which it might reasonably have been expected to acquire. In summary, the
authority
rely on three categories of fact which they say gave STW the required knowledge. Firstly, the fact that mining was taking place under or in the
vicinity
of the sewers. Secondly, other adjacent incidences of subsidence damage, in respect of which STW had previously submitted damage notices to the compensating
authority
and then executed remedial works. Thirdly, the results of investigations which either were or ought to have been carried out by either its own staff, or by staff of its agents or professional consultants.
The statutory provisions and the burden of proof
authority's
case that subsection (5)(a) was to be treated as operating in this way.
water
authority
and, secondly, in the light of all of the circumstances at the time when the events alleged to have given rise to constructive knowledge took place. Mr Darling submitted that the assessment of reasonableness should not be limited by reference to a reasonable
water
authority.
The question of reasonableness had to be taken in the round. The fact that all
water
authorities
behaved in the same way would not of itself make the behaviour of this one reasonable. It was perfectly possible that all
water
authorities
were behaving unreasonably. Mr Darling noted the two-stage introduction of reasonableness in the statutory provisions: whether it was reasonable to instruct an expert and whether it was reasonable to expect STW to acquire the relevant knowledge from what he termed "the facts in the basket" the fact of mining having taken place and damage that had actually been identified and made the subject of claims. No expertise was needed in order to detect damage through the use of CCTV, and the question therefore was whether STW ought reasonably to have acquired the relevant knowledge in the the light of the facts that were known.
coal
mining subsidence. Before the 1991 Act came into operation, the statutory scheme was that in the 1957 Act, which identified as the trigger date for the service of a damage notice the date when evidence of damage first appeared. It thus provided no reason for STW to go looking for damage, since its right to claim compensation was preserved until the damage became evident. The
Coal
Authority,
Mr Harding said, could not sensibly seek to apply the standards of the 1991 Act to actions taken while the 1957 Act was in force. In the course of the oral amplification of his closing submissions, however, Mr Harding accepted that whether it was reasonable to make enquiries about possible subsidence did not turn on the prospects of obtaining compensation for remedying such damage as might be found. We consider that Mr Harding was right to make that concession. What it is reasonable for a sewerage undertaker to do to ensure that its sewerage system is suitably maintained cannot be conditioned by the nature of any entitlement it may have to have the cost of repairing a particular type of damage paid for by another person. The only exception to this, we think, is where delay in identifying damage might increase the liability on that other person. But simply because, under the legislation providing for such liability, the claim is preserved until the damage is discovered, cannot in our
view
be seen as justifying a less active approach to the identification of damage than a sewerage undertaker would reasonably adopt to ensure that its sewerage system was suitably maintained.
v
British
Coal
Corpn (1995) 29 BMLR 159. That concerned a personal injury claim and the particular statutory provisions of relevance were sections 11 and 14 of the Limitation Act 1980. The issue was whether the claimant had knowledge (under section 14(1)(a) and (b)) that her injury was significant and that it was attributable to the negligence of the defendant. Thus the issue related to the actual knowledge of the plaintiff. Section 14(3) contains a provision relating to constructive knowledge similar to that contained in the provision of the 1991 Act that we have to consider, but no issue of constructive knowledge arose. However, in a full review of the relevant
authorities,
Mance J referred to a passage in the judgment of Mitchell J in Gascoine
v
Ian Sheridan & Co [1994] 5 Med LR 437 at 441:
"The burden on the plaintiff is to show, on the balance of probabilities, that her cause of action came into existence on a day within the limitation period. Once that is demonstrated then the evidential burden moves to the defendants they in turn must demonstrate that, in truth the cause of action arose at some earlier date byvirtue,
for example, of constructive knowledge on the part of the plaintiff: Nash
v
Eli Lilly & Co ((1992) 14 BMLR1 at 13, [1993] 1 WLR 782 at 796)."
"It is clear from the reference to the effect of constructive knowledge that Mitchell J is, as a matter of shorthand although not strictly accurately, speaking of knowledge under s 11 as if it were an element in the accrual of the cause of action. His first sentence therefore reaffirms the legal burden on a plaintiff to prove that knowledge (where material) only arose within the three years preceding the writ. His second recognises that an evidential burden may exist on a defendant to rebut the plaintiff's case, by, for example, adducing evidence to show (no doubt after pleading) constructive knowledge.
Taking this as the correct interpretation of Mitchell J's summary, there is in my judgment much to be said in favour of the analysis which it adopts. The legal burden rests throughout on the plaintiff, whether the issue is when the cause of action accrued or when the plaintiff first had knowledge of the facts in the sense identified in s 14. The concept which theauthorities
have called 'constructive knowledge' is by definition in s 14(3) one aspect of 'knowledge'. The date of first knowledge depends as much on knowledge which the plaintiff might reasonably have been expected to acquire from (a) facts observable or ascertainable by him or (b) ascertainable (subject to the proviso) by him with the help of medical or other appropriate expert advice as it does on actual knowledge. An issue arising under s 14(3) is, however, apt to involve an evidential burden on a defendant, at all events if there is nothing in the plaintiff's own case or evidence to raise the issue, although in some respects, for example in relation to the words 'so long as he had taken all reasonable steps to obtain (and, where appropriate, act on) that advice' in the proviso where they became material, it may be easy to envisage both the legal and an evidential burden on a plaintiff."
authority
to establish matters which, they say, would constitute facts for the purposes of section 3(5) and from which they assert that the claimant could reasonably have acquired the knowledge required for founding a claim. If they do so the burden is then on the claimant to show, in relation to such matters, that it could not reasonably have been expected to acquire the requisite knowledge from them. In the present case the
authority
have identified the matters that they say led to STW having the required knowledge for the purposes of section 3. They consist of the fact of mining having occurred in the
vicinity
of the sewers, the techniques available to STW for the discovery of damage, previous claims in the
vicinity
of the sewers, and complaints and records of flooding.
Evidence of witnesses
authorities
acted as sewerage agents for STW. He also called two expert witnesses, namely Mr C
V
Knipe, BSc, CEng, CGeol, MIMMM, FGS, senior partner of Johnson Poole and Bloomer, who dealt with mining issues and Mr G F Read, MSc, CEng, FICE, FIStructE, FCIWEM, a director of Deakin Walton Limited, who dealt with sewerage issues.
authority
Mr Darling called as a witness of fact Mr K Blackburn, MCIOB, MBEng, until recently employed by International Mining Consultants, who investigated subsidence claims on behalf of the compensating
authority.
Mr Darling's expert witness on mining was Dr P Carr, BSc, PhD, CEng, FIMMM, head of mining at WS Atkins Consultants Limited and his sewerage expert was Mr R Engledow, IEng, ACIWEM, a principal engineer with Atkins Design Environment and Engineering.
coal
mining subsidence claims, which all related to claims under the 1957 Act. The total
value
of those claims was in the region of £10m. Since then STW had submitted approximately 230 claims against the
Coal
Authority
and British
Coal
to a
value
of approximately a further £6.8m. Against all these claims British
Coal/the
Coal
Authority
had paid in the region of £13m.
authorities.
As the local
authorities
had detailed knowledge of the systems in their area, it was decided that STW would continue to employ them to maintain and manage the sewerage networks within their respective administrative areas. This continued until about March 2000, when STW began to carry out these functions itself.
authorities
as part of their management duties. Claims relating to
water
mains and the distribution system were generally pursued by STW's own distribution staff. There was little, if any, communication of information on subsidence damage between those responsible for sewerage and those responsible for
water
mains, as they worked for different organisations, and there was no technical need for each to be kept aware of what the other was doing.
authority
to reimburse its expenditure on repairs necessitated by mining subsidence.
coal
mining subsidence. When damage was found, its location was compared with that of known mining. If it was in an area where mining had taken place, and the damage was of a type consistent with
coal
mining subsidence, this was considered sufficient for STW to make a claim for compensation.
water
and sewerage companies to complete such an appraisal. The purpose of these inspections was not to find whether STW had claims in respect of
coal
mining subsidence, but rather to ascertain the condition of these critical sewers. When deciding when the
various
sewers were to be the subject of a DAS, the fact that mining was taking or had taken place in the area was one of the factors that STW took into account, as sewers in such areas were more likely to be in need of work.
coal
panel under a built-up area might entail a survey (both internal, by CCTV, and external, by levelling) of up to 100 km of sewers. This could cost between £100,000 and £150,000. In 1991 there were around 28 deep
coal
mines in the
Severn
Trent
area. On average, each would be working two or more faces at any time. The cost of surveying only once every sewer potentially affected by mining would therefore be up to £8.5m. This would be the equivalent of carrying out almost 300 typical subsidence remedial schemes. By comparison, the current budget for the DAS-type surveys for strategic sewers for the period 1995 to 2005 was £12m and STW's total average annual expenditure on maintenance of sewers was only about £25m. STW considered that spending in the region of £8m on investigations, with no guarantee of any recovery of the costs incurred, would not have made sense either from a commercial or an operational point of
view.
very
general terms. He usually became aware of such damage only when there was some evidence to show that damage may exist, such as surface flooding.
