QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
HEARD![]() |
Claimant |
|
- and - |
||
![]() BROADLAND DISTRICT COUNCIL ![]() SOUTH NORFOLK DISTRICT COUNCIL![]() NORWICH CITY COUNCIL![]() |
Defendants |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Mr W Upton (instructed by Sharpe Pritchard Solicitors) for the Defendants
Hearing dates: 6th and 7th December 2011
____________________
Crown Copyright ©
MR JUSTICE OUSELEY:
Heard
, challenges the adoption by the Defendants of their Joint Core Strategy on 22 March 2011, a development plan document created under the Planning and Compulsory Purchase Act 2004 for their areas. The challenge is brought under s113 of that Act, on the grounds that the Joint Core Strategy, JCS, was not within the powers of the Act, or there had been a procedural failing which had prejudiced the Claimant.
district councils
:
Broadland
DC and South Norfolk DC which surround Norwich City
Council
's area to the north and south respectively. The three have co-operated to produce a Joint Core Strategy for their areas. This includes the Norwich Policy Area, NPA, which covers the whole of the City
Council
's area and, putting it very broadly, the parts of the other two
Councils
' areas which lie closer to the City.
Heard
is a resident in that area north east of Norwich which is earmarked for major growth in the JCS. He is the chairman of an action group, Stop Norwich Urbanisation, SNUB. Although opposed to urbanisation generally, Mr
Heard
contends that the JCS is unlawful because the Strategic Environmental Assessment, SEA, which the
Councils
had undertaken, did not comply with two requirements: first, that it explain which reasonable alternatives to urban growth in the North East Growth Triangle they had selected to examine and why, and second, that it examine reasonable alternatives in the same depth as the preferred option which emerged. It was not said that the examination of the preferred option was itself inadequate, nor that changes in circumstance required a further examination of previously discarded alternatives. The Defendants contended that the work they had done was sufficient for these purposes.
Council
, and that although the JCS supported and in some ways promoted the NDR, it was not for it to assess it or to consider alternatives to it. The County
Council
was part of the informal Greater Norwich Development Partnership, GNDP, with the three
District Councils
.
The legislative framework
"In requiring the likely significant environmental effects of reasonable alternatives to be identified, described and evaluated, the Directive makes no distinction between the assessment requirements for the drafted plan or programme and for the alternatives. The essential thing is that the likely significant effects of the plan or programme and the alternatives are identified, described and evaluated in a comparable way. The requirements in Article 5(2) concerning scope and level of detail for the information in the report apply to the assessment of alternatives as well. It is essential that the authority or parliament responsible for the adoption of the plan or programme as well as the authorities and the public consulted, are presented with an accurate picture of what reasonable alternatives there are and why they are not considered to be the best option. The information referred to in Annex I should thus be provided for the alternatives chosen."
District Council
of St Albans
v
Secretary of State for Communities and Local Government [2009] EWHC 1280 (Admin), Mitting J para 14.
v
Forest Heath
District Council
[2011] EWHC 606 (Admin), Collins J, paras 17 and 40.
"40. In my judgment, Mr Elvin is correct to submit that the final report accompanying the proposed Core Strategy to be put to the inspector was flawed. It was not possible for the consultees to know from it what were the reasons for rejecting any alternatives to the urban development where it was proposed or to know why the increase in the residential development made no difference. The previous reports did not properly give the necessary explanations and reasons and in any event were not sufficiently summarised nor were the relevant passages identified in the final report. There was thus a failure to comply with the requirements for the Directive and so relief must be given to the claimants."
The facts
Council
which bears statutory responsibility for the transportation strategy, and not the Defendants.
Council
consulted on various Norwich Area Transportation Strategy, NATS, options in 2003. An SEA was carried out in 2004 for the NATS, voluntarily since it preceded the coming into force of the Directive; it was not itself subject to public consultation. A number of options, sieved from a larger variety, were fully considered including three which involved differing lengths of NDR, and three which involved no NDR, but improved public transport and other measures to reduce car usage instead. The preferred strategy included what then was called the three quarter NDR; the NATS had been designed to help deliver the growth that would occur in the Norwich area with or without a supportive transport infrastructure, and to address the problems it would create. The NDR was identified as an important element to enable growth within and around Norwich; without it, developer led schemes to provide accessibility to individual developments would lead to a disjointed network. The NDR was "the only feasible solution for dealing with growth and transport problems and issues on a long-term basis."
Council
adopted its Second Local Transport Plan in 2006 as required by the Transport Act 2000. A Strategic Environmental Assessment was undertaken for this purpose, published in 2006, and summarised in the LTP itself. It assessed the overall environmental effect of the LTP, the impact of the two potential major schemes, one of which was the NDR, and the environmental effect of the LTP with and without those major schemes. An Environmental Report was consulted on with the Provisional LTP in 2005, but it did not deal with the NDR. The rather longer SEA of 2006, which was not itself consulted on, did not assess the LTP without the NDR alone, nor alternatives to the NDR. The LTP promoted the NDR as a major scheme, describing its purpose, advantages, position in the development plan framework, and its financing status.
district
totals conforming to that total for the NPA parts of the three involved here.
Councils
had begun work on their Joint Core Strategy. In November 2007, the
Councils
issued, for public consultation, an "Issues and Options" paper. This identified the housing requirements for the NPA in the then draft EEP. The three strategic options for dealing with the required growth were dispersing growth across a large number of small scale sites, medium concentration on large estate size sites of 15-3000 units, or Larger Scale Urban Extensions and new settlements in the range 5,000-10,000 dwellings. An initial assessment of the broad locations for major growth, including the north east sectors inside and outside the NDR, was appended; a full sustainability appraisal was promised at the preferred options stage, but early indications on a comparative basis were provided under the heading "Some issues relating to potential growth locations". Comments were sought on which broad strategy should be preferred, (Q11) and on the various major growth locations outlined, (Q12). Potential combinations for large scale growth were identified and comments sought as to which were preferred (Q13):
"As well as identifying smaller urban extensions and growth in villages, the main pattern of large-scale growth could be:
a) concentration on the north east and south west of Norwich and at Wymondham
b) as a) plus a fourth location for large scale growth
c) as a) plus two or more locations for medium scale growth
d) a different combination for major growth options
e) a more dispersed pattern of growth (perhaps an average of 1,500 dwellings in ten locations)."
"3.3.2 The Pre-Submission JCS sets out the GNDPs current preferred approach in a series of draft policies. These policies represent the GNDPs preferred options, which have been selected and refined following consultation on alternative options that has occurred in the past. In particular, options were published and consulted during the 'Issue and Options' consultation in 2007. All options presented in the Issues and Options consultation document were also subjected to SA to establish the relative merits of options in sustainability terms and inform the identification of preferred options. The findings of the Issues and Options SA were summaries in a brochure, which is available to download from the GNDP website.
3.3.3 Following the Issues and Options consultation the GNDP were able to identify many of their preferred options. However, it transpired that there was a need to consult further on options for the spatial approach to growth. Identification of a spatial approach to growth is the single most important decision to be made by the JCS, and the decision with the most wide ranging and potentially significant sustainability implications. The section below gives further details as to how the preferred approach was developed."
"Recommendations
- One key area of concern relates to whether the NDR, which is promoted through this Policy, would preclude sustainable patterns of travel and transport associated with the North East Growth Triangle. It will be of great importance to ensure that the NDR does not have this effect. It will be important to design in ambitious measures that encourage residents to meet more of their needs locally by sustainable modes of travel, and that also allow ease of access to Norwich by rapid public transport. When considering the necessity for the NDR it should be possible to assume minimal use of this road by residents of the Growth Area."
Broadland
DC adopted Proposals Map. The NDR "is recognised" in the EEP, is a major scheme in the Local Transport Plan and is in the Department of Transport's Development Pool. This policy was to become Policy 6 in the adopted JCS.
Councils
was published in February 2011, and concluded that the JCS was sound and in conformity with the EEP, but certain changes were required.
"It has been argued that a non-NDR package of NATS interventions has not been modelled and that this could conceivably produce a better overall solution. However, we are not convinced that such an option would be realistic and place weight on the DfT's favourable 'in principle' assessments and the judgements which led to the NDR's acceptance into 'Programme Entry' and the 'Development Pool', as discussed above."
"The AAP is the proper mechanism for carrying out the site-specific investigations, considering the alternatives and undertaking the public consultations necessary to establish the point at which non-delivery of the NDR may, or may not, become a 'showstopper' for further development in the growth triangle. The JCS should not go beyond its strategic role and fetter the necessary thorough investigation through the AAP by making premature commitments based on untested scenarios."