Waterfield
Farm claim) STW had over 60 km of sewerage installations. It would not have been commercially prudent to carry out investigations at a cost of over £1,000 per km (excluding subsequent processing of the data obtained) in order to ascertain whether damage might have occurred due to
coal
mining. In cross-examination, however, Mr Loy accepted that this cost could have been substantially reduced if he had carried out some basic calculations of where the subsidence was likely to be most severe and then made some spot checks.
Waterfield
Farm claim related to the main trunk sewer running from Mansfield to the Edwinstowe sewerage treatment works. It was a combined sewer, carrying both foul and surface
water.
Its diameter was approximately 45 cm. Mansfield District Council ("MDC") prepared a DAS for the Clipstone/Edwinstowe area in 1991-1992. This covered the
Waterfield
Farm area. The surveys for the study were carried out in 1990, but did not discover any problems at
Waterfield
Farm at that time. However, the subject sewer crossed farmland and some of the manholes were buried under fields, so that it was difficult to locate them. As a result, neither the CCTV nor levelling surveys were completed over the section at
Waterfield
Farm where the problems were eventually found.
Waterfield
Farm sewer, it did state that most of it showed overloading (peak flow greater than capacity). In addition, the computer model produced flooding under certain simulated rainfall conditions at one manhole. In relation to that location the DAS indicated that there was no record of actual flooding having been reported, although the inspection revealed evidence of surcharge and flooding. The Clipstone/Edwinstowe DAS did discover some damage to a nearby trunk sewer in farmland known as Forge Bridge/River Maun. As a result, Mr Loy served the appropriate damage notice on 18 October 1990 in respect of a loss of gradient and possible structural damage there.
Waterfield
Farm. The levelling surveys were carried out by Newark and Sherwood DC ("NSDC") as sewerage agents. A company called Insight Surveys was engaged to carry out a CCTV survey. The initial levelling suggested that the sewer had moved. Since this was typical of subsidence damage, a damage notice was served on the compensating
authority
on 8 February 1994.
Coalville,
New Swannington, Hucknall, Huthwaite and Kirkby in Ashfield. The 1995 pilot survey related entirely to non-critical sewers. Mr Loy explained that the claimant had been concerned that the compensating
authority
would interpret the 1991 Act as precluding claims made more than six years since the last mining in the area. On 4 April 1995 Mr Loy prepared a paper outlining the background to and the results of the pilot study. He recommended that damage notices should be served on the compensating
authority
in respect of the damaged sewers which had been discovered in the Ashfield district. If they were successful, further surveys of minor sewers in other mining "hot-spots" should be undertaken on a rolling basis, with a
view
to completing them within six years of the 1991 Act coming into force. The paper correctly anticipated that the compensating
authority
might reject the damage notices on the basis of the time elapsed since the last mining in the area. In that event Mr Loy recommended that "the case(s) should be pursued in arbitration/litigation after legal advice has been sought."
authority
accepted liability, was a success. Even had they accepted liability, they would only have offered to pay 17% of the direct costs of the survey. Since a survey of the whole area would have cost more than £9m, and taken 20 years to complete, the compensating
authority
would have contributed only about £1.5m to the survey costs, leaving a shortfall of £7.5m.
authority
rejected the claim by a letter dated 23 November 1995. They pointed out that the area of Greenwood Drive was subject to a claim by STW dated 4 July 1979, which had been discharged by the NCB by a payment for repairs which were incorporated in the West Kirkby Subsidence Remedial Works Scheme. They also said that they considered that STW were aware of mine workings in the Greenwood Drive area in 1979 and therefore any claim was statute-barred. STW replied to this letter on 20 February 1996 to the effect that the previous claim and the West Kirkby Subsidence Remedial Works Scheme related to sewers on a completely different system. They accepted, however, that one section of sewer in Highfield Avenue might have been included in the earlier claim and they agreed to omit it from the Greenwood Drive claim.
water
reclamation works, strategic
water
mains, land drainage pumping stations, reservoirs, booster pumping stations,
water
towers and boreholes.
various
operational offices as a guide to potential future problems, to assist with the organisation of pre-mining surveys of strategic installations, where this was considered appropriate. In fact,
very
few such pre-mining surveys were undertaken.
Coal
Corporation, to streamline the recovery of compensation for damage caused by mining subsidence. This exercise was never completed although certain aspects, including the recovery of design and supervision fees as a proportion of the cost of works, were agreed and had been relied upon on a number of occasions.
Severn
Trent
region was 53,325 km. Approximately 15% of these were classed as "strategic". As at 30 September 1998, there were 2,495 km of strategic sewers (14.6%) and 14,539 km of non-strategic sewers (85.4%) in the East Midlands region alone, ie the area covered by the three subject claims. Due to access difficulties, it had generally proved impossible to inspect even the full strategic system. The percentage of sewers actually inspected in the studies had therefore been around 12-13%. The notion of strategic sewers had been introduced to concentrate effort on those sewers which were most likely to fail and/or potentially cause most disruption on failure, that is, where the consequences of hydraulic or structural failure were sufficient to warrant the cost of pre-emptive strategic inspection and analysis.
water
services company in the UK to have completed a comprehensive assessment of its strategic sewerage network. Since 1995 it had been carrying out drainage area management studies ("DAMS"). These used the nationally recognised definition of "critical sewers" in place of its own notion of "strategic sewers". This definition was taken from the Sewer Rehabilitation Manual ("SRM"), produced by the
Water
Research Centre ("WRC"), and related to sewers with the most significant consequences in the event of failure, taking into account whether the cost of post-failure rehabilitation exceeded that of planned renewal.
| 1984-1994 | 261 DASs covering strategic sewers in systems serving populations over 10,000 |
| 1990-1995 | 80 Rural Asset Management Plan Studies (RAMPS) covering strategic sewers in all areas not included in the DAS studies. |
| 1995-(2005) | 341 Drainage Area Maintenance Studies (DAMS) revisiting both the DAS and RAMPS studies. |
Waterfield
Farm and one short section (about 50m) in Beauvale Road, between manholes 291 and 292. The combined DAS/RAMPS studies took 11 years to assess just STW's strategic sewers, which were about 15% of the total. On a pro-rata basis it would take over 70 years to cover the whole network, even if this were a cost-effective method of managing the sewerage system.
Valley
District Council as a senior engineering technician from January 1988 to April 1990; MDC as a team leadersewerage strategy from April 1990 to April 2000 and STW as a senior modeller in the asset planning and investment department from April 2000 to March 2001.
watercourses.
visit
British
Coal's
records office at Edwinstowe House (which covered the north Nottinghamshire area) to take tracings of the mining plans. This would provide a first point of reference if any problems were notified and would enable MDC to consider whether
coal
mining subsidence was a possible cause.
authority's
liability to restore sewers which had suffered reduced gradient damage. The compensating
authority
would not accept any responsibility for remedial works which provided invert levels or gradients better than the 1957 profiles. A 1957 profile calculated the notional effect of mining on the sewer. It was done by using formulae and guidance contained in the Subsidence Engineers Handbook ("SEH"), which was prepared by the NCB. Whilst an engineering background was necessary to use it, the SEH did not require specialist knowledge of mining. Mr Draper did not hold any ground engineering or geotechnical qualifications, but he had applied the principles contained in the SEH. The engineer looked at the depth, width, thickness and direction of a mining panel (based solely on the information obtained from Edwinstowe House) and applied this to the formulae. It was not precise. No account would be taken of overlying ground conditions. Its purpose was to provide a starting point to begin to appreciate the effect of the subsidence on the sewer and the likely remedial costs. It was never used to predict any areas of actual subsidence damage.
coal
mining damage, but if damage were found it would be mentioned in the structural analysis section of the report.
Coal
began rejecting claims on the basis that the damage had not been discovered within six years of the particular mining taking place. In an effort to counter such rejections, in 1985/86 MDC began serving damage notices for the entire lengths of sewer that had been undermined by a particular mining panel. MDC would consider the mining information obtained from NCB against the sewer records and would serve damage notices on British
Coal
for all the sewers within that panel of extraction. This was done because British
Coal
considered that damage had occurred on the date that the panel was extracted. As the sewers were buried, damage would not become apparent for some time and this procedure was designed to prevent such rejections. There was no particular science to this approach, but following service of the damage notice the condition of the sewers referred to on the damage notice and/or the accompanying plan would have been investigated. British
Coal
did not like this policy.
coal
mining from the NCB's offices. He rejected the suggestion that their mapping of the location of mining activity, together with their knowledge that mining was taking place, enabled them to predict where subsidence damage might occur. Their job was to react to incidents that were notified to them, usually by members of the public. They did not have a budget for or the manpower to carry out surveying exercises of those extensive parts of their administrative area which were being undermined. They all knew that mining was taking place in the area, but the
visits
to the NCB provided the information to assess the possible causes of problems once they had occurred.
Coal's
post-1982 workings lying within the eastern division boundary, which incorporated the Nottingham, Sherwood and Leicester districts. STW did not ask WA to go back further than 1982. Secondly, to advise STW about any future workings by British
Coal
which might affect their strategic installations. The maps were a record document, whilst the reports provided STW with WA's analysis of the identified mining circumstances relating to the strategic installations. WA's brief specifically referred to the installations marked by STW, which initially did not include any sewerage systems within the eastern division. Subsequently, STW included a few strategic sewerage systems on their master plans, but these did not include the subject sewers.
volume
of mining information. It concluded that, of the 511 strategic installations identified by STW, and of the 400km of large diameter
water
pipelines, there were 153 installations and 71 pipelines which in WA's opinion lay within influencing distance of mining.
Coal,
WA would advise STW on the claim if asked to do so. In 1993 the geographical extent of WA's brief was extended to cover the northern division (including Stoke-on-
Trent,
Derby, Leicestershire and north Derbyshire) and the southern division (Warwickshire). The nature of the brief remained the same.
visited
British
Coal
headquarters at Edwinstowe, Mansfield, to collect data and to identify the progress of workings. WA obtained details about future mining from RJB Mining (UK)
Ltd
and
Coal
Investments
Ltd,
who were the principal licensed operators within the areas under consideration. At no time did WA's brief extend to a consideration of sewers in general or the subject sewers in particular. The only sewers considered by WA were pressurised sewage rising mains, which were considered by STW to be strategic installations. WA were issued with a total of 30 briefs from STW, of which 15 were in relation to the original 1988 report and subsequent annual updates. The remainder were to provide specific advice relating to the assessment of liability for damage, the anticipated impact of future mining and other miscellaneous matters.
Coal's
costs for subsidence were escalating rapidly. In an attempt to control them they rejected many claims, mainly on the grounds of limitation and STW felt that there had been a change in the way their claims were being dealt with.
various
British
coalfields
over the last 30 years.
coal
mining during their lifetime. The most recent panels of mining underlay or crossed numerous previous areas of extraction. He identified the
coal
workings at each of the claim locations and made calculations of the amount and nature of the subsidence caused. In relation to
Waterfield
Farm he said that there were three relevant seams, the Top Hard, the Deep Soft and Low Main (Tupton), and there were 11 separate workings from the 1950s to 1985/87 that could have caused subsidence damage along particular sections of the sewer. Simply from a consideration of the most recent mining it was impossible to say how much subsidence, distortion and strains a pipe or culvert had been subjected to and whether the latest mining was likely to have caused structural damage or significant hydraulic impairment. His experience in preparing the evidence for this case had demonstrated just how difficult it was in the context of the multiplicity of mine workings in the Nottinghamshire
coalfield
to predict future subsidence from impending workings or to analyse past movements, even for a single specific location. It had also shown how wholly impractical it was for a utility company like STW with a network of sewers and pipes totalling ten of thousands of miles to consider in detail every potentially-affected sewer or pipe run for every new panel of
coal
working.
authority's
argument, in the case of just a few streets in the Beauvale Estate at Hucknall, STW or its forerunners would have had to carry out physical investigations to look for damage soon after mining in the 1950s, 1961, 1968, 1979, 1982 and 1983, when there were workings directly under some or all of the estate, and perhaps on a number of intermediate occasions when there were other workings close by. But the Beauvale Estate was just one tiny area in the whole
coalfield,
and the Nottinghamshire
coalfield
was just one of several within the territory of STW which had active collieries during the same period.
coalmines
operating within STW's territory. Each would have had, on average, two or three faces active at a particular time, and each panel would have taken 1½ to 2½ years to complete, so collectively the 42 collieries would have had, say, 50 panels starting and finishing in any one year. Assuming that the average depth of working was around 750m and the average area that might be affected by mining subsidence from a single panel was 250 hectares, then the 50 new panels would affect 12,500 hectares, ie 125 sq km of surface in a year.
coal
panel below an urban area, his figure of 250 hectares might contain over 50 km of sewers. Then considering the estimated 50 panels in a year at the 42 collieries throughout STW's territory, and assuming a density appropriate to mixed urban and rural land use, the affected 125 sq km would contain perhaps 875 km of sewers. He was not surprised, therefore, that STW had considered it was wholly impractical to make general physical investigations of its drainage systems in areas of active
coal
mining.
vicinity
of the
Waterfield
Farm sewer claim. But in about 1983, the date of the last mining in the Beauvale Road area, there were many more active collieries in STW's territory and therefore more faces and even more kilometres of potentially-affected sewers. Moreover in 1976/77, when the most recent mining took place in the neighbourhood of Greenwood Drive, there were still more active collieries and working faces. He concluded that at all material times, there was so much active mining in the Nottinghamshire
coalfield
and the other Midlands
coalfields
that it was altogether impractical for STW to have made speculative physical surveys of all sewer systems potentially affected by mining.
coal
compensating
authority,
specialists and academics, and even so the amount of time taken to prepare the models and run the programmes was disproportionate. Moreover the
coal
compensating
authority
and its agents had the basic information at their fingertips, whereas any surface property owner would have had to go searching for the information necessary to make subsidence estimates.
vary,
because every panel would have a different history in relation to previous nearby mining workings and there might be fewer or more extensive drainage networks in its locality. His best estimate of the time that would be required to make the analyses and report the findings was of the order of 5 to 8 days per panel, or the equivalent of say £3,000 to £5,000 in professional fees on top of the regular retainer work; there may have been upwards of 50
coal
panels to consider in the course of a year.
authority's
assertion that, since s 2 notices under the
Coal
Industry Act 1975 had been published for the general localities, STW should have been aware of the progress of mining operations in the locality. He said that the total history of mining subsequent to a sewer system's construction was relevant to whether the last phase of workings might have resulted in subsidence damage. In each of the three cases in question, however, much of the relevant mining pre-dated 1975 and therefore pre-dated any s 2 notices under the 1975 Act. Moreover, the s 2 notices covered such wide areas that they gave no practical indication of where the actual workings would take place. Even when an interested party made periodic
visits
to inspect plans of proposed workings, the general timing and layouts and actual panels of work
very
often did not follow the indicated programme.
authority
as being relevant to the three subject sewers was in fact caused by the same panel of mining, and the combination of mining circumstances and history that led to subsidence damage at those localities was distinctly different from those at each of the claim sites. There was no geotechnical or scientific reasons for supposing that, simply because mining damage had occurred elsewhere within a few hundred metres of a particular sewer or sewer network, a new panel of work in the same or another seam would be likely also to cause damage and therefore an investigatory survey should automatically be carried out.
coal
workings at the relevant time would make it yet more impractical to make such calculations.
authorities,
two of which Arnold UDC and Doncaster CBC regularly suffered sewer damage as a result of
coal
mining subsidence. Arnold UDC subsequently became part of Gedling BC, which is located within the same
coal
mining area of Nottinghamshire as the sewers.