"Moreover, there are strong reasons to support the selection of this area as a location for a major urban extension. Fundamentally, if development is to take place at the overall scale proposed by the GNDP constituent authorities (which we have found sound), the pattern of small towns and villages inBroadlands
offers no realistic alternative 'dispersal' options capable of accommodating such numbers in ways likely to be sustainable and capable of respecting the characters of the host settlements. There is no evidence that Norwich could accommodate more than already reflected in the JCS account of existing commitments, and it appears (from our consideration of the South Norfolk options) that redistribution from the north of the NPA to south is not a viable option. Concentrating the proposed development at this major growth location is the most effective way of maximising its contribution to the NPA's sustainability and providing infrastructure economically."
"With regard to the North East Norwich growth triangle, we have already concurred with GNDP's judgement that from a relatively early stage in the evolution of the JCS there has been no reasonable sustainable alternative to a substantial urban extension in that location if this scale of growth is to be accommodated."
"We therefore conclude that South Norfolk's view that the JCS distribution represents the best overall 'political fit' is not inconsistent with judgements that it (a) represents the most appropriate plan when considered against the reasonable alternatives and (b) broadly fulfils GNDP's duty under S39 of the 2004 Act to exercise its DPD-making functions with the objective of contributing to the achievement of sustainable development."
"Our broad conclusion is that the major principles of NATS, as reflected in the JCS, represents a sound and sustainable transport strategy for the NPA. The implementation of these measures would enable the JCS to proceed with a pattern of growth which is justified, effective and consistent with national policy. This conclusion is subject to a number of necessary changes that have been discussed above. Together, these give the JCS greater resilience and effectiveness in the case of delay to, or non delivery of, the NDR by indicating a mechanism for transparently establishing the maximum extent to which development at the growth triangle could proceed before triggering the need for review of the JCS in that respect."
"5.1 The iterative plan making process set out above, informed by SA and consultation throughout, involved consideration of a number of reasonable alternatives.
5.2 This is particularly the case in relation to the spatial location of growth. At the Issues and Options stage ten potential growth options were put forward (plus brownfield sites in the city & suburbs). The Sustainability Appraisal was used to select options to take forward along with other evidence such as the water cycle study, public transport modelling and discussions with children's services.
5.3 The former preferred options document considered alternatives for growth options and area-wide policies. The alternatives were assessed and captured in the SA document and remain in it as evidence of considering reasonable alternatives.
5.4 The strategy submitted to the Secretary of State has a relatively concentrated pattern of growth inBroadland
, based on sustainable urban extensions and a more dispersed pattern in south Norfolk, with growth focussed on a number of existing settlements. Earlier plan drafts, supported by the SA, included options that had promoted a somewhat less dispersed pattern of growth in south Norfolk, with more limited development at Long Stratton.
5.5 Having regard to the technical evidence and public comment, the strategic preference of the GNDP was to promote growth in Long Stratton to achieve the consequent environmental improvements to the village.
5.6 The strategy has been adopted subsequent to a formal Examination in Public. The independent Inspectors concluded that the plan is sound, subject to a number of required changes. These changes have been incorporated into the adopted strategy."
Ground 1: SEA and alternatives
Councils
were not relying on the SA accompanying that paper. There was no analysis of why the alternatives selected at that stage only included ones with growth in the NEGT. The preferred option emerged from that process as a mixture of options 2 and 3, and the Environmental Report/SA of September 2009 dealt with it. There was no comparable assessment of reasonable alternatives considered by the three Defendants in it; the assessment of the options from the technical consultation paper was not done on the same basis as that of the preferred option. There was no explanation of the alternatives selected. It contained no cross-reference to any other paper where the identification and equivalent appraisal of alternatives could be found. Its summary was silent on that topic. It was possible that the options considered in the Issues and Options SA were reasonable options, even the only reasonable ones considered, but the SA did not say so, and it was not obvious why every combination of options included a north east sector, especially as the NDR on which it depended was uncertain. There was no comparable assessment of reasonable alternatives against the one preferred, nor could there be one until the preferred option had been identified. It was not his argument that there was some topic of assessment which those options had failed to consider, nor did that meet his argument.