water
companies. He said that the first
water
regulator (OFWAT) was appointed in 1989 following privatisation of the
water
and sewerage companies and introduced the concept of trends in serviceability to customers (and the environment) in 1994. Previously control had been by the appropriate government department.
water
companies had a statutory duty to maintain the condition of their asset base, condition and age were not seen as indicators of the need for capital investment by the regulator. The sole criterion was the ability of the asset to deliver future services (serviceability) to the customer. In Mr Read's experience the public in general showed little interest in sewers until they failed and interfered with normal life. It was the public's
views
and the level of charging which were critical in the decision making process concerning levels of expenditure.
water
companies. The recommended strategy was based on concentrating rehabilitation efforts on those sewers where collapse repairs would be
very
expensive or disruptive to the community at large the "critical sewers". Pre-emptive maintenance on these sewers would, it was claimed by the WRC, greatly reduce the risk of such failures occurring and could be shown to be cost-effective. The basic philosophy of the SRM strategy was to provide an acceptable service at lowest cost. The WRC had suggested that the development of DASs as advocated in the SRM could result in sewer rehabilitation solutions significantly cheaper than those produced by more conventional or traditional planning methods, which were essentially reactive in nature and based on repairing the most structurally defective sewers as and when required, rather than concentrating on the critical sewers. The WRC accepted that failures would occur on the non-critical sewers, but the cost of rehabilitation of non-critical sewers following failure would be relatively cheap and non-disruptive. For the non-critical sewers the
view
was taken that the response to failure, or crisis maintenance, was the most cost-effective strategy to adopt. This policy was adopted by STW.
water
companies were involved in its development and it was an accepted standard throughout the industry. No
water
company was bound to follow the recommendations, but in
view
of its wide acceptance they would be unlikely and imprudent not to. In Mr Read's opinion, it was improbable that OFWAT would have countenanced any alternative.
view
of the nature of the area, it broke down the DASs into urban and rural areas, whilst still concentrating on the strategic or critical sewers. Of the three subject sewers, only
Waterfield
Farm was a critical sewer. It fell within the area covered by the Clipstone/Edwinstowe DAS, which was prepared by the claimant's local agent, MDC in 1991/92. By 1995 STW was the only
water
company in the UK to have completed a comprehensive assessment of its strategic sewer network in accordance with the recommendations of the SRM.
vertical
movement and, secondly, pipes could be fractured or joints opened as a result of compressive or tensile ground strain. In his experience, even in an active mining area, sewerage damage, particularly pipe fracture, did not always materialise. Sewer pipe damage was usually concentrated at pre-formed junctions and at manholes, owing to the extra stiffness there.
varied
from point to point and ranged from zero through maximum compression and tension and back to zero in only 100 metres. He would expect this to be a
very
difficult situation for even a mining expert to predict with any degree of accuracy. In his experience, fractured pipes as a result of mining operations were more common where the sewers were comparatively old. Pipe damage of this type might lead to significant infiltration of ground
water,
possibly increasing the cost of pumping (if this were involved) or ultimate treatment of the effluent. The pipes also had to deal with traffic
vibration,
seasonal swelling and contraction of clay soils factors which in themselves would not necessarily cause pipe failure, but which might do so if the sewer had previously been strained and disturbed by
coal
mining subsidence. In the areas with which this reference was concerned, sewer pipes were likely to have comprised a
variety
of different forms of construction.
coal
mining operations was in no way an exact science, because there were too many unknowns involved. Even if the discovery of damage led to an assessment that similar damage was likely as work on the same
coal
seams continued, that did not always happen in practice. It had been his direct experience that damage to sewers in one road was caused by a panel being worked, but that the same panel had not caused any noticeable damage to sewers in adjacent roads.
Coal
authority
alleged should have alerted STW to conduct further investigations themselves or take expert advice and which, had they done so, would have led them to identify the damage before the start of the six year period. In addition, in the case of the Greenwood Drive Claim, the
Coal
Authority
asserted that the area had been subject to a claim in 1979 which the NCB had accepted.
Waterfield
Farm
a. Newlands Road claim.
The damage was 1.8 km from the closest part of theWaterfield
Farm sewer, resulted from completely different mining and pre-dated the last mining to have undermined the
Waterfield
Farm sewer.
b. Mansfield Road claim.
The damage was 1.4 km fromWaterfield
Farm, resulted from completely different mining and pre-dated the last mining to have undermined
Waterfield
Farm.
c. Squires Lane claim.
The damage was 310 m fromWaterfield
Farm and resulted from completely different mining.
d. Forge Bridge claim
The damage was almost contiguous withWaterfield
Farm, although the damaged lengths were over 1 km apart. It resulted from completely different mining and its discovery resulted from the DAS which failed to discover damage to
Waterfield
Farm. This claim led to the investigations which located damage at
Waterfield
Farm but was within 6 years of the
Waterfield
Farm damage notice.
e. 15 inchwater
main claim.
The damage was 375m fromWaterfield
Farm, resulted from completely different mining and was on a pressure main, which behaved differently from a sewer.
f. 3 inchwater
main claim
The damage occurred within six years of theWaterfield
Farm damage notice, and was therefore irrelevant.
Beauvale Road
a. Tiverton Close claim.
The damage was 0.5 km from the closest part of the Beauvale Road sewer, resulted from completely different mining from that which caused the sewer damage at Beauvale Road and pre-dated the last mining to have undermined the Beauvale Road sewer.
b. Whyburn Lane No.4 reservoir claim
The damage was 0.4 km from the closest part of the Beauvale Road sewer, resulted from completely different mining and pre-dated the last mining to have undermined the Beauvale sewer.
c. Beauvale Estate claim
This was not a claim of which STW had any notice and BritishCoal
at that time had concluded that the damage was not the result of
coal
mining subsidence.
Greenwood Drive
a. West Kirkby claim
The previous claim did not cover the sewers in Lawrence Avenue and Greenwood Drive, which formed the current claim. It related to part of a sewerage system flowing in the opposite direction to the sewers in the Greenwood Drive claim. The damage which caused the current claim was either present at the time of the West Kirkby scheme or it was not. If it was present, it had not "occurred" within the meaning of the contemporary 1957 Act and therefore no claim was possible under that Act. The earliest time that a claim could have been made under the 1991 Act was 7 August 1989. The current damage notice was served within six years of that date.
Waterfield
Farm and Beauvale Road claims, STW had received no complaints or reports which would have alerted them to the possibility of the sewers being damaged. In cross-examination he accepted that, because of the absence of documents, it was not possible to say whether or not there had been any complaints. He also accepted that the 1991 DAS had referred to overloading of the sewer at
Waterfield
Farm and that a report on
Waterfield
Farm dated 23 March 1995 had referred to a "recurring problem caused by lack of capacity". He did not consider, however, that there was evidence that the problem was sufficiently serious to highlight the need for further investigations.
vicinity
of each. The damage notice on
Waterfield
Farm was submitted on 8 February 1994. Following correspondence and meetings between the parties the
Coal
Authority
wrote to STW on 9 March 1998 as follows:
"Further to our meeting held on 2 July 1997, as agreed please find the reason why theauthority
considers this claim statute barred. As explained in the meeting, the reason for rejection was that the
authority
consider
Severn
![]()
Trent
![]()
Water
to have reasonable knowledge of the mining six years prior to the submission of the damage notice. In reaching this conclusion consideration was given to the following facts:
The last mining to affect the upstream end of the sewer was in 1986 and the downstream end in 1982, some 8 and 12 years before submission of the damage notice. Investigations revealed that other claims in close proximity to this one had been submitted atvarious
times between 1982 to 1990, one claim for Squires Lane sewer was surveyed up to the manhole where this claim joins that run. Accordingly it is considered that
Severn
![]()
Trent
![]()
Water
were aware of mining in this area and, under the 1991 Act, as a person who would have had reasonable knowledge, should have investigated the sewers at that time, when any subsidence damage would have been evident."
Coal
Authority
wrote to STW rejecting the notice on 23 November 1995. The reasons given were:
"The area of Greenwood Drive was subject to a claim under the provisions of theCoal
Mining (Subsidence) Act 1957 and dated 04/07/1979. It was submitted by Ashfield District Council as agents to
Severn
![]()
Trent
![]()
Water.
![]()
The claim was discharged by the NationalCoal
Board by payment for repairs which were incorporated in the West Kirkby Subsidence Remedial Works Scheme.
The Mining Reports Office have indicated that no mine workings have affected the area of the claims since 1976.
TheCoal
![]()
Authority
is of the opinion that a reasonable body such as
Severn
![]()
Trent
![]()
Water
were aware of mine workings in the Greenwood Drive area in 1979 and any damage evident resultant from those workings would now be statute barred and therefore I am unable to recommend that any liability is accepted."
Coal
Authority
rejected the claim by a letter dated 19 June 1996 for the following reason:
"The investigations have confirmed that there is no evidence that anycoal
mining subsidence damage has occurred within the relevant limitation period for making claims. All mining activity in the
vicinity
of the sewer ceased in 1984."
Waterfield
Road claim. They were:
a. Newlands Road.
Claim on 10 April 1984. This related to the trunk sewer along Newlands Road, upstream of the current claim. BritishCoal
paid £38,395.73 in about March 1993. STW accepted this sum in settlement in February 1994.
b. Mansfield Road
Claim on 12 July 1984. A supporting drawing showed details of a survey which extended towards the trunk sewer and the current claim. Settled in February 1994 for £56,156.
c. Squires Lane
Claim on 14 October 1987. The sewer from Squires Lane connected with the trunk sewer at manhole 490 and the sewer length between manhole ("MH") 490 and MH 690 was surveyed for both claims. Settled in June 1994 at £52,020.10
d. Trunk Sewer between River Maun and Railway
Claim on 18 October 1990. Immediately downstream of the current claim and along the same trunk sewer. Settled in December 1993 at £68,086.43
e. 3 inch publicwater
main between Clipstone Pumping Station and
Waterfield
Farm.
Claim on 5 May 1988. Settled in September 1989 for £193.82.
f. 15 inch publicwater
main opposite Clipstone Pumping Station.
Claim on 20 April 1987. Settled in August 1987 at £4,098.02.
a. No.4 Reservoir, Whyburn Lane, Hucknall
Claim in 1982. Immediately adjacent to that part of current claim relating to Whyburn Lane. Claim accepted and damage to reservoir repaired.
b. Tiverton Close
Claims in March 1978, July 1980 and June 1981.
c. Beauvale Estate
Claim by ADC on 11 May 1987. An STW hydrologist attended a meeting with representatives of ADC at which mining subsidence was discussed as a possible cause.
d. ADC housing claims
A number of claims submitted. Limited information available, but repairs undertaken included drains.
e. Other claims to damaged kerbs and 4 inchwater
main at Common Lane. No detailed information available.
a. Greenwood Drive
Claim on 4 July 1979. This related to sewers for Greenwood Drive, Berry Avenue, Highfield Avenue and the rear of Willow Street. The damage notice did not exclude any specific lengths of sewer within the streets named.
b. Sewers in the Kirkby area. A letter dated 17 January 1979 from NCB to Ashfield DC accepted liability for a number of lengths of sewers in the Kirkby area. This related to the sewers on Berry Avenue/Greenwood Drive and Highfield Avenue/Greenwood Drive and also Station Road/Copeland Road, Banks Avenue, The Hill/Victoria
Road, Lime Tree Avenue and Chestnut Avenue.
c. West Kirkby Subsidence Remedial Work. A letter dated 5 April 1982 from Ashfield DC to NCB identified that works had commenced in relation to Berry Avenue, Greenwood Drive, Highfield Avenue and Lime Tree Avenue.
d. Main Drainage System to west of Kirkby. An NCB expenditure sheet dated November 1980 indicated that the main drainage system to the west of Kirkby had been investigated by the localauthority
as agent for STW.
e. Frederick Avenue. Damage notice dated 23 December 1976, relating also to Copeland Road and Sutton Road.
various
claims and actually duplicated part of the earlier claim for Greenwood Drive. A similar duplication had been identified in relation to Highfield Avenue, which had resulted in STW subsequently withdrawing that element of the current claim.
Victoria
Road were also surveyed up to the junction with Greenwood Drive. Mr Blackburn did not know why STW or the local
authority
had chosen to leave a small section of sewer between these points unchecked, especially as they were originally all on the same system.
Coal's
consultants had concluded there was no evidence that these had been caused by mining activities and, in respect of other claims at Common Lane, that it was possible that they too had been rejected because they were not mining related.
various
firms of geotechnical and mining consultants in South Africa, Australia, Sweden and the UK. In 1997 he joined WS Atkins Consultants as head of mining. In this position he has technical and management responsibility for the majority of Atkins's mining related projects, excluding the rehabilitation of former mining sites.
Coal
Industry Act, 1975, which required the NCB to give notice of its intentions three months before support was to be withdrawn; the 1957 Act, which provided statutory rights of repair or compensation to owners of land damaged by subsidence, no matter when mining had taken place, provided a damage notice was served within 2 months of the occurrence of damage, and the 1991 Act which introduced the six year time limit for claims.
authority
or their agents, and a remediation scheme prepared by the local
authority
engineers, possibly incorporating improvements to the system. When appropriate, the local
authority
would prepare a drawing identifying the 1957 profile of the sewer to establish the extent of the compensating
authority's
liability for remedial works. This drawing was prepared by the local
authority's
engineers, using the methods set out in the SEH.
authority.
After 1986, the compensating
authority
instructed British Mining Consultants Limited, acting as the compensating
authority's
agents, to investigate claims on their behalf. Those agents would
view
the CCTV tapes and carry out an assessment of the structural condition of the sewer, identifying the nature and extent of the damage likely to be due to mining subsidence. The agents would also obtain a mining subsidence report identifying the relevant workings and date of extraction. Subsidence calculations would then be carried out to determine the hydraulic damage to the sewer resulting from the identified workings. The compensating
authority
then advised STW or their agents whether or not they accepted liability and, if liability was accepted, made a provisional offer of compensation. If the
authority
were not considered to be liable, either because the damage was not subsidence related, or because the claim was considered to be out of time, a rejection notice would be issued. On receipt of a response from the compensating
authority,
STW's agents, or latterly STW's mining liaison officer would make a recommendation to STW to accept or reject the compensating
authority's
assessment. If liability was accepted, and remedial works were to be undertaken immediately, STW's agents would invite tenders for the remediation work and inform the compensating
authority
of the lowest tender. If the remedial works were to be deferred, compensation was based on an estimated cost for the works. The compensating
authority
would then issue a formal offer of compensation to STW accompanied by a form of discharge. Compensation was paid by the compensating
authority
on receipt of the signed form of discharge.
authority
and WA at which STW informed the
authority
of the appointment of WA and divisional mining liaison officers. At the meeting STW expressed the
view
that it would be preferable for STW and the compensating
authority
to work together in respect of mining subsidence matters rather than adopt an adversarial approach. It was agreed that Mr Hassall of WA and Mr Wenn of the compensating
authority
would set down guidelines for submission and acceptance of damage claims. Dr Carr outlined the principal elements of the guidelines. He did not know, however, the extent to which the guidelines had been implemented in practice.
velocity
and capacity. The change in gradient might be either adverse or favourable, depending on where in the system the subsidence occurred and the mining sequence. Furthermore, any change in gradient might be only temporary. The original gradient might be restored once the face had passed, or an adjacent panel had been extracted.
| Type of failure | Cause | Prevention |
| Beam fractures | Uneven resistance of foundations or soil movement, or differential settlement. Caused by mining in extreme cases of shallow workings. | Flexible joints and uniform hardness of foundation. |
| Pull fractures | Thermal or drying shrinkage of pipe, or site concrete, drying shrinkage or clay soil. Extension of ground through mining. | Flexible telescopic joints and gaps in site concrete and pipe joints. |
| Shear fractures | Differential settlement of wall relative to pipe or vice versa. Can be caused by fissuring in subsided ground. |
Flexible joints at a and b and making ab not more than 1m. |
| Thrust fractures | Restrained thermal or moisture expansion of pipe or compression due to subsidence. | Flexible telescopic joints. Spigot End not laid hard up in socket |
| Leverage fractures | Excessive angular displacements. Extreme cases of differential subsidence. | Flexible joints. Avoidance of excessive slew when laying. |
coal
panels. As the analysis was a manual process, it was less suitable for assessing the effects of more complex multi-panel layouts, although this was technically feasible. The SEH was, however, widely used as a standard against which other subsidence prediction methods were compared.