Councils
, took me through the evolution of the planning documents, placing considerable weight on the April 2009 SA accompanying the public consultation document, and the September 2009 SA. It was for the three
Councils
to decide what were reasonable alternatives in the light of the SA scoping report of December 2007 and the requirements of the RSS. A range of reasonable alternatives had been identified and assessed, in a way appropriate for the level at which the JCS was operating in the plan-making hierarchy. Many alternatives supported by SNUB were not alternatives which conformed to the RSS, and so could not be considered as alternatives at all. A wide range of options had been assessed on a comparable basis; the later document of September did not have to continue to examine so wide a range as at earlier stages as the St Albans case held. There really was only one sensible way to meet the growth requirements, as the Inspectors found.
Conclusions on Ground 1
Councils
in February 2009 which led to the selection of the preferred option; it explains why it was preferred, and could contain information as to why the options examined had been selected. But that was not produced before me, and more importantly, it was not cross-referred to or publicly available as part of any SA. By the time of public consultation in March 2009, the preferred option had been selected.
Councils
intended as the fulfilment of their directive obligations. It would have been open to the
Councils
to describe here the process of selection of alternatives for examination at each stage. They could have done this by reference to earlier documents, if earlier documents had contained the required material. But the earlier documents do not contain the required information as to why the alternatives considered had been selected. If the outline of the reasons for the selection of alternatives was not dealt with in the earlier documents, the
Councils
had to provide them in this document. But that is missing from the SA.
Councils
' answer is to the Claimant's question: were the only alternatives it was thought reasonable to select ones involving development in the NEGT, and if so -in outline- why so, especially in view of the uncertainty over the NDR, and the importance attached to the NDR in achieving the JCS with development in the NEGT. The SA is wrong in saying that all the options in the "Issues and Options" paper were assessed.
Councils
, nor does the Inspectors' conclusion suffice to answer it.
Ground 2: the absence of an assessment of the NDR in the JCS SA
councils
to have regard to the LTP under regulation 15 (1)(b) and (c) of the Town and Country Planning (Local Development)(England) Regulations 2004 SI No. 2204. The RSS required regard to be had to the NATS. It did not require the NDR. Since the NDR was part of the JCS, and was said to be "promoted" through it, the JCS SA had to include an environmental assessment of the NDR. Instead, it had been taken as part of the baseline for the assessment of other development, colloquially as a given and not as a JCS proposal; Mr Doleman, a transportation planner with the County
Council
, made as much clear in his witness statement. The County
Council
was part of the GNDP, which as a partnership would promote the NDR, with the JCS supporting its provision and protecting its alignment, opposing inconsistent development. The NDR and NEGT went together: there may have been a case put forward by the County
Council
for the NDR without the NEGT, but there was no case for the full NEGT without the NDR. If the NDR were undesirable, it would affect the whole growth strategy, or at least the distribution of the major growth areas. The JCS protected an alignment corridor for the preferred three-quarter length NDR, yet that had not been assessed. However, his real concern was not with alternative alignments but with alternatives to the NDR altogether. Nothing in the Inspectors' report showed that there were no reasonable alternatives to the NDR. Given that there remains uncertainty over whether the NDR will be built, and the effect which that would have on the NEGT, there had to be alternatives to the NDR and NEGT. Those had not been considered.
Council
as highway and transportation authority. There were no reasonable alternatives for the
District Councils
to consider in promoting the JCS, since transportation was not within their statutory competence. So it had rightly been treated as part of the baseline, though the various levels of development in various locations on the NDR and on the roads leading to it would be relevant. Besides, the Inspectors had concluded that there was no reasonable alternative to the NDR. The reference in the SA of September 2009 to the NDR being promoted through the JCS was no more than a reference to its being relied on in the JCS. The detail of the route would be dealt with in the
Broadland
DC AAP.
Conclusions on ground 2
Councils
are in harmony on this issue.
Discretion
v
Secretary of State for the Environment [2000] UKHL 36, [2001] 2 AC 603 also showed that a disparate collection of documents, a paper chase through which the public might find its way, did not constitute substantial compliance with Directive requirements on environmental assessment. This case was to be distinguished from Younger Homes (Northern)
v
First secretary of State and Calderdale
District Council [2004] EWCA Civ 1060, Laws LJ at paras 42-47.
Conclusions on discretion