Waterfield
Farm claim related to a section of a 450mm diameter main trunk sewer which ran from Mansfield to the Edwinstowe sewage treatment works. It ran from MH 0201 to MH 8401. The total length of this section of the sewer was approximately 2535m. It was constructed in 1961. The damage comprised a reduction in gradients and/or backfills to some 1300m, structural damage, including 252 m of sewer with structural condition grade 3, and evidence of pulled joints generally.
various
facts which he considered might have been observable or ascertainable in relation to the damage to the
various
sewers. Firstly, the s 2 notices, which were dated 20 January 1983 (
Waterfield
Farm) and 12 February 1976 (Beauvale Estate, Lawrence Avenue and Greenwood Drive). Those provided notice that mining operations were planned in the general area. To identify what infrastructure might be affected by the planned operations, STW's agents regularly inspected the large scale plans for each colliery at the relevant area headquarters of the compensating
authority.
Waterfield
Farm, 1977 in the case of Greenwood Drive, 1982 in the case of Beauvale Road and Beauvale Crescent and 1984 in the case of the Whyburn Lane sewers), evidence of subsidence damage would have been observed. He accepted, however, that in
view
of their cost such surveys would only have been undertaken if there were reasonable grounds to suspect that damage had occurred.
Waterfield
Farm only started in March 1995. However, the first complaint listed related to flooding of a field and commented that this was a "recurring problems caused by lack of capacity". He therefore inferred that STW or its agents had received previous (undisclosed) complaints.
vicinity
of
Waterfield
Farm: Mansfield Road and Newlands Road, Clipstone; Squires Lane, Old Clipstone; River Maun (Forge Bridge); a burst 15 inch
water
main and a burst 3 inch
water
main. Dr Carr said it was apparent from this table that workings in the Deep Soft and High Hazles seams were instrumental in causing damage in the majority of the previous claims in the area, particularly those in the immediate
vicinity
of the sewer. Although the damage that was the subject of the
various
claims was not necessarily caused solely by these panels, nevertheless it was the extraction of these panels that triggered the claims. In particular, the claim for the damage to the 3 inch main in 1988 was attributed to the Deep Soft 103's panel, the same panel that was primarily responsible for the damage to the
Waterfield
Farm sewer.
vicinity
of Lawrence Avenue and Greenwood Drive, and to the West Kirkby Subsidence Remediation Scheme. He considered that three panels in the Second
Waterloo
scheme were probably responsible for all the claims in the
vicinity
of Greenwood Drive. In his opinion, if all the sewers likely to be affected by these three panels had been investigated at the time of the other claims, the damage to the subject sewers could have been identified in or about 1980.
vicinity
of Beauvale Road: Tiverton Close and Hucknall No 4 reservoir, Whyburn Lane. He did not consider two other claims which had been referred to in the
Coal
Authority's
pleadings, namely the Beauvale Estate and 24 Beauvale Road, were relevant, since the former was not caused by mining activity and the latter did not relate to any of STW's assets. He said that it was apparent from the table that the panels that were responsible for the damage to the Hucknall No 4 reservoir were two of the same panels that were responsible for the damage to the subject sewers. Therefore, had the sewers affected by those panels been investigated at the time of the Hucknall No 4 reservoir claim, the damage to the subject sewers would have been identified at that time.
"(a) Identify panels which had been worked during the preceding year;
a. identify the zone of influence around that year's mining in respect of each panel (based on 0.7 x depth);
b. identify one or more sewers within each panel most likely to be adversely affected by subsidence (generally those crossing the downstream rib side of the panel);
c. determine the pre-and post-subsidence profile of the sewer by reference to the SEH;
d. estimate the maximum anticipated ground strain induced by each panel by reference to the SEH."
Waterloo
seam during the period 1972 to 1977. He also considered that STW and their agents were aware that these panels had resulted in subsidence damage to sewers in the immediate
vicinity
of the subject sewers; that the West Kirkby Subsidence Remediation Scheme had been implemented during 1978/9 to make good some of the resulting damage, and that further damage notices had been submitted in 1979 and 1980 in relation to other sewers undermined by the same panel. In his opinion, by 1980 there were sufficient grounds to suspect that damage had occurred to the subject sewers to warrant investigation of the Lawrence Avenue and Greenwood Drive sewers without recourse to expert advice.
authority
would meet the cost of surveys where subsidence damage was identified and half of the cost where it was not, he accepted that this statement had been based on a recommendation in the code of practice. In fact, the evidence of Mr Loy and Mr Blackburn was that in practice the compensating
authority
only contributed to the cost of surveys where damage was discovered. He also agreed that he had not carried out an exercise along the lines he had suggested; that the prediction exercise he had done using the SWIFT programme could not have been used to predict damage in 1988 or 1989, and that its use would have cost about £5,000 for every km of sewer.
Waterfield
Farm prior to March 1995.
coal
seam (as opposed to a particular panel in a particular seam) would not have given a reliable indication of likely damage in a different seam.
various
local
authorities
between 1974 and 1990, working in main drainage departments dealing with the design and maintenance of public sewer systems. All these local
authorities
had sewerage agency agreements with their respective
water
authorities.
He joined WS Atkins Consultants in 1990 as a senior engineer. In that capacity he had been responsible for the design of new and rehabilitation of existing sewerage systems, mainly located within the
Severn
Trent
administrative region. He was currently leading a team of engineers dealing with a
variety
of sewerage infrastructure projects, including several in former
coal
mining areas.
Water
Act 1973. This structure included local
authority
agents, with staff who would have had local knowledge of both mining activity and the operational history of the sewerage network in their areas. During the 1970s and 1980s STW were actively involved with the formulation of
water
industry good practice regarding the strategic inspection and management of sewerage systems in England and Wales. In line with industry good practice they commenced their programme of DASs in or around 1982, but studies in the claim areas were not undertaken until the 1990s.
various
other sewers in the
vicinity
of each of the reference sewers. He said that, in the Baulker Lane area, near
Waterfield
Farm, the original section of the trunk sewer between MH 0401 and MH 1502 had been replaced with larger diameter pipes at some time during, or more probably after, the period 1977 to 1986. He considered that these works, even if not carried out as a result of subsidence damage, would have exposed evidence of mining subsidence affecting the claim sewer. In his opinion this section of public sewer would have been constructed either by STW or their agent, NSDC.
water
companies and sewerage agents had been followed, he would have expected improved communication within STW to have been part of this control. Even without the increased control recommended by the Commission, it was reasonable to expect the constituent parts of STW to exchange information about matters which were likely to affect their assets. With mining subsidence in particular, where different assets were affected by the same physical conditions, there was clearly a common interest for all parts of STW with responsibilities for those assets to exchange information.
water
main did not necessarily mean that a sewer immediately adjacent to it would be damaged. He also accepted that the Monopolies and Merger Commission's report did not say that more money should be spent on the sewerage system.
Conclusions
The general approach to the identification of damage
water
companies in the United Kingdom. Mr Read described it as the standard reference work for industry professionals involved in the maintenance and rehabilitation of sewers and an accepted standard throughout the industry. Mr Darling contended that STW was wrong to suggest that what it had done should be judged against the industry standard set by the SRM. It was, he said, a self-serving document prepared for the industry by the industry. We do not accept this contention. There is nothing to suggest to us that the SRM was prepared with any other objective than that of establishing what it was reasonable for sewerage
authorities
to do for the purpose of managing their sewers.
very
expensive or disruptive to the community at large. These were termed the "critical sewers". The WRC claimed that pre-emptive maintenance on these sewers would greatly reduce the risk of such failures occurring and could be shown to be cost-effective. The basic philosophy of the SRM strategy was to provide an acceptable service at least cost. The WRC suggested that the development of drainage area plans as advocated in the SRM could result in sewer rehabilitation solutions significantly cheaper than those produced by more conventional or traditional planning methods, which were essentially reactive in nature and based on repairing the most structurally defective sewers as and when required rather than concentrating on the critical sewers. The WRC accepted that failures would nevertheless occur in the non-critical sewers, but the cost of rehabilitation of such sewers following failure would be relatively cheap and non-disruptive. The SRM took the
view
that for the non-critical sewers the response to failure, or crisis maintenance as it could be described, was the most cost-effective strategy to adopt.
view
of the nature of the area it broke down the DASs into urban and rural areas, whilst still concentrating on the strategic or critical sewers. Of the three sewers with which we are concerned, only
Waterfield
Farm is a critical sewer. It falls within the area covered by the Clipstone/Edwinstowe DAS, which was prepared by the claimant's local agent, MDC, in 1991/92.
various
sewers were to be the subject of a DAS, whether mining was taking or had taken place in the area. It was in our
view
appropriate to take this factor into account, as sewers in such areas are more likely to be in need of work. Despite the relatively small proportion of STW's repair costs that is attributable to mining damage the potentiality of mining subsidence to cause damage is obvious
authority
that STW should have carried out studies aimed at predicting where damage caused by mining was likely to have occurred and to use this as the basis for deciding which lengths of sewer should be investigated. There are, in our
view,
two reasons why such an approach would not be justified. The first is that such studies could at best predict the amount of subsidence which would have affected specific locations on the lengths of sewer and, as Dr Carr agreed, to predict subsidence is not the same as predicting damage since the subsidence will not necessarily have caused damage. Secondly, and of fundamental importance, is that the more accurate the prediction the more it will cost to produce because of the detail of the studies required, and the less accurate the prediction the less its utility in assisting in the identification of damage. Dr Carr referred to two different methods of predicting subsidence affecting sewers. The first used a computer programme called SWIFT but, as he accepted, this was not available until 1989, and there was no evidence to show what could have been predicted using programmes available in the 1980s. Any such analysis would be location-specific and extremely time-consuming to carry out so that, given the great lengths of the sewers in the area, the cost of any extensive study would be huge; and, unless the study were extensive, its predictions would be of little help. In any event, it appears that different experts using different computer programmes could reach widely differing predictions of subsidence, as the three different predictions of Dr Carr, Mr Knipe and Binnie and Partners at a single location at Beauvale Road demonstrate.
view
of Mr Knipe that the information required for such an approach would be too extensive, the calculations needed would be too complex and imprecise and the lengths of sewer involved would be too great for such an approach to be practicable. In the area under consideration the calculations are in any event made extremely difficult both by the local geological conditions and because of the multiplicity of seams and panels. Dr Carr produced no worked example of how such a predictive exercise would perform, and it does not surprise us that prediction of subsidence is not a method used by sewerage and
water
authorities
in their approach to maintenance.
authority
paid an uplift of only 15% on the cost of repairs any system of investigation that had much less than a 100% success rate would be unlikely to be cost-effective. The extent of reimbursement that STW might achieve can only, in our
view,
be relevant to whether it should have gone further in its investigations than it was reasonable for it to go for the purposes of the proper management of its sewers. Such reimbursement would not be any guide to the extent of the investigations that it would be reasonable for it carry out as a sewerage undertaker to ensure that its system was kept in proper repair. We accept that the prospective recovery from the
authority
was not sufficient to justify going beyond the investigations carried out in its DASs in respect of its critical sewers.
authority
to adopt in relation to the identification of damage is that recommended by the SRM a system of planned maintenance involving DASs for the critical sewers and a reactive response to manifestations of possible damage to both critical and other sewers. In determining the timing and priority of DASs and the response to complaints and evidence of flooding the fact that the an area has been the subject of mining is likely to be a material consideration.
Complaints and the absence of complaints
view
it is appropriate that they should do so. The reliance on complaints was explained by Mr Harding in opening as follows:
"The public will complain to the localauthority,
saying: 'There is a terrible smell of the drains round here. Can you come and inspect?' What has generally happened is that the sewage is not flowing through the sewer any more and that may be because there is a lack of gradient or back fall or the sewer has been damaged, and that could be by mining or it could be by other causes, tree roots or other works or simply the age of the sewer, or it could be blocked by some material that has got into the pipe.
So there might be smells resulting from that or alternatively that can also lead to flooding of property, because if the sewer is blocked and more sewerage is coming down, ultimately, particularly if there is heavy rain, then the sewer can back up either in houses or on to land, and then that will be again reported to the localauthority.
![]()
The localauthority
will come out to investigate. What they will do is clear the blockage. They will jet out what is there, because it is usually a blockage that they will find. If they see there is damage or there is obviously a hydraulic problem, then they will report that and come back and carry out surveys, but what generally happens is that they clear the incident and leave it and wait to see what happens, because the majority of incidents will be isolated ones and will not run on, or if they do, it will not be for a number of years, but if they encounter a number of complaints about a particular area, then they will go and carry out more detailed investigations as to what is the cause of those problems, and that will involve them carrying out a CCTV and levelling surveys."
authority
will also react to damage as and when it is identified. For non-critical sewers, on the other hand, the recommended approach by the SRM is a purely reactive one. We have concluded that such an approach is one that a reasonable undertaker would have adopted. It requires that the undertaker should receive complaints about the possible malfunctioning of sewers and should then investigate them. Such investigations ought in our
view
undoubtedly to include, where appropriate, CCTV inspections. Mr Loy regarded the pilot CCTV survey carried out in the Beauvale Road and Greenwood Drive area as unsuccessful, not only because the compensating
authority
had not accepted liability for the damage that had been discovered, but also because it had discovered damage in only 17% of the sewers surveyed and the compensating
authority
would only therefore reimburse 17% of the study cost of £2,440. The implication is that STW ought not to carry out such surveys where the prospective discovery of damage is only of this order. We cannot accept this. As we have said, what it is reasonable for a sewerage
authority
to do to ensure that its system is suitably maintained cannot depend on the amount that it may hope to recover from the
Coal
Authority.
The pilot study discovered damage that was in need of repair, and on that account was successful. Moreover the remedial cost of the repairs as set out in the points of claim was £110,000, so that the cost of the study was small in relation to this.
Waterfield
Farm and up to August 1989 in the case of Beauvale Road and Greenwood Drive) STW is unable to locate its records of complaints. Mr Loy said that prior to 1989/90 STW operated what was referred to as the CRIES system, with a manual recording of complaints. It was replaced by a computer-based system, SCARS 1. There was a suggestion on STW's part, but with no reliable evidence to support it, that the changeover from CRIES to SCARS 1 occurred in 1986. Mr Loy said that some SCARS 1 data was available but that it was not complete.
authority's
investigative efforts. He agreed with the
view
expressed by Mr Engledow that, given the extent of the recorded problems with the sewers in the DAS area, the lack of complaints before those recorded in the 1990s was surprising. In relation to Beauvale Road and Greenwood Drive, Mr Read was asked in cross-examination why the CCTV survey that located the damage could not have been carried out earlier.
"Q. Now can we then, please, go forward to Beauvale and Greenwood? Now, I wonder if I can just try to cut matters short. We know that both of these areas of problem were discovered from a pilot CCTV survey.
A. Yes.
Q. Is there any reason, so far as you are concerned, technically why such a survey could not have been carried out years earlier?
A. Technically, no.
Q. Now you nevertheless think that it was not reasonable, or nor reasonably necessary, to carry out such an investigation?
A. We are dealing with Greenwood Drive and Beauvale Road together, are we?
Q. They were dealt with by the same pilot CCTV survey.
A. Precisely, so we are dealing with them. The answer to the question is no, because there is no evidence of complaints.
Q. Essentially the debate between you and I comes down, does it not, to the presence of or absence of complaints?
A. Precisely."
Waterfield
Farm
Waterfield
Farm sewer is a critical sewer and thus, on the basis of the SRM strategy, which STW adopted, in our
view
reasonably, it fell to be investigated as part of the programme of DASs that STW put in hand in 1984. Given our conclusion that it was appropriate for STW to follow the SRM strategy, two questions arise: firstly, whether the priority accorded to the Clipstone/Edwinstowe area was reasonable (and, if it ought reasonably to have been carried out earlier than it was, whether the damage would have been discovered); and, secondly, if the priority was reasonable, or if the damage could not have reasonably have been discovered by an earlier DAS, whether complaints or reports of flooding ought to have caused STW to react by carrying out investigations (and, if so, whether such investigations would have identified the damage). We express the questions in this way, but it must be borne in mind that the onus in relation to them is, as we have concluded, on STW. It is for STW to show that it could not reasonably have acquired knowledge of the damage to the
Waterfield
Farm sewer before 8 February 1988.
Waterfield
Farm sewer has been affected by a large number of
coal
workings, most recently in 1985/86, and there is no dispute that this was ascertainable by STW. Neither party seeks to attribute the damage that the sewer has suffered to any particular workings. There is agreement that subsidence damage usually occurs within a short time of the withdrawal of support. The damage could have occurred, therefore, in 1986 or it could have occurred earlier. There is no dispute that previous claims had been made in the
Waterfield
Farm area, and these are identified above in the evidence of Mr Read. Flooding occurred and was recorded in the
vicinity
of the
Waterfield
Farm sewer in 1995 and it was recorded as being a recurrent problem. CCTV and levelling surveys, if carried out after the damage had occurred, would have identified the damage. All these matters, which we accept as being factually correct, are relied on by the compensating
authority
as showing that the damage was ascertainable by STW more than six years before the service of the damage notice.
authority's
contention that specific calculations of mining subsidence should have been done and that a specially targeted survey should have been carried out. The
Waterfield
Farm trunk sewer, however, was a critical sewer and as such it fell to be investigated as part of STW's DASs. It is clear that a DAS carried out before February 1988 and after the 1985/86 workings could have been expected to identify any damage caused by those or earlier workings. The question, as we have said, is whether the priority accorded to the Clipstone/Edwinstowe area was reasonable. The evidence on this is exiguous. In evidence in chief Mr Loy said simply:
"When deciding when thevarious
sewers were to be the subject of a DAS, we gave priority to areas where we knew mining was taking or had taken place, as these were more likely to be in need of work."
vicinity
of the
Waterfield
Farm sewer, that also would have been relevant. How those matters would have impinged on the priority given to Clipstone/Edwinstowe DAS we do not know. STW has failed to show that the DAS ought not reasonably to have been carried out before 8 February 1988.
view
have been the approach that a reasonable sewerage
authority
would have taken before the publication of the SRM recommendations. We have no evidence as to the approach of STW before then, however, so that, for that earlier period also STW has failed to show that the DAS ought not reasonably to have been carried out.
Waterfield
Farm. This was because the subject sewer crossed over farmland and some of the manholes were buried under fields and were difficult to locate. When, however, NSDC were subsequently instructed to carry out levelling surveys in this area, they were able to locate the relevant manholes and discover evidence suggesting that the sewer had moved. No evidence was adduced by STW to explain why the manholes in question, which were able to be located in late 1993, could not have been located at an earlier date, and in our judgment a properly conducted DAS would have done so. We find that STW have failed to establish that a DAS carried out before 1988 would not have identified the damage.
coal
mining subsidence claims and no experience of
water
authorities'
funding, to say what STW ought reasonably to have done. Indeed Mr Harding had been at pains to stress that in relation to these matters Mr Engledow was not an expert and was not in a position to comment on the issue of whether STW had acted reasonably. We attach no significance to the answer on which Mr Harding sought to rely.
Waterfield
Road claim, therefore, STW has failed to show that it was reasonable for the DAS not to have been carried out before 1988 or that, if it had been, the damage would not have been discovered. In
view
of this conclusion the second question we identified whether complaints or reports of flooding ought to have caused STW to react by carrying out investigations (and, if so, whether such investigations would have identified the damage) does not arise.
Beauvale Road and Greenwood Drive
authority
would seek to interpret the limitation provision in the 1991 Act. The area was chosen for study as a mining "hot-spot". It was an area in which it was known that damage to sewers had been caused by mining subsidence and there was a likelihood that further damage would be found.
authority
reacting to damage as and when it occurs. We have concluded that such an approach is one that a reasonable undertaker would have adopted. It requires that the undertaker should receive complaints about the possible malfunctioning of sewers and should then investigate them appropriately. We have referred above to the issue of complaints and the absence of complaints. Mr Read, in evidence we have recorded, said that the reason he did not think that Beauvale Road and Greenwood Drive should have been investigated earlier was the absence of complaints prior to 1989/90. Mr Harding submitted that, had there been any complaints before those for which records existed, it must be presumed that an
authority
such as Ashfield District Council would have investigated the sewer, found the damage and submitted a damage notice, as they had previously done on numerous occasions. The absence of a damage notice was therefore strong evidence that there were no complaints that should have led STW to find the damage any earlier than it did.
authority
are of significance, the fact is, as STW have put it, that this area is a mining "hot-spot" so that the reactive approach to any complaints ought to have been conditioned by this consideration.
authority's
favour. We determine that STW did have the knowledge, as defined by section 3(4) of the 1991 Act, required for founding the claim more than six years before the claim notice was given. That determination disposes of the references, which are accordingly dismissed. A letter on costs accompanies this decision, which will take effect when, but not until the question of costs is decided.
Dated 14 April 2004
George Bartlett QC, President
N J Rose, FRICS
Addendum on costs
authority
ask for their costs. They say that they have been successful in the three references which went to a hearing as well as in the two which were abandoned at an earlier stage. They submit that no special reason exists for departing from the principle that costs should follow the event. Although the Tribunal rejected the compensating
authority's
case that STW should have carried out predictive studies and targeted investigations, that finding should not prevent the normal order for costs being made, for two reasons. Firstly, the issue did not cause any significant increase in the cost or duration of the proceedings and was not raised unreasonably or improperly. Secondly, the expert evidence, in relation to mining and its timing and effects, and in relation to sewerage systems and their operation, was necessary in any event for the proper determination of the references. The claimant has not gained by pursuing the references and there are no matters of conduct which have any significant bearing upon the issue of costs.
authority
on matters that were unpleaded and were only contained in supporting evidence and that the Tribunal expressly or impliedly rejected the compensating
authority's
pleaded case on the three issues referred to in its replies to further and better particulars, as summarised in paragraph 10 of the decision. STW says that the compensating
authority
should pay its costs of and occasioned by those issues in all five references. STW also argues that the compensating
authority's
failure to serve a proper and detailed defence, and to accept STW's repeated suggestion that it should drop its reliance on the section 2 notices had increased costs unnecessarily, and that its dismissive response to a request that it should amend its pleadings "borders on the arrogant".
view
no need for the oral hearing on the matter that has been suggested by STW.
Ltd
v
Secretary of State for Transport Local Government and the Regions [2003] 1 P & CR 324, the Civil Procedure Rules, and the observations by Lord Woolf MR in AEI
Ltd
v
Phonographic Performance
Ltd
[1999] 1 WLR 1507 at 1522-3, in which he emphasised that under the CPR the following the event principle is a starting point from which the court can readily depart. Reference is also made to Johnsey Estates
Ltd
v
Secretary of State for the Environment, Transport and the Regions [2001] EWCA Civ 535, in which Chadwick LJ, identifying the principles applicable in that case, said at para 21 that a judge should consider making different orders for costs where a party has been successful on one issue but unsuccessful on another and may, in that event, make an order for costs against the party who has been generally successful in the litigation.
authority's
conduct, either in relation to their approach to the pleadings or otherwise, warrants a departure from the general rule, under which, as the successful party, they ought to receive their costs. The issues raised in the pleadings and the disclosure that was sought as a result were not, in our
view,
unjustifiably extensive, given the nature of the claims and the fact that the application of section 3 of the 1991 Act to damage to sewers was an important and previously unexplored matter. STW are wrong in suggesting that we impliedly rejected as factually irrelevant to the issue all the incidences of damage in adjacent lengths of sewers. We did not do so, as appears from paragraphs 157 and 164 of our decision. Nor do we consider that the fact that the issues on which the compensating
authority
succeeded were not pleaded but arose in the course of the hearing is sufficient justification for depriving the
authority
of all or part of their costs.
authority
to adopt to the identification of damage we found in favour of STW and against the compensating
authority,
and we think that this should be reflected in the order that we make. The evidence relating to predictive studies and targeted investigations, involving as it did both mining and sewerage experts, occupied a significant part of the hearing. Taking into account both the compensating
authority's
failure on this issue and the time spent in exploring it, therefore, we consider that the compensating
authority
should receive only fifty per cent of their costs.
authority
of their costs.
authority's
costs of references LCA/35/1999 and LCA/37/ 1999 and one half of the compensating
authority's costs of references LCA/34/1999, LCA/36/1999 and LCA/38/1999. In default of agreement such costs are to be the subject of a detailed assessment by the Registrar on the standard basis.
Dated 16 June 2004
George Bartlett QC, President
N J Rose FRICS